Everett School District office cost jumps $535K

The cost of the Everett School District’s new administration building has increased by more than a half-million dollars, with the tab for construction now expected to hit $17.49 million.

The $535,392 in additional charges paid for two projects: digging out and taking away petroleum-contaminated soil found on the site as construction was under way and installing equipment to back up the school district’s power network and protect it against power surges, said Hal Beumel, director of facilities and planning.

The 66,365-square-foot building is scheduled to open in October. It is being built near the corner of Broadway and 41st Street SE in Everett.

The final cost of the building, including taxes and purchase of furniture and equipment, is expected to be at least $23.8 million.

The school district initially paid to have petroleum-contaminated soil removed from the site in the summer of 2009.

There were two gas stations and a fuel distribution center on the land from early 1960s through 1984, according to Beumel. The school district bought the site in 1986.

However, as construction on the new administration proceeded, four additional areas of soil contaminated with gasoline or oil were found. Removal of the contaminated soil took about two weeks.

“We had to clean that up, excavate it and haul it to an approved disposal site,” he said

In order to avoid delay, the soil had to be removed quickly, Beumel said.

The total cost to remove and dispose the contaminated soil was $242,539.

The power unit, which provides an uninterrupted power supply during power outages, cost $292,853. The project is being completed by Everett-based Valley Electric.

Administrative offices currently are split among several sites in the school district. The Longfellow building, a former elementary school built in 1911, was converted to an office building in 1970. A building at 4730 Colby Ave. is where Superintendent Gary Cohn and some other administrators have their offices and where school board meetings are held.

BNCC Inc. of Steilacoom is the contractor in charge of constructing the new administration building.

Sharon Salyer: 425-339-3486 or salyer@heraldnet.com.

More in Local News

Turkey talk: Kindergartners explain the Thanksgiving holiday

Our annual pilgrimage led us this year to Pathfinder Kindergarten Center in Everett.

Police locate suspect in Snohomish River after he fled

They used a thermal-imaging camera to locate the man in the water near Dagmars Marina.

Electrical fire on roof of Marysville school extinguished

There was no apparent structural damage to Cascade Elementary School.

As police closed in, 2 heavily armed pot-shop robbers fled

Cops surrounded the place in Mountlake Terrace. The suspects were tracked by dogs and apprehended nearby.

Hiker rescued on Boulder River trail after 15-foot fall

She was reported to have possible leg and rib fractures.

Alleged philanderer attacked with hammer near Everett

His girlfriend had accused him of cheating and allegedly called on another man to confront him.

State waging war with tenacious ivy, an invasive ‘bully’

The public is being asked to help with a study by collecting and sending in samples.

Front Porch

EVENTS Holiday lights parade in Monroe Monroe will host a Holiday Lights… Continue reading

Most Read