Rail boosters to Sound Transit: Don’t delay Link expansion

“For too long Everett has paid into the system with minimum benefit,” said transit supporter Brock Howell.

By Mike Lindblom / Seattle Times

SEATTLE — A dozen advocacy groups encouraged Sound Transit leaders Thursday to deliver voter-approved rail and bus extensions faster, instead of accepting project delays as inevitable.

When 2021 began, elected officials on the agency’s governing board were notified of a $12 billion funding shortage to build nine rail extensions and two bus-rapid transit routes promised in the Sound Transit 3 ballot measure in 2016. Inaccuracies in early cost estimates, along with rapid land and construction inflation, played a major role, a consultant’s review found this spring.

The agency declared a self-imposed July 22 deadline to publish new construction schedules, known as a “realignment,” that postpone most opening dates two to 10 years. Doing so would spread costs out to 2045, so tax revenues don’t run low late this decade.

On Thursday, board Chairperson Kent Keel loosened his timetable to set a realignment vote for Aug. 5.

Board member Claudia Balducci, a Metropolitan King County Council member from Bellevue, is working on a counter proposal she said would “keep us on schedule as much as humanly possible.”

The pro-transit coalition says realignment can wait.

For one thing, Sound Transit may learn by late summer how much federal infrastructure money the agency could receive. That might be a $1.9 billion grant increase co-sponsored by Sens. Patty Murray and Maria Cantwell, both D-Washington, or higher if the Biden administration coaxes an infrastructure package through Congress.

Keel, who is a University Place City Council member, worked with transit staff to devise a slate of project postponements: Ballard light rail by 2040 instead of the original 2035 ballot promise; the Federal Way-Tacoma extension by 2032 instead of 2030; or Everett Station by 2042 instead of 2036. His plan would kick a host of park-and-ride garages to the 2040s, conserving money to finish the major rail lines.

Transit activists point to last week’s record temperature of 108 degrees as reason to expand the electrically powered train network as an alternative to fossil-fuel powered transportation.

“Sound Transit would be committing a crime against the climate if they move ahead with the proposed plan to delay the rail projects voters approved in 2016,” argued Robert Cruickshank of the Sierra Club.

On the other hand, “when states like Washington take action, regardless of their share of global emissions, they help drive market transformation beyond their borders,” said Vlad Gutman-Britten, state director for Climate Solutions, which wasn’t involved in the advocates’ statement Thursday.

Keel’s version contains a new concept: build an intermediate Snohomish County segment from Lynnwood to southwest Everett along Highway 99, by 2038. Then the final destination in downtown Everett would be pushed to 2042, compared to the ballot promise of a longer Lynnwood-Paine Field-Everett line in 2036.

“For too long Everett has paid into the system with minimum benefit,” said transit supporter Brock Howell, executive director of Everett Station District Alliance. “Another six-year delay to ST3 would not just be another six years without light rail service, it’d be a lost opportunity to grow our economy year-over-year through transit-oriented development, to address housing affordability, and to address climate change.”

Already, a robust economy has boosted tax-revenue predictions, whittling the funding gap to $8 billion, which could settle at $6 billion after federal aid. These figures don’t include extra costs for options such as a West Seattle tunnel, a south-end train base over the toxic Midway Landfill , or a 200-foot-deep International District/Chinatown station.

The realignment, Keel says, is needed to write reliable budgets and to assure the agency keeps its premier credit rating. Any postponed projects would be re-examined yearly to confirm whether delays are still needed, his plan says.

“The transit expansions our voters have approved are critical for the region’s future, and for our planet,” he said at a transit-committee meeting Thursday. “I and every member of the Sound Transit board share the strong desire to complete them as quickly and as humanly possible. At the same time, we have a responsibility to play it straight with our region’s voters, taxpayers and commuters on what is possible under current revenue and cost projections.”

Seattle Mayor Jenny Durkan and King County Executive Dow Constantine have joined Balducci in seeking additional time to find better options.

Durkan gave a glimpse of coming debates. Is it possible, she wondered, to finance light-rail all the way from Alaska Junction in West Seattle to downtown and Smith Cove near Interbay together, instead of waiting until 2038 to tunnel north of Sodo? Otherwise, she said, delays to both rail and ST3’s RapidRide bus improvements will strand travelers in Ballard.

Talk to us

More in Local News

Logo for news use featuring the municipality of Monroe in Snohomish County, Washington. 220118
Police: Monroe hit and run suspect arrested for 2 DUIs in 3 hours

The driver had just been arrested and released for a DUI, when he allegedly ran a red light and crashed into a pickup.

Everett
Man hurt in house fire east of Everett

The home in the 12400 block of 51st Avenue SE was reported on fire at 12:54 a.m.

A wanted suspect was arrested after a standoff with law enforcement Tuesday night. (Bothell Police Department)
Kidnapping suspect arrested after standoff in Bothell

A large police presence contained the property in the 20500 block of 32nd Dr. SE on Tuesday night.

Community Transit's Lynnwood microtransit pilot project is set to launch this fall with a service area around the Alderwood mall. (Community Transit)
Lynnwood’s microtransit test begins this fall, others possible

Community Transit could launch other on-demand services in Arlington, Darrington and Lake Stevens.

Doctor Thomas Robey sits in a courtyard at Providence Regional Medical Center on Thursday, Aug. 11, 2022, in Everett, Washington. (Ryan Berry / The Herald)
‘It’d be a miracle’: Providence tests new treatment for meth addiction

Monoclonal antibodies could lead to the first drug designed to fight meth addiction. Everett was chosen due to its high meth use.

Rev. Barbara Raspberry, dressed in her go-to officiating garments, sits in the indoor chapel at her home, the Purple Wedding Chapel, on Tuesday, Aug. 9, 2022, in Everett, Washington. The space used to be two bedrooms, but she and her husband Don took down a wall converted them into a room for wedding ceremonies the day after their youngest son moved out over 20 years ago. The room can seat about 20 for in-person ceremonies, plus it serves as a changing room for brides and is the setting for virtual weddings that Raspberry officiates between brides and their incarcerated fiancees at the Monroe Correctional Complex. (Ryan Berry / The Herald)
Everett’s oh-so-colorful Purple Wedding Chapel is in the red

Rev. Rasberry has hitched hundreds of couples over the years. After her husband died, she’s unsure if she can keep the place.

Everett
Man dies in motorcycle crash that snarled I-5 in Everett

Washington State Patrol: he tried to speed by another driver but lost control and hit the shoulder barrier.

x
Edmonds Library continues as rooftop pop-up

For now, the building is still shuttered from a June flood.

A performer with Up Up Up, a touring circus on a flatbed truck with a crane for aerial acts. (Submitted photo)
Double fun in Everett with a big truck circus, big screen movie

Up Up Up circus returns to Hewitt at 6 p.m. “Encanto” at the Sail-in Cinema at the waterfront is at 8:25 p.m.

Most Read