No lasting fix likely for slides along railroad

EVERETT — Some measures to prevent mudslides along railroad tracks between Everett and Seattle have been taken and more are in the works, but they won’t be enough to fix the drainage problems on the corridor, according to state officials.

Travelers on Sounder commuter and Amtrak passenger trains along the route have been plagued by delays from mudslides for years. Most recently, mudslides resulted in closing the line to passenger service the entire Thanksgiving week, said Gus Melonas, a spokesman for Burlington Northern Santa Fe Railway, which owns the tracks.

The hillsides along the tracks between Everett and Seattle are the worst slide area for trains in Western Washington, said David Smelser, a high-speed rail program manager for the state Department of Transportation.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The problem, he said, isn’t just the slopes — it’s the runoff from developed areas above the slopes along the route.

“The key is stormwater runoff, and, frankly, BNSF and (the Transportation Department) are not going to fix that,” he said.

Sounder, which has experienced low ridership because of parking and other issues as well as mudslides, has had more than 200 trips canceled because of slides since it began running in 2003, according to Sound Transit figures. The railroad requires a 48-hour moratorium on passenger service when tracks are blocked by a mudslide. Eight Sounder trains operate on weekdays between Everett and Seattle, four each way. Six Amtrak trains run on the line every day, three each way.

The state has $16 million in hand from the federal government specifically for mudslide prevention on rail corridors, and most or all of it will go to work between Everett and Seattle, state officials said.

The money could pay for projects such as building small catchment walls, basins and deepening ditches, Smelser said. The state is working with BNSF railroad to pinpoint the most vulnerable areas and on engineering and design.

The earliest that work could begin is the summer of 2014, he said — two winters from now.

Some work was done this past summer along the route. The state spent about $100,000 of its money, not from the federal pot, Smelser said. The railroad spent several million, Melonas said.

The state cleared drains and culverts, trimmed trees and brush and removed debris. Railroad projects included building new ditches, improving seawalls, culverts and bridge footings and contouring hillsides.

There were more than 20 slides altogether between Everett and Seattle during Thanksgiving week, he said. The largest were two in Everett and one in Mukilteo. The Mukilteo slide shut down passenger trains Nov. 19 and the closure was extended by two days, to Friday, because of more slides and more work that needed to be done, Melonas said. Another slide on Friday night shut down the line for the weekend to Amtrak riders, he said.

The summertime projects didn’t prevent last week’s mudslides but likely kept them from being worse, Melonas said.

While this work can lessen the effect of the slides, in the long run it’s small potatoes, Smelser said.

He said state transportation officials are talking with local government officials about how to address storm water runoff, but there’s little or no money for fixes.

Larger hillside projects provide some relief, but they’re expensive and are not a permanent solution, Smelser said. These involve installing drains into hillsides, collecting water, piping it into a ditch and creating a new drainage system at the bottom of the hill, he said. Trees also are removed and large rocks put in place.

The railroad recently spent between $50 million and $70 million on such a project in north Seattle — covering just a few acres, according to Smelser. The state does not have that kind of money for the work, he said.

“It’s kind of a finger in the dike,” Smelser said. “It really gets back to storm water.”

Bill Sheets: 425-339-3439; sheets@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

Steven M. Falk / The Philadelphia Inquirer / Tribune News Service
James Taylor plays Sunday and Monday at Chateau Ste. Michelle in Woodinville.
A&E Calendar for May 22

Send calendar submissions for print and online to features@heraldnet.com. To ensure your… Continue reading

Members of Washington State patrol salute the casket of slain trooper Chris Gadd during a memorial cremony on Tuesday, March 12, 2024, at Angel of the Winds Arena in Everett, Washington. (Ryan Berry / The Herald)
Opening statements begin in trial of man charged in crash of WSP trooper

Deputy prosecutor described to jurors what began as a routine patrol for Christopher Gadd — “until it wasn’t.”

Aaron Weinstock uses an x-ray machine toy inside the Imagine Children Museum on Tuesday, Dec. 3, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Imagine Children’s Museum $250k grant reinstated following federal court order

The federal grant supports a program that brings free science lessons to children throughout rural Snohomish County.

Edmonds Mayor Mike Rosen goes through an informational slideshow about the current budget situation in Edmonds during a roundtable event at the Edmonds Waterfront Center on Monday, April 7, 2025 in Edmonds, Washington. (Olivia Vanni / The Herald)
Edmonds mulls November property tax levy lid lift

The city is considering options to address its fiscal crisis, including a potential levy higher than originally budgeted.

A person walks up 20th Street Southeast to look at the damage that closed the road on Wednesday, Nov. 20, 2024 in Lake Stevens, Washington. (Olivia Vanni / The Herald)
WA delegation urges Trump to reconsider request for bomb cyclone aid

The Washington state congressional delegation urged President Donald Trump on… Continue reading

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.