Federal memo criticizes nuclear cleanup contractor

YAKIMA — The company hired to design and build a massive plant at the nation’s most contaminated nuclear site should no longer have authority over its design, according to an internal U.S. Department of Energy memo released Tuesday.

The memo raises more questions about a waste treatment plant project long viewed as critical to ridding the Pacific Northwest of pollutants left from decades of weapons production for the nation’s nuclear arsenal, but one that has endured countless technical problems, delays and skyrocketing costs.

It also raises more concerns about the contractor at the center of the mix, Bechtel National Inc., which has come under fire in recent months from critics who say the company has suppressed employee concerns related to the plant’s safety and retaliated against whistleblowers.

The memo noted 34 instances where Bechtel National provided information that was incorrect, technically unfeasible or failed to provide the best value to the government, among other things, while designing the $12.3 billion plant at south-central Washington’s Hanford nuclear reservation.

“The behavior and performance of Bechtel Engineering places unnecessarily high risk that the WTP design will not be effectively completed,” Gary Brunson, the Energy Department’s engineering director assigned to the project, said of the waste treatment plant in a memo to top Energy Department managers Thursday.

The federal government created Hanford in the 1940s as part of the top-secret Manhattan Project to build the atomic bomb, and the site continued to produce plutonium for nuclear weapons through the Cold War. Today, it is the nation’s most contaminated nuclear site, with cleanup expected to last decades.

“This memo details exhaustive and disturbing evidence of why Bechtel should be terminated from this project and subject to an independent investigation,” Tom Carpenter, executive director of Hanford Challenge, a watchdog group that monitors cleanup efforts, said in a statement.

Bechtel project director Frank Russo said the findings highlight how the project — and the demands on the contractor — have changed in the past decade, rather than failures by the company.

Russo said the company and the Energy Department have hired hundreds of consultants who are experts in their fields to review calculations and design decisions for a project where the available information is constantly changing — including the cost and scope.

“If we ignore new information, we can finish it on price and we can finish it on schedule, and it would look like an ideal project that would make some people happy,” he said. “But if we review new information as it becomes available, it’s not failure.

“The reality is that this project has a huge element of science and a huge element of research involved before (the Energy Department) decides it has enough information to make a decision,” he said. “And when that happens, there will always be groups of people who believe it’s a wrong decision.”

Long considered the cornerstone of Hanford cleanup, the waste treatment plant is being built to convert millions of gallons of highly radioactive waste into a stable glass form. The waste is currently stored in underground tanks, many of which have leaked into the groundwater, threatening the neighboring Columbia River.

The plant’s unresolved issues include inadequate mixing of the waste, which could lead to a buildup of flammable gases or a small risk of creating a nuclear reaction inside the plant, and whether the rate of corrosion in piping and vessels will hold the radioactive waste. The issues are of particular concern because workers will be barred from entering highly radioactive areas of the plant — and repairing potential problems — once it is operating under the current design.

Design of the plant is 85 percent complete, and construction is more than 50 percent complete.

The plant had been scheduled to begin operating in 2019, but the Energy Department has said a new estimate on the plant’s start date and cost will be pushed off for a least a year while it embarks on additional tests to resolve those problems.

The Energy Department said in a statement Tuesday that it was reviewing Brunson’s memo and continues to work with Bechtel to address ongoing technical issues, though it continues to be frustrated with the lack of progress.

“Addressing these challenges effectively will require both additional work by the contractor, as well as improved oversight by the department,” the statement said. “It’s also important to note that the successful completion of this important project depends on employees continuing to be able to freely raise concerns.”

The federal government spends roughly $2 billion each year for Hanford cleanup, $690 million of which goes toward the plant.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Firefighters respond to a 911 call on July 16, 2024, in Mill Creek. Firefighters from South County Fire, Tulalip Bay Fire Department and Camano Island Fire and Rescue left Wednesday to help fight the LA fires. (Photo provided by South County Fire)
Help is on the way: Snohomish County firefighters en route to LA fires

The Los Angeles wildfires have caused at least 180,000 evacuations. The crews expect to arrive Friday.

x
Edmonds police shooting investigation includes possibility of gang violence

The 18-year-old victim remains in critical condition as of Friday morning.

The Everett Wastewater Treatment Plant along the Snohomish River. Thursday, June 16, 2022 in Everett. (Olivia Vanni / The Herald)
Everett council approves water, sewer rate increases

The 43% rise in combined water and sewer rates will pay for large infrastructure projects.

Robin Cain with 50 of her marathon medals hanging on a display board she made with her father on Thursday, Jan. 2, 2025 in Lake Stevens, Washington. (Olivia Vanni / The Herald)
Running a marathon is hard. She ran one in every state.

Robin Cain, of Lake Stevens, is one of only a few thousand people to ever achieve the feat.

People line up to grab food at the Everett Recovery Cafe on Wednesday, Dec. 4, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Coffee, meals and compassion are free at the Everett Recovery Cafe

The free, membership-based day center offers free coffee and meals and more importantly, camaraderie and recovery support.

Washington Gov. Jay Inslee proposed his final state budget on Tuesday. It calls for a new wealth tax, an increase in business taxes, along with some programs and a closure of a women’s prison. The plan will be a starting point for state lawmakers in the 2025 legislative session. (Jerry Cornfield / Washington State Standard)
Inslee proposes taxing the wealthy and businesses to close budget gap

His final spending plan calls for raising about $13 billion over four years from additional taxes. Republicans decry the approach.

Devani Padron, left, Daisy Ramos perform during dance class at Mari's Place Monday afternoon in Everett on July 13, 2016. (Kevin Clark / The Herald)
Mari’s Place helps children build confidence and design a better future

The Everett-based nonprofit offers free and low-cost classes in art, music, theater and dance for children ages 5 to 14.

The Everett Wastewater Treatment Plant along the Snohomish River on Thursday, June 16, 2022 in Everett, Washington. (Olivia Vanni / The Herald)
Everett water, sewer rates could jump 43% by 2028

The rate hikes would pay for improvements to the city’s sewer infrastructure.

Everett
Police believe Ebey Island murder suspect fled to Arizona

In April, prosecutors allege, Lucas Cartwright hit Clayton Perry with his car, killing him on the island near Everett.

The bond funded new track and field at Northshore Middle School on Thursday, Oct. 24, 2024 in Bothell, Washington. (Courtesy of Northshore School District)
Northshore School District bond improvements underway

The $425 million bond is funding new track and field complexes, playgrounds and phase one of two school replacements.

A person walks up 20th Street Southeast to look at the damage that closed the road on Wednesday, Nov. 20, 2024 in Lake Stevens, Washington. (Olivia Vanni / The Herald)
Snohomish County bomb cyclone victims can access federal disaster loans

The Small Business Administration will be at Evergreen State Fairgrounds through Jan. 31 for those impacted by November’s windstorm.

Ava Downing, left, and Harper Hinojosa, right, listen as the prosecution questions a witness during a mock trial at 10th Street Middle School on Friday, Jan. 10, 2025 in Marysville, Washington. (Olivia Vanni / The Herald)
Marysville middle school mock trial program in session

The program’s founder worries proposed cuts by Marysville School District could jeopardize successful curriculum.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.