Change orders can turn remodel into money pit

  • By James and Morris Carey / The Carey Brothers
  • Wednesday, September 7, 2005 9:00pm
  • Life

The end of yet another summer is in sight. It’s a time when vacations become mere memories, kids head back to school, and home once again becomes the object of much attention.

In fact, after spring, fall is the second most popular season to remodel, as folks scurry to complete a much-needed kitchen or bath remodel in time for holiday entertaining.

Every homeowner who ventures into the world of home remodeling or repair must come to respect – and, when possible, avoid – four little words: “While you’re at it.”

Uttering these potentially explosive words can wreak havoc, bust budgets and turn once straightforward remodeling projects into monstrous catastrophes.

The context in which these words are spoken is what makes them dangerous. Typically, homeowners say these words to their contractor when requesting more work – “While you’re at it, why don’t you add a skylight?” In the construction industry, this request is known as a change order, two more words you must come to respect. Change orders are written addendums to the contract that specify a change or group of changes that the owner and the contractor agree upon.

A change here or there is certainly to be expected with most any remodel, no matter how well planned. Unfortunately, one while-you’re-at-it too many can trigger big delays and major overspending.

You may end up scrambling for cash to pay for the job and wondering if your home will ever be back to normal. Worse yet, you may spend too much money, making your investment nearly impossible to recoup.

Look at change orders – and the “while you’re at it” phrase – as remodeling credit cards. In fact, you can best understand the potential danger for any project-in-progress if you simply exchange the word change (in change order) to charge order.

Change orders cause delays, overspending, communication difficulties, and a host of other problems that can make an already difficult experience virtually unbearable.

Life would be a whole lot simpler for all parties if change orders didn’t enter the scheme of things; most reputable contractors that we know would be very happy if they never had to do a change order. They are the contractors who suggest the three P’s of remodeling: planning, planning and planning.

Many people mistakenly believe that planning begins with a floor plan and ends when the ink is dry on the contract. Actually, it is the period from the creation of the floor plan to the final preparation of the contract that is the most crucial time in the planning process. It is during this time that any questions, generalizations or confusion must be honed and resolved to ensure a successful remodeling adventure.

For instance, the contract for your new kitchen remodel may include labor to install a new ceramic tile floor along with an allowance for tile. Budget allowances are frequently used for items that have yet to be chosen such as appliances, tile, plumbing fixtures and flooring. Remember that an allowance should never be arbitrary and should always be accompanied by a sample of what can be purchased within the value being allowed.

Unprofessional contractors often include unrealistically low allowances. Their philosophy is that their pricing is then lower, which gives them an edge in getting the job. Sadly, after they have the job, they typically bury the consumer with change orders for upgrades.

Allowance items can count for a good chunk of a project, so make absolutely sure that you are satisfied with the appearance and quality of the products being used to establish the allowance. If you don’t, you have broken one of the fundamental rules of good planning and are headed down a dangerous path.

The contractor who suggests making decisions after the job has begun is committing one of remodeling’s greatest crimes. Often, in order to generate quick cash, he suggests that the job be started right away. When queried about finish selections, he invariably responds by suggesting that they can be “made along the way.” Avoid this contractor like the plague.

Whenever possible, make all selections before your remodeling project begins. This way, the contractor has a head start on ordering material and supplies, which contributes to an orderly, on time and in-budget project. Finding out – before your job begins – that the kitchen tile you want takes eight weeks to get is far easier than scrambling around looking for an alternative or, worse yet, stopping the project for eight weeks.

Having the information in advance gives you ample time to make choices without being under tremendous pressure. And, if necessary, you can wait to begin the project until all of the finishes that you want are available for prompt installation. After all, you don’t often remodel a bathroom or your kitchen, so you may as well have what you want.

For more home improvement tips and information from James and Morris Carey, visit their Web site at www.onthehouse.com or call 800-737-2474 Saturdays from 6 a.m. to 10 a.m. The Careys are also on KRKO (1380-AM) from 6 to 8 a.m. every Saturday.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Life

Arlo Frostad, 7, and his twin brother Harrison Frostad, walk through the fields of Roozengaarde outside of Mount Vernon, Washington during the Skagit Valley Tulip Festival on April 10, 2025. (Will Geschke / The Herald)
Stop and smell the flowers at Skagit Valley Tulip Festival

The largest tulip festival in North America features five gardens and runs through April.

Image from Canva.com
Say “I Do” to these stunning wedding venues

From rustic barns to elegant halls, discover where love stories in Snohomish County begin.

Grayson Bed and Breakfast (Photo courtesy of HD Estates and Grayson Bed and Breakfast)
The Grayson Bed and Breakfast: Where strangers become friends

A cozy retreat with scenic views and pet-friendly amenities just two miles from downtown Monroe.

Image from Prince Life Photography website.
Light, lens & love: These photographers bring the magic

Want to see who’s turning everyday moments into jaw-dropping memories? Let’s find out.

Small SUV Provides Big Time Value. Photo Provided by Chevrolet Newsroom
2025 Chevy Trax Activ Delivers Beyond Expectations

Sub-Compact SUV Surprises With Value And Features

Hai Viet Hong, center, performs with the Huong Viet Performing Arts Group during The Wendt Mayor’s Arts Awards on Thursday, April 10 in Everett, Washington. (Will Geschke / The Herald)
Everett artists celebrated with The Wendt Mayor’s Arts Awards

Award recipients included a former City Council member and the former publisher of My Everett News.

2025 Honda Civic Si sport-compact sedan (Provided by Honda).
2025 Honda Civic Si could be the darling of young drivers

Bold styling, fun-to-drive performance and reasonable pricing are part of the appeal.

The Tulalip Resort Casino. (Sue Misao / The Herald)
Check in, chill out, and wake up to comfort

These top Snohomish County stays are serving up relaxation, charm, and a touch of luxury

The 2025 Ford F-150 full-size pickup, in the XLT trim (Provided by Ford).
2025 Ford F-150 can do hard work but still be comfortable

The multifaceted popular pickup meets the needs of many different buyers.

Q4 55 e-tron quattro photo provided by Audi Media Center
2025 Audi Q4 55 e-tron SUV Makes Driving Electric Easier Than Ever

Upgrades Include Enhanced Power, Range, And Quicker Charging

Trailhunter photo provided by Toyota Newsroom
2025 Toyota Tacoma Trailhunter Designed For Off-Road

New Standard Equipment Adds Even More Functionality

The 2025 Infiniti QX80 full-size luxury SUV (Provided by Infiniti).
2025 Infiniti QX80 is a complete remodel

The full-size luxury SUV has fresh styling, advanced technology and a new twin-turbo V6 engine.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.