Mukilteo ferry terminal takes shape and could open in 2020

The Whidbey Island ride might be short, but it’s the busiest for traffic — 2.3 million vehicles per year.

MUKILTEO — Unless you were right there, you wouldn’t know there was a big hoopla happening Wednesday morning in the cordoned-off construction zone of the new ferry terminal.

Amid anticipation, and with a dozen cameras trained, a crane slowly lifted the brace covering part of a spartan concrete wall at the water’s edge.

It revealed … more gray concrete.

It was a grand reveal, Washington State Ferries-style. Not HGTV-style.

The pretty stuff will come later.

“This is a significant starting milestone for the future ferry terminal,” said Nicole McIntosh, director of terminal engineering for Washington State Ferries.

The walls are part of the first level of the complex with holding lanes and an overhead bridge, which the existing terminal lacks.

McIntosh and others in hardhats stood on the foundation of what will be the elevator shaft, against the backdrop of ferries crisscrossing Puget Sound on the 20-minute Mukilteo-Clinton route from the old terminal one-third of a mile away.

There was no champagne or any appetizers at Wednesday’s event, though a construction worker on site offered to share his lunch. About 60 workers are often on hand in this stage of the job.

Construction workers begin taking off the outside wall braces of the terminal building at the site of the new Mukilteo ferry terminal. (Olivia Vanni / The Herald)

Construction workers begin taking off the outside wall braces of the terminal building at the site of the new Mukilteo ferry terminal. (Olivia Vanni / The Herald)

Construction on the passenger building, lanes, toll plaza and promenade was started earlier this year by IMCO General Construction, the lowest bidder, which landed the deal for $49.7 million.

“The whole project is now $167 million,” McIntosh said. “The target for opening is the fall of 2020.”

It hasn’t always been smooth sailing.

Terminal construction was delayed when the five bids for this major phase were rejected in August. State Department of Transportation engineers came up with an estimate of $65 million for work that includes upland buildings and the marine structures. The lowest contractor bid came in at $8 million over the estimate but was rejected for irregularities. The next was $18 million over budget. Bids went up from there.

After seeking feedback from bidders, some aspects were re-examined and tweaked to keep it within budget. That led to a decision to split it into two contracts, one for upland and another for marine elements.

The marine phase will soon be up for bid, subject to the Legislature’s approval. This includes a fishing pier along the waterfront to replace the popular one now on the Ivar’s side of the terminal.

The existing terminal was built in 1957 to accommodate the much-lesser traffic of 62 years ago.

“It is the busiest vehicle route in our system, with 2.3 million vehicles per year,” McIntosh said.

With 4.2 million riders annually, the route is not the busiest overall in terms of passengers. That would be the Seattle-Bainbridge Island run.

Construction has resulted in an increase of heavy vehicles to the Mukilteo waterfront, resulting in minor traffic delays.

Brace for more.

Diane Rhodes, ferry spokeswoman, said over the next few weeks there will be big trucks on the Mukilteo Speedway hauling in fill for the exit lanes.

“The trucks will be spaced out. There will be about six to eight per hour,” Rhodes said.

Rhodes said trucking hours are 7 a.m. to 2:45 p.m. Monday through Thursday, and 7 a.m. to 1 p.m. Friday. Flaggers will be in place during those times.

Andrea Brown: abrown@heraldnet.com; 425-339-3443. Twitter @reporterbrown.

Talk to us

More in Local News

Vesper Peak, as seen from Gothic Peak, is the highest summit on the left. (Caleb Hutton / Herald file)
Anacortes man found dead near Vesper Peak identified

Adam L. Johnson, 29, didn’t return from a hike Saturday. Search and rescue found his body in a creek.

A driver yelled "Black lives don’t matter” at a man working in his driveway.
Family endures racist taunt over ‘Black Lives Matter’ sign

They were doing yard work at their Everett home when a driver yelled ‘Black lives don’t matter.’

‘Residency makes you a doctor:’ New WSU program coming to Prov

WSU’s medical college is starting an Everett-based internal medicine residency. New docs will come here.

A police officer stands outside of Boohan Oriental Market after a shooting on Tuesday, Sept. 29, 2020 in Everett, Wa. (Olivia Vanni / The Herald)
1 dead, 2 injured after Edmonds shooting; suspect arrested

One woman was shot in the face. Police believe all four people knew each other.

Sultan woman, 20, identified after fatal Friday night crash

Sarah A. Markley crashed into a tree and died of blunt-force injuries, the medical examiner found.

Jazz Jarrell leads a march outside Denney Juvenile Justice Center to push reforms in Everett on September 26, 2020.  (Kevin Clark / The Herald)
No more youth jail, group demands at small rally in Everett

The Snohomish County Equity Alliance wants youth treated differently in the criminal justice system.

Human skeletal remains found Saturday near Mill Creek

Circumstances around the death are under investigation by the sheriff’s office Major Crimes Unit.

Three people were shot at the Boo Han Oriental Market Tuesday, Sept. 29, 2020, off of Highway 99 in Edmonds. (Olivia Vanni / The Herald)
Edmonds triple-shooting suspect turned self in, police say

The suspect allegedly admitted to family that he shot his wife and her two friends. One later died.

Worker cheer and wave as Boeing's 787 Dreamliner takes off from Paine Field Tuesday morning on Dec. 15, 2009. (Justin Best/ The Herald
Report: Boeing will end 787 Dreamliner production in Everett

Boeing declined comment on a WSJ story saying the passenger jet’s assembly will move to South Carolina.

Most Read