A worker directs others on a barge as construction continues earlier this year at the new Mukilteo ferry dock. Ferries project employees recently met with Mukilteo City Council members in a work session for an update about the $167 million project. (Andy Bronson / Herald file)

A worker directs others on a barge as construction continues earlier this year at the new Mukilteo ferry dock. Ferries project employees recently met with Mukilteo City Council members in a work session for an update about the $167 million project. (Andy Bronson / Herald file)

Keeping the Mukilteo ferry project pretty but not pricey

Washington State Ferries and the city are hashing out details for new bid package on the terminal.

MUKILTEO — When stuck in the ferry holding lanes, there’s nothing better than bopping over to the Ivar’s window for a soft-serve ice cream cone.

That might not be an option at the proposed new ferry terminal.

Those coveted cones are one of the details in the scheme of things still being worked out by Washington State Ferries and the city of Mukilteo.

For now, though, there are bigger fish to fry. Issues such as dealing with escalating steel costs and securing contractor bids to avoid more project delays.

Ferries project employees recently met with Mukilteo City Council members in a work session for an update about the $167 million project.

“We explained our need to repackage the bid to meet available project funding,” said ferry spokesperson Broch Bender, who wasn’t at the meeting. “We will update the council when we have more specifics.”

The recent snag came when all five bids received for a major phase of the construction of the terminal were rejected in August. The state Department of Transportation said the offers were way over budget. The department’s engineers came up with an estimate of $65 million for the work that includes building the main terminal and holding lanes.

The lowest contractor bid came in at $8 million over the estimate, but was rejected for irregularities. The next was $18 million over budget. Bids went up from there.

The ferries plan to advertise a new bid package in October with bid openings in late November. Bender is hopeful that a bid will be accepted this time, after some aspects are re-examined and tweaked to keep it within budget and draw more bidders.

“Everybody wants this to move forward as quickly as possible,” Bender said.

The bid rejection delays the terminal opening for use by about six months in 2020. “Originally we said spring and now we’re saying fall, but that could shift again,” Bender said.

Mayor Jennifer Gregerson said the ferries mentioned changing the flooring material and artwork in the new terminal, which is fine with her.

Her main concern is to keep items in the project “that really matter to Mukilteo,” she said. “Of all the things that have gone away, there are a few left that we really want.”

These involve fencing material and the promenade, a boardwalk that the mayor said will provide needed access to the waterfront.

“There is a design concept that our community and council adopted, that has treated concrete, is 15 feet wide, has benches and all those things that make it a good experience. The ferries wants to eliminate some of the design features that make it unique,” she said.

Fencing aesthetics is another concern for Gregerson, a council member since 2004 who was elected mayor in 2013 and reelected in 2017.

“The ferries want to change the fence material to a black coated chain link from the nicer material that would fit the rest of the design and from far away would kind of melt into the landscape. It would be easier to see through and wouldn’t stand out as much,” she said.

The fencing would enclose holding lanes for security reasons, ensure accurate passenger counts and prevent fare evasion. Gregerson wants there to be some type of access gate.

Otherwise, she said, “Passengers and drivers won’t be able to get out of their cars and visit the waterfront. They won’t be able to walk up to Ivar’s … It doesn’t meet today’s vision for what it means to be waiting for the ferry in Mukilteo or what we’ve thought this project may look like over the years.”

Bender said the mayor’s concerns are still on the table and that no decisions have been made. Another meeting is scheduled soon.

The new terminal is being built along the waterfront one-third of a mile east of the existing terminal. The route has more than 4 million passengers a year.

“Every public meeting I go to or when I talk to kids, everybody wants to know what’s going on with the waterfront and what will happen next,” Gregerson said.

Bender is optimistic about the end result.

”We have a commitment to build a beautiful and efficient terminal. Because of the climate now, we have to look at everything,” Bender said.

Andrea Brown: abrown@heraldnet.com; 425-339-3443. Twitter @reporterbrown.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

The Everett City Council on Wednesday, April 16, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Everett City Council approves apprenticeship ordinance

The new ordinance builds upon state law, requiring many city public works contracts to use at least 15% apprentice labor.

Logo for news use featuring the municipality of Stanwood in Snohomish County, Washington. 220118
Stanwood nears completion of deployable floodwall

The new floodwall will provide quick protection to the downtown area during flood conditions.

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

Steven M. Falk / The Philadelphia Inquirer / Tribune News Service
James Taylor plays Sunday and Monday at Chateau Ste. Michelle in Woodinville.
A&E Calendar for May 22

Send calendar submissions for print and online to features@heraldnet.com. To ensure your… Continue reading

Members of Washington State patrol salute the casket of slain trooper Chris Gadd during a memorial cremony on Tuesday, March 12, 2024, at Angel of the Winds Arena in Everett, Washington. (Ryan Berry / The Herald)
Opening statements begin in trial of man charged in crash of WSP trooper

Deputy prosecutor described to jurors what began as a routine patrol for Christopher Gadd — “until it wasn’t.”

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.