Treatment plant work to begin

EVERETT — Work crews building the Everett Water Pollution Control Facility on Smith Island will begin driving piles for three new buildings next week.

The work will take place Monday through Friday from 7 a.m. to 5 p.m. and is expected to take approximately 10 weeks to complete. There will also be heavy equipment moving around the work site during those hours.

This is the first phase of a series of upgrades to the north Everett treatment plant. The three structures being added to the plant’s mechanical treatment system will increase its capacity and keep it compliant with the National Pollutant Discharge Elimination System permit program.

The upgrade project has a $31 million price tag.

More in Local News

Everett district relents on eminent domain moving expenses

Homeowners near Bothell still must be out by April to make way for a planned new high school.

Their grown children died, but state law won’t let them sue

Families are seeking a change in the state’s limiting wrongful-death law.

Shock from WSU suicide ripples through Snohomish County

Roughly 1 in 10 seniors, sophomores and 8th-graders said they had attempted to take their own lives.

Marysville hit-and-run leaves man with broken bones

The state patrol has appealed for help solving an increasing number of hit-and-runs in the state.

$1,000 reward for info on who killed an eagle near Snohomish

After being shot, the raptor was treated at the Sarvey Wildlife Center but died overnight.

Woman confronts man leaving house with stolen item

“He swung at her with a crowbar, missing her.”

Police seek suspect in Wells Fargo bank robbery

He was described as white, in his 30s, heavyset, with blonde hair and a maroon sweatshirt.

Possible bobcat sighting keeps Snohomish students inside

The creature was spotted on the campus of Valley View Middle School around noon.

Stabbing in Everett follows dispute between brothers-in-law

The victim, 54, was hospitalized. The suspect, 29, had not been apprehended Thursday.

Most Read