Boeing 787 expected to be cleared to fly soon

WASHINGTON — Boeing’s 787 Dreamliner is nearing the end of a three-month grounding, with U.S. regulators ready to approve proposed changes to its lithium-ion batteries, according to people briefed on the decision.

The Federal Aviation Administration has agreed that a hardened case, added circuitry protection and a system to vent smoke will ensure safety, said the people, who asked not to be identified because they aren’t authorized to discuss the matter. It’s unclear when the decision will be announced, they said.

Ending the first U.S. grounding of an entire model in 34 years is pivotal for Boeing, which has had deliveries halted, and for the eight airlines with Dreamliners in their fleets. Regulators around the world followed the FAA’s Jan. 16 directive to park the planes after two incidents in which batteries smoldered and emitted fumes.

“It’s a very big deal,” said Michael Derchin, an analyst at CRT Capital Group in Stamford, Conn. “Everybody’s life has been on hold since it occurred.”

A Boeing spokeswoman, Yvonne Leach, declined to comment on the FAA’s pending moves.

The transport ministry in Japan, where two airlines have almost half the 49 Dreamliners in service, is in the final stage of its own probe, Shigeru Takano, the ministry’s director in charge of air transport safety, said at a briefing in Tokyo Friday.

Takano declined to comment on the FAA decision. Hiroharu Nakano, a spokesman for the battery supplier, GS Yuasa Corp. in Kyoto, Japan, also declined to comment.

Boeing is working to double 787 production in 2013 at assembly lines in Everett and North Charleston, S.C., to help fill a backlog of more than 800 orders for a plane whose list price starts at about $207 million. Eight carriers have received the jet since it began commercial service in late 2011 after more than three years of delays.

The FAA last grounded an entire model in 1979, when it revoked certification of the Douglas DC-10 after inspections discovered wing damage similar to what led to a crash in Chicago that killed 271 people. That order was lifted a month later.

The trigger for regulators’ actions in the Dreamliner case were battery faults in January that caused a fire in a Japan Airlines 787 in Boston and forced an emergency landing by an ANA plane in Japan days later.

While Boeing hasn’t been able to replicate the faults in those incidents, it has said the proposed fixes to the battery system would eliminate the possibility of a fire, prevent the spread of any overheating and vent any liquid or vapors outside the plane.

FAA Administrator Michael Huerta said at a Senate hearing April 16 that the planemaker has completed all the tests it agreed to conduct on the redesigned batteries. The power cells start a backup generator and are used when the plane is on the ground.

Dozens of completed Dreamliners remain parked around Boeing factories awaiting delivery, and Leach, the spokeswoman, said work on assembling the 115th plane is under way. Boeing kept production steady at five jets a month during the grounding.

Handing over jets to buyers is important for planemakers, because that’s the step at which airlines typically make bulk payments. Boeing is targeting a production increase to 10 Dreamliners a month by year’s end to whittle down the backlog.

Boeing’s own pilots have to first fly each 787 to test its systems, followed by the airlines’ pilots, before each delivery can be made. The FAA began allowing those so-called functional test check flights to resume yesterday, starting with a jet intended for ANA. The Japanese carrier was the first to fly the new model.

Japan Airlines said last month the cancellation of Dreamliner flights will cut operating profit by 1.1 billion yen ($11 million).

More in Herald Business Journal

Health-care consumers need to take the lead, so get smart

David Russian, CEO of Western Washington Medical Group, writes our third essay about fixing health care.

More business, more competition for Everett kidney dialysis center

Nonprofit Puget Sound Kidney Centers sees large for-profit competitors enter state market.

Molina Medical holds fall carnival for families in Everett

Molina Medical is hosting a free event for families in the Everett… Continue reading

Leadership Snohomish County celebrates 20 years of service

Leadership Snohomish County is celebrating its 20th anniversary. The organization was launched… Continue reading

Snohomish, Monroe manufacturers honored for innovation, excellence

Two Snohomish County companies have been honored with Manufacturing Excellence awards at… Continue reading

Remodeled home tours planned this weekend

This weekend, Edmonds-based Chermak Construction will participate in the 2017 Remodeled Homes… Continue reading

Barron Heating to celebrate anniversary at Marysville showroom

Barron Heating and Air Conditioning is celebrating its 45th anniversary from 10… Continue reading

Robots on Wall Street: Slow-footed regulators lose ground

Watchdogs have to figure out how to check computers running lightening-fast algorithms.

US budget deficit hits $666B, an $80B spike for the year

The deficit issue has largely fallen in prominence in Washington in recent years.

Most Read