Boeing tells airlines that 787 deliveries could slip

  • By Robert Wall Bloomberg News
  • Friday, February 8, 2013 1:46pm
  • Business

LONDON — Boeing has told airlines expecting to receive new 787 Dreamliners in coming months that deliveries may be late as regulators investigate overheating batteries that prompted the model’s grounding worldwide.

British tour operator Thomson Airways said it’s arranging to use other planes to serve Florida and Mexico if its first 787 is delayed beyond March. Norwegian Air Shuttle said the handover of an initial 787 in April may slide and that a second due in June may also be affected.

The 787 fleet has been sidelined since Jan. 16 following a lithium-ion battery fire on a Japan Airlines Co. plane in Boston and an emergency landing by an All Nippon Airways Co. plane in Japan. U.S. regulators said Thursday that Boeing can conduct test flights to help determine the cause, as evidence mounts that the battery may have to be redesigned.

“We have informed our customers expecting 787 deliveries in the near-term that those aircraft either have been or are at risk of being delayed,” the Chicago-based planemaker said in emailed comments. “Boeing deeply regrets the impact that recent events have had on the schedules of our customers and their passengers.”

Boeing has dropped 1.7 percent to $76.39 in New York since Jan. 6, the day before the Boston fire. The shares now trade at a 21 percent discount to European Aeronautic Defence &Space Co., the parent of competitor Airbus SAS. That compares with an 8 percent discount on a price-earnings basis at the end of last year.

Oslo-based Norwegian Air said in a statement that Boeing has not given it new handover dates or provided written confirmation of the holdups.

“Although a potential delay is completely out of our control, we would like to apologize in advance if the Dreamliner isn’t ready for Norwegian’s first long-haul flights,” Chief Executive Officer Bjorn Kjos said in a statement.

As one of Boeing’s biggest European customers, Norwegian said it expects the manufacturer to do “everything in its power” to get the 787 ready for delivery as soon as possible. To allow for new services to New York and Bangkok, the carrier said it will obtain alternative aircraft through a leasing company for as long as three months.

No provider has been selected, though the carrier’s first two 787s are owned by International Lease Finance Corp.

Thomson, a unit of Tui Travel, also said that Boeing has provided no new delivery dates.

London-based British Airways, which is due to start receiving Dreamliners from May, said in an email that discussions with Boeing continue. The carrier has 30 jets on order and said it’s committed to the model.

Boeing said Friday it’s staying in close communication with its customers as it works to develop a plan to resume the 787 pipeline, adding that it doesn’t discuss specific deliveries. European safety officials are due to visit Boeing next week to review progress of the probe.

National Transportation Safety Board Chairman Deborah Hersman said Thursday that U.S. regulators’ assumptions in certifying the 787’s lithium-ion batteries “must be reconsidered” after investigators found a short circuit in one cell set off a chain reaction that destroyed the unit.

What’s known so far suggests Boeing will have to come up with a new design, John Hansman, an aeronautics professor at the Massachusetts Institute of Technology, said in an interview.

“They weren’t supposed to have a fire, and they had a fire, so something went wrong,” Hansman said. “By doing it this way, the NTSB has forced Boeing to do something significant, to prove that they’re doing something different with the battery.”

Boeing’s problems with the lithium-ion unit have prompted Airbus to develop plans to jettison that power source in its new A350 model and use standard nickel-cadmium batteries instead, said two people familiar with the situation.

Should Toulouse, France-based Airbus opt to switch to a traditional battery now, the change could be accomplished with a few months’ delay, one of the people said, while waiting until Boeing resolves the 787 issue could put back the A350 significantly.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Business

A closing sign hangs above the entrance of the Big Lots at Evergreen and Madison on Monday, July 22, 2024, in Everett, Washington. (Ryan Berry / The Herald)
Big Lots announces it will shutter Everett and Lynnwood stores

The Marysville store will remain open for now. The retailer reported declining sales in the first quarter of the year.

George Montemor poses for a photo in front of his office in Lynnwood, Washington on Tuesday, July 30, 2024.  (Annie Barker / The Herald)
Despite high mortgage rates, Snohomish County home market still competitive

Snohomish County homes priced from $550K to $850K are pulling in multiple offers and selling quickly.

Henry M. Jackson High School’s robotic team, Jack in the Bot, shake hands at the 2024 Indiana Robotics Invitational.(Henry M. Jackson High School)
Mill Creek robotics team — Jack in the Bot — wins big

Henry M. Jackson High School students took first place at the Indiana Robotic Invitational for the second year in a row.

The computer science and robotics and artificial intelligence department faculty includes (left to right) faculty department head Allison Obourn; Dean Carey Schroyer; Ishaani Priyadarshini; ROBAI department head Sirine Maalej and Charlene Lugli. PHOTO: Arutyun Sargsyan / Edmonds College.
Edmonds College to offer 2 new four-year degree programs

The college is accepting applications for bachelor programs in computer science as well as robotics and artificial intelligence.

FILE — Boeing 737 MAX8 airplanes on the assembly line at the Boeing plant in Renton, Wash., on March 27, 2019. Boeing said on Wednesday, Feb. 21, 2024, that it was shaking up the leadership in its commercial airplanes unit after a harrowing incident last month during which a piece fell off a 737 Max 9 jet in flight. (Ruth Fremson/The New York Times)
Federal judge rejects Boeing’s guilty plea related to 737 Max crashes

The plea agreement included a fine of up to $487 million and three years of probation.

Neetha Hsu practices a command with Marley, left, and Andie Holsten practices with Oshie, right, during a puppy training class at The Everett Zoom Room in Everett, Washington on Wednesday, July 3, 2024. (Annie Barker / The Herald)
Tricks of the trade: New Everett dog training gym is a people-pleaser

Everett Zoom Room offers training for puppies, dogs and their owners: “We don’t train dogs, we train the people who love them.”

Andy Bronson/ The Herald 

Everett mayor Ray Stephenson looks over the city on Tuesday, Jan. 5, 2015 in Everett, Wa. Stephanson sees  Utah’s “housing first” model – dealing with homelessness first before tackling related issues – is one Everett and Snohomish County should adopt.

Local:issuesStephanson

Shot on: 1/5/16
Economic Alliance taps former Everett mayor as CEO

Ray Stephanson will serve as the interim leader of the Snohomish County group.

Molbak's Garden + Home in Woodinville, Washington will close on Jan. 28. (Photo courtesy of Molbak's)
After tumultuous year, Molbak’s is being demolished in Woodinville

The beloved garden store closed in January. And a fundraising initiative to revitalize the space fell short.

Everett Mayor Cassie Franklin, Advanced Manufacturing Skills Center executive director Larry Cluphf, Boeing Director of manufacturing and safety Cameron Myers, Edmonds College President Amit Singh, U.S. Rep. Rick Larsen, and Snohomish County Executive Dave Somers participate in a ribbon-cutting ceremony on Tuesday, July 2 celebrating the opening of a new fuselage training lab at Paine Field. Credit: Arutyun Sargsyan / Edmonds College
‘Magic happens’: Paine Field aerospace center dedicates new hands-on lab

Last month, Edmonds College officials cut the ribbon on a new training lab — a section of a 12-ton Boeing 767 tanker.

Gov. Jay Inslee presents CEO Fredrik Hellstrom with the Swedish flag during a grand opening ceremony for Sweden-based Echandia on Tuesday, July 30, 2024, in Marysville, Washington. (Ryan Berry / The Herald)
Swedish battery maker opens first U.S. facility in Marysville

Echandia’s marine battery systems power everything from tug boats to passenger and car ferries.

Helion Energy CEO and co-founder David Kirtley talks to Governor Jay Inslee about Trenta, Helion’s 6th fusion prototype, during a tour of their facility on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
State grants Everett-based Helion a fusion energy license

The permit allows Helion to use radioactive materials to operate the company’s fusion generator.

People walk past the new J.sweets storefront in Alderwood Mall on Thursday, July 25, 2024, in Lynnwood, Washington. (Olivia Vanni / The Herald)
New Japanese-style sweets shop to open in Lynnwood

J. Sweets, offering traditional Japanese and western style treats opens, could open by early August at the Alderwood mall.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.