Boeing CEO isn’t sweating 787 delays

EVERETT — The recently announced delay of its 787 jet program doesn’t signal a significant flaw in the Boeing Co. or its Dreamliner, the company’s chief executive said Tuesday.

“I’m disappointed that we’ve had a stutter step,” said Boeing’s chief executive, Jim McNerney. “But it doesn’t fundamentally change my view of Boeing’s competitive position or where we’re going to end up.”

Speaking to investors at the Morgan Stanley conference in California, McNerney reiterated the message conveyed by Boeing officials last week: The company’s 787 jetliner will be delivered on time next May despite several months’ delay of the plane’s first flight. McNerney will check in personally on Boeing’s new baby, visiting the Puget Sound region today.

The planemaker’s CEO noted that problems with the 787’s software, supplied by Honeywell, could have been found days, perhaps a few weeks, sooner — still not enough time to make much of a difference in getting the Dreamliner in the air.

Muddled up work coming from Boeing’s major Dreamliner partners also played a part in pushing back the 787’s first flight, which kicks off the plane’s flight-test program.

Suppliers from around the world provide major sections of the Dreamliner, which goes through final assembly in Everett. Eventually, the main assemblies will be delivered complete with wiring. Several had to send their sections for the first airplane with temporary fasteners installed due to a shortage of fasteners.

“We discovered that things that were supposed to be in the plane weren’t,” McNerney said.

By pushing back the first flight, Boeing condensed its schedule for flight testing, when the company proves to aviation authorities that its jet is safe to fly. The company faces running an around-the-clock flight-test program if it intends to deliver the first Dreamliner to All Nippon Airways of Japan in May.

“Is there room for glitches at this point?” McNerney said. “No.”

However, Boeing originally planned for a shorter certification plan than announced, he said.

Looking forward, McNerney doesn’t expect the flight-test delay to dampen Boeing’s place in the market either with the 787 or with future aircraft. Rival Airbus has a mostly composite aircraft, like the 787, in the works. The A350 seems aimed more at Boeing’s 777 than at the 787, but Airbus’s new jet won’t be out until 2013.

In the meantime, Boeing will continue to hone its experience with using composites as company officials like McNerney ponder a response to the A350.

“We have a huge customer base that I think will work with us as we react,” he said.

McNerney’s comments came on the same day competitor Airbus released its commercial jet order and delivery tally through the first eight months of 2007.

Airbus had taken a lead in total orders over Boeing during the Paris Air Show but relinquished that lead in August. The European company lists 713 jet orders through the end of August, compared with 773 by Boeing over the same period.

Beside maintaining its sales lead of the more profitable widebody jets, Boeing also took the lead in airplane deliveries with 295 jets delivered over eight months compared with 294 jets delivered by Airbus.

Boeing’s stock price rose $2.11 Tuesday to close at $97.44.

Reporter Michelle Dunlop: 425-339-3454 or mdunlop@heraldnet.com.that were supposed to be in the plane weren’t and things that were (supposed to be there) weren’t,” McNerney said.

By pushing back the first flight, Boeing condensed its schedule for flight testing, when the company proves to aviation authorities that its jet is safe to fly. The company faces running an around-the-clock flight test program if it intends to deliver the first Dreamliner to All Nippon Airways of Japan in May.

“Is there room for glitches at this point?” McNerney said. “No.”

However, Boeing originally planned for a shorter certification plan than announced, he said.

Looking forward, McNerney doesn’t expect the flight test delay to dampen Boeing’s place in the market either with the 787 or with future aircraft. Rival Airbus has a mostly composite aircraft, like the 787, in the works. The A350 seems aimed more at Boeing’s 777 than at the 787, but Airbus’s new jet won’t be out until 2013.

In the meantime, Boeing will continue to hone its experience with using composites as company officials like McNerney ponder a response to the A350.

“We have a huge customer base that I think will work with us as we react,” he said.

McNerney’s comments came on the same day competitor Airbus released its commercial jet order and delivery tally through the first eight months of 2007.

Airbus had taken a lead in total orders over Boeing during the Paris Air Show but relinquished that lead in August. The European company lists 713 jet orders through the end of August, compared to 773 by Boeing over the same period.

Beside maintaining its sales lead of the more profitable widebody jets, Boeing also took the lead in airplane deliveries with 295 jets delivered over eight months compared to 294 jets delivered by Airbus.

Boeing’s stock price rose $2.11 Tuesday to close at $97.44.

Reporter Michelle Dunlop: 425-339-3454 or mdunlop@heraldnet.com

Talk to us

More in Herald Business Journal

Members of Gravitics' team and U.S. Rep. Rick Larsen stand in front of a mockup of a space module interior on Thursday, August 17, 2023 at Gravitics' Marysville facility. Left to right: Mark Tiner, government affairs representative; Jiral Shah, business development; U.S. Rep. Rick Larsen; Mike DeRosa, marketing; Scott Macklin, lead engineer. (Gravitics.)
Marysville startup prepares for space — the financial frontier

Gravitics is building space station module prototypes to one day house space travelers and researchers.

Orca Mobility designer Mike Lowell, left, and CEO Bill Messing at their office on Wednesday, Aug. 16, 2023 in Granite Falls, Washington. (Olivia Vanni / The Herald)
Could a Granite Falls startup’s three-wheeler revolutionize delivery?

Orca Mobility’s battery-powered, three-wheel truck is built on a motorcycle frame. Now, they aim to make it self-driving.

Catherine Robinweiler leads the class during a lab session at Edmonds College on April 29, 2021. (Kevin Clark / The Herald)
Grant aids apprenticeship program in Mukilteo and elsewhere

A $5.6 million U.S. Department of Labor grant will boost apprenticeships for special education teachers and nurses.

Peoples Bank is placing piggy banks with $30 around Washington starting Aug. 1.
(Peoples Bank)
Peoples Bank grant program seeks proposals from nonprofits

Peoples Bank offers up to $35,000 in Impact Grants aimed at helping communities. Applications due Sept. 15.

Workers build the first all-electric commuter plane, the Eviation Alice, at Eviation's plant on Wednesday, Sept. 8, 2021 in Arlington, Washington.  (Andy Bronson / The Herald)
Arlington’s Eviation selects Seattle firm to configure production plane

TLG Aerospace chosen to configure Eviation Aircraft’s all-electric commuter plane for mass production.

Jim Simpson leans on Blue Ray III, one of his designs, in his shop on Friday, August 25, 2023, in Clinton, Washington. (Ryan Berry / The Herald)
Whidbey Island master mechanic building dream car from “Speed Racer”

Jim Simpson, 68, of Clinton, is using his knowledge of sports cars to assemble his own Mach Five.

Inside the new Boeing 737 simulator at Simulation Flight in Mukilteo, Washington on Wednesday, Sept. 20, 2023. (Annie Barker / The Herald)
New Boeing 737 simulator takes ‘flight’ in Mukilteo

Pilots can test their flying skills or up their game at Simulation Flight in Mukilteo.

An Amazon worker transfers and organizes items at the new PAE2 Amazon Fulfillment Center on Thursday, Sept. 14, 2023, in Arlington, Washington. (Ryan Berry / The Herald)
Amazon cuts ribbon on colossal $355M fulfillment center in Arlington

At 2.8 million square feet, the facility is the largest of its kind in Washington. It can hold 40 million “units” of inventory.

A computer rendering of the North Creek Commerce Center industrial park in development at 18712 Bothell-Everett Highway. (Kidder Mathews)
Developer breaks ground on new Bothell industrial park

The North Creek Commerce Center on Bothell Everett Highway will provide warehouse and office space in three buildings.

Dan Bates / The Herald
Funko president, Brian Mariotti is excited about the growth that has led his company to need a 62,000 square foot facility in Lynnwood.
Photo Taken: 102312
Former Funko CEO resigns from the Everett company

Brian Mariotti resigned Sept. 1, six weeks after announcing he was taking a six-month sabbatical from the company.

Cash is used for a purchase at Molly Moon's Ice Cream in Edmonds, Washington on Wednesday, Aug. 30, 2023. (Annie Barker / The Herald)
Paper or plastic? Snohomish County may require businesses to take cash

County Council member Nate Nehring proposed an ordinance to ban cashless sales under $200. He hopes cities will follow suit.

A crowd begins to form before a large reception for the opening of Fisherman Jack’s at the Port of Everett on Wednesday, August 30, 2023, in Everett, Washington. (Ryan Berry / The Herald)
Seafood with a view: Fisherman Jack’s opens at Port of Everett

“The port is booming!” The new restaurant is the first to open on “restaurant row” at the port’s Waterfront Place.