Utility blames math error for Wanapum Dam crack

SPOKANE — Preliminary results of what caused a big crack in Wanapum Dam point to a mathematical error during design of the structure more than 50 years ago, the Grant County Public Utility District said Tuesday.

The underwater crack formed across a spillway pier of the huge dam and may have been exacerbated by a weak construction joint, the utility said.

The preliminary findings will be submitted to the utility’s Board of Consultants for final review.

The utility says a team of engineers discovered the mathematical error while examining the original design calculations of the Wanapum Dam spillway. When they recalculated the design formulas, they found that additional concrete and/or reinforced steel should have been used in the construction.

The dam is located on the Columbia River a few miles south of Vantage.

A crack that was 2 inches wide and 65 feet long was discovered in February on a spillway pier of the 8,000-foot dam. The reservoir behind the dam was lowered by 26 feet, relieving pressure and causing the crack to close itself.

The utility has been working for months to learn the cause of the crack, spokesman Thomas Stredwick said.

They believe the original designers of the dam mistakenly believed that the weight of the spillway’s concrete provided enough strength to resist the force of the water pushing against it, the utility said in a press release.

“Over time this weak point on spillway pier No. 4 succumbed to the force of the water pushing against it until after approximately 50 years of operation, the fracture formed,” the utility said.

Had engineers known of the miscalculation earlier, the spillway could have been reinforced, the utility said.

Investigators believe the crack may have originated a number of years ago and spread gradually, ultimately allowing enough water into the fracture to push the upper portion of the spillway pier out of place, revealing the problem.

Repairing the pier will require that additional steel be installed through the concrete structure and into the bedrock, the utility said.

The remaining 12 spillway piers have a design similar to the one that cracked, and steel reinforcement will likely be necessary there as well, the utility said.

The federal government must approve any repairs, the utility said.

Repairs are likely to take all summer, and the reservoir won’t be raised until the fourth quarter of the year, the utility said.

More in Local News

Shock from WSU suicide ripples through Snohomish County

Roughly 1 in 10 seniors, sophomores and 8th-graders said they had attempted to take their own lives.

$1,000 reward for info on who killed an eagle near Snohomish

After being shot, the raptor was treated at the Sarvey Wildlife Center but died overnight.

Woman confronts man leaving house with stolen item

“He swung at her with a crowbar, missing her.”

Police seek suspect in Wells Fargo bank robbery

He was described as white, in his 30s, heavyset, with blonde hair and a maroon sweatshirt.

Possible bobcat sighting keeps Snohomish students inside

The creature was spotted on the campus of Valley View Middle School around noon.

Stabbing in Everett follows dispute between brothers-in-law

The victim, 54, was hospitalized. The suspect, 29, had not been apprehended Thursday.

New leaders coming to county, state political parties

Hillary Moralez of Bothell takes over as chair for the Snohomish County Democratic Party.

Mom and brother turn in suspect in Stanwood robberies

The man is suspected of robbing the same gas station twice, and apologizing to the clerk afterward.

Derrick “Wiz” Crawford, 22, is a suspect in the homicide of his roommate. (Edmonds Police Department)
Roommate suspected in Edmonds killing found hiding in closet

Police had been searching for him for 10 days before locating him at a house in Everett.

Most Read