How to read your road report: Road restrictions may be near, but not necessarily in, the cities under which they are listed. Most restrictions are from 7 a.m. to 6 p.m. weekdays. Any lane on the road could be closed between the two cross streets found in most listings. Weather conditions may change work plans.
Freeway work through Everett
Multiple lanes of I-5 may be closed Monday through Thursday nights and on some Friday nights for the remainder of the year. Closures will be in both directions in various locations between Highway 526 (the Boeing Freeway) and Marine View Drive. Southbound closures begin at 7 p.m. and end at 4 a.m. Northbound closures begin at 10 p.m. and end at 5 a.m. Friday night closures end at 7 a.m. Saturdays. Watch for traffic signs.
Lane striping continues this week on northbound I-5 between Highway 526 and the Broadway exit. Lane closures begin about 9 p.m. and end about 6 a.m. the next day.
On dry nights this week, paving operations in the southbound I-5 lanes are set to continue. Lanes begin closing as early as 6 p.m. and open about 4 a.m. the next day.
On dry nights this week, exits from and onramps to I-5 may be closed in the downtown Everett area. Paving and construction of noise walls is continuing.
I-5 overpass work continues between Highway 526 (the Boeing Freeway) and Marine View Drive in Everett. The state will close lanes and reroute drivers onto several downtown Everett streets, including Everett Avenue, Broadway, 41st Street, Pacific Avenue, Lowell Road-52nd Street, Hewitt Avenue, Harrison Avenue, Highland Avenue, Smith Avenue and Summit Avenue. Street closures could cause ramp and city street backups. Drivers are encouraged to use other routes.
New or updated roadwork
For information on emergency county road closures and maintenance projects, call Snohomish County road maintenance at 360-862-7500 or go to www.snoco.org and use the keyword search.
Bothell
Locust Way north of 234th Place SW. Lane closure through Dec. 21. Culvert repair.
Locust Way south of 228th Street SW. Lane closure through Jan. 4. Frontage improvements.
49th Avenue SE, north of 224th Street SE. Lane closure through Jan. 4. Water drain installation.
244th Street SE in the 5700 block. Lane closure through Dec. 21. Shoulder and road subgrade repairs.
Cathcart
180th Street SE between Fales Road and 109th Avenue SE. Lane closure through Friday. Shoulder and road subgrade repairs.
Everett
Alexander Road between 122nd Street SW. Lane closure through Jan. 4. Utility construction and frontage improvements.
Lynnwood
Motor Place south of 160th Street SW. Lane closures through Dec. 31. Utility installation and frontage improvements.
Marysville
84th Street NE southwest of the intersection with 123rd Avenue NE. Shoulder closure through Jan. 11. Gas valve maintenance.
Mill Creek
Larch Way near the intersection with 164th Street SW. Lane closure through Jan. 4. Utility installation and frontage improvements.
Monroe
High Bridge Road north of Crescent Lake Road. Lane closure through Friday. Culvert installation.
Snohomish
Riverview Road along the eastbound lane. Lane closure through Dec. 31. Riverbank repair.
Ongoing roadwork
Alderwood Manor
Poppy Road between Second Avenue SE, Meridian Drive SE and Winesap Road. Lane closures through Tuesday. Power pole replacement.
Arlington
Swanson Road Bridge east of Swanson Road. Intermittent full road closure through Friday. Bridge construction.
Bothell
Damson Road north of Eighth Place W. Lane closed through Friday. Gas service installation.
26th Avenue SE at 171st Street SE. Lane closures through Friday. Gas main reinforcement.
28th Avenue SE north of the intersection with 176th Street SE. Gas main reinforcement.
Brier
Larch Way between 21st Avenue W. and 22nd Avenue W. Lane closure through Friday. Gas service installation.
Edmonds
82nd Place W. just north of 224th Street SW. Lane closure through Friday. Frontage improvements.
Everett-Lake Stevens
87th Avenue SE between 12th Street SE and Eighth Street SE. Lane closure through Dec. 22. Utility and frontage installation.
Granite Falls
Mountain Loop Highway between Benson Creek Road and Monte Cristo Grade Road. Lane closure through Jan. 4. Bridge closure.
Lynnwood
14th Avenue W. from 175th Place SW north to 172nd Street SW. Lane closure through Dec. 21. Utility connections and frontage improvements.
Madison Way between 146th Street SW and 148th Street SW. Lane closure through Friday. Frontage improvements.
Magnolia Road between Filbert Road and 189th Street SW. Lane closures through Jan. 4. Gas line installation.
164th Street SW between 25th Avenue W. and the northbound onramps of I-5. Lane closure through Friday. Transmission line contract for PUD.
Marysville
77th Street NE between 27th Avenue NE and 31st Avenue NE. Lane closure through Dec. 28. Driveway access installation and fire hydrant installation.
Mill Creek
171st Place SE between 23rd Avenue SE and 24th Avenue SE. Lane closure through Friday. Gas main reinforcement.
Monroe
High Bridge Road north of Crescent Lake Road. Lane closure through Friday. New culvert installation.
High Bridge Road between 167th Avenue SE and Crescent Lake Road. Lane closure through Dec. 24. Cross-culvert construction.
Snohomish
131st Avenue SE and Three Lakes Road, in conjunction with 139th Avenue SE. Lane closures through Dec. 26. Utility work.
Stanwood
Lakewood Road, Frank Waters Road and Marine Drive. Lane closure through Dec. 31. Constructing 7.5 miles of PUD electric power transmission line.
Woodinville
58th Avenue SE between 238th Street SE and 244th Street SE. Lane closure through Dec. 21. Gas pipe hanger installation.