Could Dakota Access pipeline move after permit is denied?

By Josh Funk

Associated Press

OMAHA, Neb. — The Army Corps of Engineers’ refusal to grant a permit for the Dakota Access oil pipeline to cross beneath the Missouri River has focused more attention on alternative routes, but several other options already have been considered and rejected as being more risky and expensive.

Some questions and answers about the Dakota Access pipeline and its route:

WHAT IS THE STATUS OF THE PIPELINE?

Nearly all of the 1,172-mile, $3.8 billion pipeline has been built by Dallas-based Energy Transfer Partners except for a mile-long section across federal land and beneath Lake Oahe, a Missouri River reservoir. But the project is in limbo because the Corps suggested Sunday that it now needs a more detailed environmental review than it received initially.

The pipeline is designed to carry oil from North Dakota through South Dakota and Iowa to a shipping point in Patoka, Illinois. State regulators in all four states approved the route through their territory. The proposed route skirts the Standing Rock Sioux Reservation that straddles the North Dakota-South Dakota border, and the tribe objects to the project, saying it could threaten drinking water and destroy sacred sites.

———

ARE THERE OTHER ROUTES AVAILABLE?

The company examined other routes when federal regulators conducted their initial environmental review. Energy Transfer Partners and the Corps agreed initially that the proposed route appeared to be the safest and most cost-effective path. The initial review looked at factors including the number of water crossings, how close the route came to homes and whether it crossed wetlands.

In North Dakota, the Dakota Access route parallels the existing Northern Border Pipeline, which carries natural gas from Canada across the Dakotas to the Chicago area. The Dakota Access pipeline would use a nearly identical route to cross Lake Oahe near the Standing Rock reservation.

One alternative the company considered called for the pipeline to cross the Missouri River north of Bismarck, about 50 miles upstream of the current path. That option was rejected because it was 10 miles longer and required more water and road crossings. It was also estimated to cost $22.6 million more than the current route.

DOES ANOTHER ROUTE HAVE SUPPORT?

Energy Transfer Partners doesn’t want to reroute the pipeline, which was originally expected to be completed before the end of this year. The company says delaying the project a year would cost it $1.4 billion in lost revenue. CEO Kelcy Warren told The Associated Press last month that the company doesn’t see another way to complete the project besides the current route.

Standing Rock Sioux Chairman Dave Archambault has said the tribe does not oppose oil pipelines if they do not threaten water sources, environmentally sensitive areas or sacred sites. He said a route that would follow existing west-east and north-south oil pipeline corridors that avoid Missouri River crossings would be acceptable to him.

HOW WILL THE TRUMP ADMINSTRATION AFFECT THE PROJECT?

President-elect Donald Trump wouldn’t say Monday whether he will try to overturn the permit decision that has delayed the pipeline. Trump has said he supports the pipeline, and he holds stock in Energy Transfer Partners. Trump spokesman Jason Miller said the new administration would review the Corps’ decision after it takes office in January.

WHAT ARE THE PIPELINE’S PROSPECTS?

Energy analyst Afolabi Ogunnaike with the Wood Mackenzie consulting firm said it appears to be a question of how long it takes for the project to regain approval and whether the route will have to be adjusted.

“Our expectation is that the Dakota Access pipeline will go forward. I think what’s unclear is the path it will take and when it will start up,” he said.

Talk to us

More in Herald Business Journal

Members of Gravitics' team and U.S. Rep. Rick Larsen stand in front of a mockup of a space module interior on Thursday, August 17, 2023 at Gravitics' Marysville facility. Left to right: Mark Tiner, government affairs representative; Jiral Shah, business development; U.S. Rep. Rick Larsen; Mike DeRosa, marketing; Scott Macklin, lead engineer. (Gravitics.)
Marysville startup prepares for space — the financial frontier

Gravitics is building space station module prototypes to one day house space travelers and researchers.

Orca Mobility designer Mike Lowell, left, and CEO Bill Messing at their office on Wednesday, Aug. 16, 2023 in Granite Falls, Washington. (Olivia Vanni / The Herald)
Could a Granite Falls startup’s three-wheeler revolutionize delivery?

Orca Mobility’s battery-powered, three-wheel truck is built on a motorcycle frame. Now, they aim to make it self-driving.

Catherine Robinweiler leads the class during a lab session at Edmonds College on April 29, 2021. (Kevin Clark / The Herald)
Grant aids apprenticeship program in Mukilteo and elsewhere

A $5.6 million U.S. Department of Labor grant will boost apprenticeships for special education teachers and nurses.

Peoples Bank is placing piggy banks with $30 around Washington starting Aug. 1.
(Peoples Bank)
Peoples Bank grant program seeks proposals from nonprofits

Peoples Bank offers up to $35,000 in Impact Grants aimed at helping communities. Applications due Sept. 15.

Workers build the first all-electric commuter plane, the Eviation Alice, at Eviation's plant on Wednesday, Sept. 8, 2021 in Arlington, Washington.  (Andy Bronson / The Herald)
Arlington’s Eviation selects Seattle firm to configure production plane

TLG Aerospace chosen to configure Eviation Aircraft’s all-electric commuter plane for mass production.

Jim Simpson leans on Blue Ray III, one of his designs, in his shop on Friday, August 25, 2023, in Clinton, Washington. (Ryan Berry / The Herald)
Whidbey Island master mechanic building dream car from “Speed Racer”

Jim Simpson, 68, of Clinton, is using his knowledge of sports cars to assemble his own Mach Five.

An Amazon worker transfers and organizes items at the new PAE2 Amazon Fulfillment Center on Thursday, Sept. 14, 2023, in Arlington, Washington. (Ryan Berry / The Herald)
Amazon cuts ribbon on colossal $355M fulfillment center in Arlington

At 2.8 million square feet, the facility is the largest of its kind in Washington. It can hold 40 million “units” of inventory.

A computer rendering of the North Creek Commerce Center industrial park in development at 18712 Bothell-Everett Highway. (Kidder Mathews)
Developer breaks ground on new Bothell industrial park

The North Creek Commerce Center on Bothell Everett Highway will provide warehouse and office space in three buildings.

Dan Bates / The Herald
Funko president, Brian Mariotti is excited about the growth that has led his company to need a 62,000 square foot facility in Lynnwood.
Photo Taken: 102312
Former Funko CEO resigns from the Everett company

Brian Mariotti resigned Sept. 1, six weeks after announcing he was taking a six-month sabbatical from the company.

Cash is used for a purchase at Molly Moon's Ice Cream in Edmonds, Washington on Wednesday, Aug. 30, 2023. (Annie Barker / The Herald)
Paper or plastic? Snohomish County may require businesses to take cash

County Council member Nate Nehring proposed an ordinance to ban cashless sales under $200. He hopes cities will follow suit.

A crowd begins to form before a large reception for the opening of Fisherman Jack’s at the Port of Everett on Wednesday, August 30, 2023, in Everett, Washington. (Ryan Berry / The Herald)
Seafood with a view: Fisherman Jack’s opens at Port of Everett

“The port is booming!” The new restaurant is the first to open on “restaurant row” at the port’s Waterfront Place.

Tanner Mock begins unwrapping new furniture that has been delivered on Thursday, Aug. 24, 2023 in Everett, Washington. (Olivia Vanni / The Herald)
In Everett, new look, new name for mainstay Behar’s Furniture

Conlin’s Furniture, based in South Dakota, bought the huge store and celebrates with a grand opening this week.