Light rail up north? Its iffy
Sound Transit officials express confidence, but funding is predicted to fall short by nearly $4 billion.
When voters two years ago approved a plan to expand the Sound Transit system, they said yes to a ballot measure that called for light rail to be extended to Lynnwood by 2023.
As it turns out, that plan for light rail could turn into more buses, a combination of buses and rail, or a cut-back version of any of those. In the worst extreme, considered unlikely, it could be nothing at all.
As Sound Transit officials begin to plan the expansion in detail, they say they have to study all the possibilities to be eligible for federal grants. This is especially important considering that the recession could cause Sound Transit to fall short of the cash it needs to carry out the plans.
Were always in the business of trying to build tomorrows system on todays finances and thats the challenge, said Everett City Councilman Paul Roberts, a member of the Sound Transit board of directors.
In 2008, voters approved a $17.9 billion plan to add to the regions mass transportation system with more trains and buses. The vote raised the sales taxes a half-cent per dollar in the Sound Transit service area in Snohomish, King and Pierce counties.
Tax revenue is already expected to fall $3.9 billion short by 2023.
The plan included an estimated $1.2 billion to $1.4 billion for light rail from Northgate to Lynnwood, and expansion of some bus service in Snohomish and north King counties. Some of that service already has been added, some is yet to come. Officials hope to have a plan for further study by next spring and a final plan in place by mid-2012.
The plan put before voters assumed a route from Northgate along I-5 to the Lynnwood Transit Center, with stations at 145th Street NE and 185th Street NE in King County and in Mountlake Terrace.
Some Sound Transit board members elected officials from cities and counties who make the final decisions for the agency say they still believe the final plan for Northgate to Lynnwood likely will include light rail.
Three elected officials represent Snohomish County on the agencys 18-member board. County Executive Aaron Reardon is the Sound Transit board chairman. He said he, too, understands the need to obtain federal grants.
Still, Im very confident the study will yield results that empirically show that the light rail that the voters voted for is indeed the best alternative and the best use for that corridor, he said.
A light-rail tunnel is currently under construction between downtown Seattle and the University District. In early 2009, Sound Transit received an $813 million federal grant, cutting the local cost of the three-mile, $1.9 billion tunnel nearly in half.
Light rail has been approved for the U-District to Northgate and planning is underway. The next segment on the way to Snohomish County is from Northgate to Lynnwood, referred to by Sound Transit as the north corridor.
In planning for this segment, in addition to what best moves riders, public opinion will be taken into account, officials say. A series of meetings was held early this month and written comments will be accepted through Wednesday.
The 2008 ballot measure read that Sound Transit would expand and coordinate light-rail, commuter rail, and (beginning 2009) express bus service, and improve access to transit facilities in King, Pierce and Snohomish Counties .
Its the text of an initiative, however, that carries the legal weight, said David Ammons, spokesman for the state secretary of states office.
He pointed out that past initiatives such as those raising teacher salaries, reducing class sizes and $30 car tabs have not always been carried out.
Recessions happen, he said. Even though voters said they want X, you may not be able to afford it.
If funding for the Sound Transit plan falls short, the text of the measure calls for the agencys board to build the part of the system it deems the most necessary and to adjust the plan as appropriate.
This fallback was not widely publicized during the campaign for the initiative. Nonetheless, the board has always ultimately had the decision-making power, Sound Transit spokesman Bruce Gray said.
It was put out there that this is the board-approved plan and this is the plan going forward. We also said were going to look for federal money for these projects and thats where we are today, he said.
Board members say that while obtaining grants is critical, the choice will likely be light rail.
I think were committed to build the system the voters asked us to build, Roberts said.
Mukilteo Mayor Joe Marine is Snohomish Countys other representative on the board. He said because light rail has already been approved to Northgate, its likely it will continue north.
When youre tying it into an existing system of light rail then it would have an advantage, he said. The mode of transportation is not likely to change to monorail, and buses are already operating on the route, he said.
Ammons of the secretary of states office said if light rail is not built, it could be challenged in court and at the ballot box.
The decision makers eventually will be on the ballot themselves, he said.
Bill Sheets: 425-339-3439; sheets@heraldnet.com.
As it turns out, that plan for light rail could turn into more buses, a combination of buses and rail, or a cut-back version of any of those. In the worst extreme, considered unlikely, it could be nothing at all.
As Sound Transit officials begin to plan the expansion in detail, they say they have to study all the possibilities to be eligible for federal grants. This is especially important considering that the recession could cause Sound Transit to fall short of the cash it needs to carry out the plans.
Were always in the business of trying to build tomorrows system on todays finances and thats the challenge, said Everett City Councilman Paul Roberts, a member of the Sound Transit board of directors.
In 2008, voters approved a $17.9 billion plan to add to the regions mass transportation system with more trains and buses. The vote raised the sales taxes a half-cent per dollar in the Sound Transit service area in Snohomish, King and Pierce counties.
Tax revenue is already expected to fall $3.9 billion short by 2023.
The plan included an estimated $1.2 billion to $1.4 billion for light rail from Northgate to Lynnwood, and expansion of some bus service in Snohomish and north King counties. Some of that service already has been added, some is yet to come. Officials hope to have a plan for further study by next spring and a final plan in place by mid-2012.
The plan put before voters assumed a route from Northgate along I-5 to the Lynnwood Transit Center, with stations at 145th Street NE and 185th Street NE in King County and in Mountlake Terrace.
Some Sound Transit board members elected officials from cities and counties who make the final decisions for the agency say they still believe the final plan for Northgate to Lynnwood likely will include light rail.
Three elected officials represent Snohomish County on the agencys 18-member board. County Executive Aaron Reardon is the Sound Transit board chairman. He said he, too, understands the need to obtain federal grants.
Still, Im very confident the study will yield results that empirically show that the light rail that the voters voted for is indeed the best alternative and the best use for that corridor, he said.
A light-rail tunnel is currently under construction between downtown Seattle and the University District. In early 2009, Sound Transit received an $813 million federal grant, cutting the local cost of the three-mile, $1.9 billion tunnel nearly in half.
Light rail has been approved for the U-District to Northgate and planning is underway. The next segment on the way to Snohomish County is from Northgate to Lynnwood, referred to by Sound Transit as the north corridor.
In planning for this segment, in addition to what best moves riders, public opinion will be taken into account, officials say. A series of meetings was held early this month and written comments will be accepted through Wednesday.
The 2008 ballot measure read that Sound Transit would expand and coordinate light-rail, commuter rail, and (beginning 2009) express bus service, and improve access to transit facilities in King, Pierce and Snohomish Counties .
Its the text of an initiative, however, that carries the legal weight, said David Ammons, spokesman for the state secretary of states office.
He pointed out that past initiatives such as those raising teacher salaries, reducing class sizes and $30 car tabs have not always been carried out.
Recessions happen, he said. Even though voters said they want X, you may not be able to afford it.
If funding for the Sound Transit plan falls short, the text of the measure calls for the agencys board to build the part of the system it deems the most necessary and to adjust the plan as appropriate.
This fallback was not widely publicized during the campaign for the initiative. Nonetheless, the board has always ultimately had the decision-making power, Sound Transit spokesman Bruce Gray said.
It was put out there that this is the board-approved plan and this is the plan going forward. We also said were going to look for federal money for these projects and thats where we are today, he said.
Board members say that while obtaining grants is critical, the choice will likely be light rail.
I think were committed to build the system the voters asked us to build, Roberts said.
Mukilteo Mayor Joe Marine is Snohomish Countys other representative on the board. He said because light rail has already been approved to Northgate, its likely it will continue north.
When youre tying it into an existing system of light rail then it would have an advantage, he said. The mode of transportation is not likely to change to monorail, and buses are already operating on the route, he said.
Ammons of the secretary of states office said if light rail is not built, it could be challenged in court and at the ballot box.
The decision makers eventually will be on the ballot themselves, he said.