Highway 520 bridge design errors add to costs, delays

SEATTLE — State officials say construction delays and redesign costs could use up the Highway 520 bridge’s $100 million in reserves and eventually send the project another $128 million into the red, The Seattle Times reported in Saturday’s newspaper.

Most of the costs are related to design errors by the state Department of Transportation (DOT) that caused cracks in the first four giant pontoons. These required repairs, while others have been redesigned.

The estimate for when the floating bridge will be completed has also changed — from late 2004 to April 2016.

Information released Friday on the DOT website comes a month after new Transportation Secretary Lynn Peterson and 520 program administrator Julie Meredith held a news conference to reassure the public that the bridge project’s $250 million reserve fund is sound.

The state doesn’t have concrete plans for finding more money if the project requires it.

An Aug. 16 letter from Peterson instructs the 520 team to look for cost savings, negotiate aggressively and work with the state treasurer’s office on financing options.

DOT spokesman Lars Erickson said $228 million is the upper end of estimated cost overruns and the DOT will try to negotiate downward from there with contractors, including Kiewit, the primary partner for the floating section of the bridge.

The DOT has money to proceed through mid-2014 while it makes plans for the rest of the project.

State lawmakers failed to pass a new 10-year highway package before they went home this year, and the latest news makes that a tougher sell for DOT, said state Rep. Ed Orcutt of Kalama, the ranking Republican on the House Transportation Committee.

“If they want a gas tax, to build more projects, they’ve got to get things right. They’ve lost a lot of trust,” he said.

Orcutt said he doesn’t know how to react if the 520 fund “goes negative.” Conceivably, if some other project is done under budget, money could be shifted around, he said.

House Transportation Chairwoman Judy Clibborn, D-Mercer Island, tried to allocate at least $100 million more for 520 in the failed package in the spring, and could be expected to try again.

More in Local News

Spikes put end to ride from Seattle to Everett in stolen car

Two men were taken into custody at the bottom of Marine View Drive off I-5.

2 arrested after Marysville shooting leaves man brain dead

The victim had shown 1 suspect — a friend — a stack of money he won at the casino, police said.

Water to be shut off for some homes, districts next week

The pipe closing will affect mainly the Snohomish and Monroe areas.

Election results are finalized for school tax measures

More than 135,000 ballots were cast, a turnout of about 31 percent.

Section of W. Marine View Drive will be closed Saturday

A footbridge is being torn down between Everett Ave. and the Naval Station entrance.

Faith Calendar for Feb. 24 to March 10, 2018

EVENTS Purim banquet: Chabad Jewish Center of Snohomish County holds a “Purim… Continue reading

Everett council defers decision on methadone clinic zoning

Councilmembers asked to see more information on potential options in the weeks ahead.

Front Porch

A main strip of Everett’s waterfront… Continue reading

Two more suspects identified in shooting death of casino winner

The two, who have ties to Everett, Mount Vernon and Bellingham, remain at large.

Most Read