Workers testing Hood Canal bridge drawspan
Published 7:55 am Monday, June 1, 2009
SHINE — The Hood Canal floating bridge could reopen in a few days.
The Transportation Department says the day may be determined by tests Tuesday on the drawspan. It must complete 20 perfect openings in a row.
The work is ahead of schedule. The department had expected the assembly work on the $500 million project that began on May 1 would keep the bridge closed until mid-June.
On the Net:
www.HoodCanalBridge.com