Gas tax won’t be enough to keep promises

Work to widen I-5 in Everett is wrapping up early and on budget.

The $263 million project, set to finish by June, is being called a signature example of the roadwork the Legislature promised in 2003 and 2005, after adopting the two largest gasoline tax increases in state history.

Now the state is running short of money to pay for everything. The reasons: Drivers are buying less gas than expected and it’s costing the state more to build projects than estimated.

And some of the roadwork promised may be put off until money can be found to complete it.

Half the projects will be finished or under construction by summer.

Drivers across the state already are driving on new lanes and over wider bridges funded by the 5-cent and 9.5-cent per gallon gas tax hikes.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

When the Legislature adopted the gas tax increases, they counted on them to raise $11 billion over 16 years for road projects, said Glenn Kuper, a spokesman for the state Office of Financial Management.

In order to finish everything, the state needs to come up with about $782 million. In Snohomish County the projected shortfall is $51 million out of $1.3 billion budgeted for roads, bridges and other projects.

Most of that potential shortfall stems from an 11 percent increase in the cost of construction supplies between 2002 and 2006, including a 30 percent increase in 2006, Kuper said.

And with gas prices hovering near $3 a gallon, drivers are buying less. That’s expected to short the state’s two-year budget by about $76 million. And transportation planners figure the problem will continue.

“We have to work with the Legislature to come up with a way to close the gaps,” Kuper said. “We don’t want to put things off for very long because we need to get things stabilized.”

Gov. Chris Gregoire does not want to take money out of the general fund to pay for the projected shortfall, he said, but she still wants the problem solved.

“She wants to work with the Legislature and do it at a pace that makes sense,” Kuper said.

It’s crucial not to drop projects that legislators promised taxpayers, said Sen. Mary Margaret Haugen, D-Camano Island, chairwoman of the Senate Highways and Transportation Committee.

“We need to stay on top of the (transportation) department,” Haugen said. “We can do better.”

Construction projects can be built faster and more efficiently, she said. She pointed to the Everett I-5 widening project, where the state is saving millions of dollars by having the contractor build the project as quickly as design work is complete.

The shortfall can’t be blamed on the state Department of Transportation, said Rep. Judy Clibborn, D-Mercer Island, chairwoman of the House Transportation Committee.

“I think from a project delivery standpoint, they can crow,” she said. “They’re finishing their projects on time and on budget.”

The costs of steel and concrete “are beyond our control,” she said.

Transportation Department officials are looking for creative ways to get the projects done without dropping any, said Dave Dye, the agency’s chief operating officer.

“It might take longer to deliver some of the projects,” Dye said. “Some of the project schedules might be affected.”

Facing the same increase in costs and declining gas tax revenue last year, the Legislature voted to push out some of the projects promised in the nickel package, Kuper said.

Originally the nickel tax package was to end by 2038. The Legislature last year decided that taxpayers will have to pay that tax until 2042 to cover the revenue shortfall, he said. The 9.5-cent per gallon tax hike has no sunset date.

Reporter Lukas Velush: 425-339-3449 or lvelush@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

Sound Transit approves contract to build Bothell bus facility

The 365,000-square-foot facility will be the heart of the agency’s new Stride bus rapid transit system, set to open in 2028.

One dead in Everett crash involving motorcycle and two vehicles

Police shut down the 10300 block of Evergreen Way in both directions during the multi-vehicle collision investigation.

Katie Wallace, left, checks people into the first flight from Paine Field to Honolulu on Friday, Nov. 17, 2023 in Everett, Washington. (Olivia Vanni / The Herald)
Executive order makes way for Paine Field expansion planning

Expansion would be a long-range project estimated to cost around $300 million.

A person pauses to look at an art piece during the Schack Art Center’s 50th anniversary celebration on Thursday, Oct. 10, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Everett to seek Creative District designation

The city hopes to grow jobs in the creative sector and access new grant funds through the state label.

Former Herald writer Melissa Slager’s new book was 14-year project

The 520-page historical novel “Contests of Strength” covers the 1700 earthquake and tsunami on Makah lands.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.