Construction continues on Edgewater Bridge along Mukilteo Boulevard on Wednesday, Jan. 22, 2025. (Olivia Vanni / The Herald)

Everett pushes back opening of new Edgewater Bridge

The bridge is now expected to open in early 2026. Demolition of the old bridge began Monday.

EVERETT — The expected opening of the new Edgewater Bridge, which connects Mukilteo to Everett, has been delayed until early 2026, Everett Public Works announced Friday.

The closure was initially estimated to last about a year, with opening planned for late 2025. But unexpected underground conditions, the city wrote in a project update Friday, affected the construction schedule. Although many of those issues have been addressed, the city said, the new bridge is now expected to open early in the new year, with work continuing on the bridge through the first quarter of 2026.

“While the timeline has shifted slightly, we’re optimistic that the next phase will bring steadier progress,” the project update read. “We are working closely with the contractor to make up time wherever possible.”

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The main cause of the current delays were difficulties with subsurface work, wrote Everett Public Works spokesperson Kathleen Baxter in an email Monday. While building the project, workers had to install steel piling — a structure used to hold back soil or water during construction — to create a temporary work bridge needed to complete the permanent one.

But the installation of the steel piling was slowed by unexpected underground obstructions, Baxter wrote, including old timber and concrete left behind from a previous bridge structure.

“These obstructions required additional time and care to safely navigate, adding complexity to an already challenging task in steep and unstable terrain,” she wrote.

The city had delayed starting construction of the bridge multiple times due to the COVID-19 pandemic and an environmental review. Initially looked at as a 2022 project, it was delayed until summer 2023, then to mid-2024. The city first closed the bridge for construction in October 2024.

Demolition of the existing bridge began Monday. It is expected to take several weeks and “will be noisy and involve heavy equipment,” the city wrote in a release. The start of the demolition marked “a dramatic and highly visible turning point in the project,” the city wrote.

The Edgewater Bridge, built in 1946, was a critical connection between Everett and Mukilteo. Before its closure, about 6,000 vehicles crossed it every day.

But the old bridge needed to be replaced. City reports found it was vulnerable to failure in the event of a major earthquake. The bridge was also “functionally obsolete,” a City Council document read, because of its narrow traffic lanes and sidewalks.

The new bridge will have 12-foot lanes in each direction, 6.5-foot sidewalks on each side and 5-foot bike lanes.

A total of $34.9 million has been set aside for the project. Much of that money — about $25 million — comes from a federal bridge fund. The city is contributing about $6 million in local funds.

A proposed ordinance would allow the city to spend just over $4 million in proceeds from limited tax general obligation bonds on the project. Those dollars would be used to offset planned spending from the city’s traffic mitigation fund. The City Council could vote on that ordinance on May 21.

The city issued a total of $28 million worth of limited tax general obligation bonds in March. Other projects the bonds will help pay for include improvements to Everett’s municipal building and renovations to the city’s waterfront. Issuing bonds for construction projects is routine for municipalities.

Will Geschke: 425-339-3443; william.geschke@heraldnet.com; X: @willgeschke.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

The Everett City Council on Wednesday, April 16, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Everett City Council approves apprenticeship ordinance

The new ordinance builds upon state law, requiring many city public works contracts to use at least 15% apprentice labor.

Logo for news use featuring the municipality of Stanwood in Snohomish County, Washington. 220118
Stanwood nears completion of deployable floodwall

The new floodwall will provide quick protection to the downtown area during flood conditions.

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

Steven M. Falk / The Philadelphia Inquirer / Tribune News Service
James Taylor plays Sunday and Monday at Chateau Ste. Michelle in Woodinville.
A&E Calendar for May 22

Send calendar submissions for print and online to features@heraldnet.com. To ensure your… Continue reading

Members of Washington State patrol salute the casket of slain trooper Chris Gadd during a memorial cremony on Tuesday, March 12, 2024, at Angel of the Winds Arena in Everett, Washington. (Ryan Berry / The Herald)
Opening statements begin in trial of man charged in crash of WSP trooper

Deputy prosecutor described to jurors what began as a routine patrol for Christopher Gadd — “until it wasn’t.”

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.