Marysville’s Grove Street down to one lane for road work
Published 1:30 am Wednesday, May 3, 2017
MARYSVILLE — The city started work this week to improve Grove Street between State Avenue and 47th Avenue NE. Traffic will be reduced to one lane between 7 a.m. and 5 p.m. Mondays through Thursdays. Work is expected to conclude by the end of July.
Suggested alternate routes include 76th Street NE.
Crews will install 1,250 feet of new 8-inch sewer line, pedestrian ramps, traffic signal improvements, an asphalt overlay and road striping. The work is being performed by SRV Construction, of Oak Harbor.
More information is at www.marysvillewa.gov.