Boeing faces decade-long challenge in recouping 787 costs

How long will it take the Boeing Co. to work off the costs of developing the new 787? In September, Boeing handed over the first Dreamliner, more than three years behind schedule. And last month, company executives revealed the magic number: 1,100 jets. The company estimates it will take more than 10 years of production to reach this mark.

In today’s print edition, we created a graphic representation of those 1,100 airplanes and where they fall on the production calendar to help you visualize the challenge ahead for workers in Everett and South Carolina. It’s posted to the right as a PDF for download.

What follows is the description from that chart.

Accumulating costs

The program’s deferred costs, pegged at $9.7 billion at the end of September, will continue to grow until Boeing finishes developing the next version of the Dreamliner, the 787-9.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Recovering that cost of developing and producing the airplane efficiently depends on how quickly Boeing can increase the production rate to 10 787s per month by the end of 2013 at the factories at Paine Field in Everett and in Charleston, S.C.

Learning curve

Boeing workers and suppliers must quickly become more proficient at assembling the 787. This is a common phenomenon in manufacturing — the more you do something, the better you get at it. In the case of the most complicated mass-produced product in the world, Boeing estimates, it won’t be until sometime in 2015 when the revenue from each plane actually exceeds the cost of building it.

Order book

Boeing has 821 orders for the 787. That gets the company most of the way to recouping the program’s costs, but not all the way. It’s assumed the company will have no trouble selling more airplanes for delivery in 2019 and beyond.

Break even

Boeing spreads the total cost of an airplane program over a long period of selling and building airplanes — in the case of the 787, about 10 years and 1,100 deliveries. Chief Financial Officer James Bell says that’s roughly equivalent to the period of recouping the costs of the 777. But Boeing didn’t need to deliver nearly as many 777s over those 10 years to cover costs as it will 787s. Boeing delivered fewer than 500 777s in the first 10 years of production.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in unincorporated Snohomish, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

Outside of the Madrona School on Monday, Aug. 26, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Sewer district notifies Edmonds schools of intent to sue

The letter of intent alleges the school district has failed to address long-standing “water pollution issues” at Madrona K-8 School.

Everett
Man stabbed in face outside Everett IHOP, may lose eye

Police say the suspect fled in the victim’s car, leading officers on a 6-mile chase before his arrest.

A person walks up 20th Street Southeast to look at the damage that closed the road on Wednesday, Nov. 20, 2024 in Lake Stevens, Washington. (Olivia Vanni / The Herald)
WA delegation urges Trump to reconsider request for bomb cyclone aid

The Washington state congressional delegation urged President Donald Trump on… Continue reading

Aaron Weinstock uses an x-ray machine toy inside the Imagine Children Museum on Tuesday, Dec. 3, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Imagine Children’s Museum $250k grant reinstated following federal court order

The federal grant supports a program that brings free science lessons to children throughout rural Snohomish County.

Snohomish County 911 Executive Director Kurt Mills talks about the improvements made in the new call center space during a tour of the building on Tuesday, May 20, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
New 911 center in Everett built to survive disaster

The $67.5 million facility brings all emergency staff under one roof with seismic upgrades, wellness features and space to expand.

Everett
Five arrested in connection with Everett toddler’s 2024 overdose death

More than a year after 13-month-old died, Everett police make arrests in overdose case.

Madison Family Shelter Family Support Specialist Dan Blizard talks about one of the pallet homes on Monday, May 19, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Madison Family Shelter reopens after hiatus

The Pallet shelter village, formerly Faith Family Village, provides housing for up to eight families for 90 days.

A member of the Sheriff's office works around evidence as investigators work the scene on 20th Street SE near Route 9 after police shot and killed a man suspected in a car theft on Friday, Jan. 13, 2023, in Lake Stevens, Washington. (Ryan Berry / The Herald)
Family of Lake Stevens man shot by police sues over mental health care delays

Lawsuit says state failed to evaluate James Blancocotto before he was shot fleeing in a patrol car.

The age of bridge 503 that spans Swamp Creek can be seen in its timber supports and metal pipes on Wednesday, May 15, 2024, in Lynnwood, Washington. The bridge is set to be replaced by the county in 2025. (Ryan Berry / The Herald)
Snohomish County report: 10 bridges set for repairs, replacement

An annual report the county released May 22 details the condition of local bridges and future maintenance they may require.

Traffic moves north and south along the southbound side of the Highway 529 after the northbound lanes were closed due to a tunnel on Tuesday, July 2, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Southbound 529 to close near Marysville for four days for bridge work

WSDOT said the 24-hour-a-day closure is necessary to allow contractors to perform work on the aging Steamboat Slough Bridge.

The Edmonds City Council gathers to discuss annexing into South County Fire on Tuesday, Dec. 3, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Community group presents vision for Edmonds’ fiscal future

Members from Keep Edmonds Vibrant suggested the council focus on revenue generation and a levy lid lift to address its budget crisis.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.