Highway 530 at mudslide could be cleared for use in June

OSO — As Gov. Jay Inslee scanned the stretch of Highway 530 where workers were clearing mudslide debris on Thursday, he marveled at the progress.

State transportation officials told Inslee they hope to re-open the former highway by mid- to late-June. Although it will still be in rough shape, it should be faster and safer than an unpaved utility road in use now as a detour.

They also aim to have a permanent, elevated highway built by October, before flood danger increases.

“I think we’ve seen the power of teamwork, the power of compassion and the power of volunteers,” Inslee said.

Uncertainty surrounding the river could still pose engineering challenges, the governor added.

Inslee was making his first trip to slide-affected areas in about three weeks. He’s visited the area more than a dozen times since disaster struck on March 22.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The slide ran across the valley, leaving 10 million cubic yards of dirt, trees and debris strewn over a square mile. It buried 40 homes.

Searchers recovered the remains of 41 people killed by the slide. They scaled back search operations in late April. Two people remain missing and are presumed dead.

With odds of recovering more remains diminishing, authorities have turned their focus to rebuilding Highway 530, a vital economic link for Darrington and surrounding communities.

The governor received an update Thursday from Bill Vlcek, a regional administrator for the state Department of Transportation.

Crews have hauled away about 23,000 cubic yards of mud, about 20 truckloads per hour, Vlcek said. The material is being dumped at a former county landfill in Oso after being screened for hazardous materials and personal belongings.

A contractor has cleared about 1,100 feet of the highway buried by the slide, he said. So far, most of the roadway is intact. Of what they’ve uncovered, only about 160 feet of roadway were destroyed.

There’s an estimated 800 feet to go before they’ve cleared the road surface.

“We’re hoping to get traffic on 530, off the utility road, by the middle to end of June,” Vlcek said.

Until the one-lane temporary access road opened late last month, reaching Darrington from Arlington by car entailed a two-hour trip via Highway 20 in Skagit County. That added huge fuel costs for commuters and for businesses such as Hampton Lumber, Darrington’s largest employer.

Inslee’s previous visit to the area, on April 25, was to announce $300,000 in assistance for Hampton to offset the added expense of bringing timber to market.

To use the access road, drivers line up and wait in what’s been likened to a ferry line. They follow a pilot car at a constant 10 mph over the two-mile route.

The state awarded Granite Construction Co. of Everett a $3.8 million contract to operate the road around the clock. Up to seven employees work in eight-hour shifts as flaggers or pilot-car drivers, company spokeswoman Jacque Fourchy said.

The state also inked a $5 million contract with IMCO Construction of Ferndale to remove slide debris from the highway.

By the end of the month, state officials expect to award a third contract to rebuild Highway 530, transportation department spokesman Travis Phelps said. They hope to start work in June and finish in October.

The contract will cover about two miles of roadway, Phelps said. The work extends beyond areas covered or ruined by debris because of the need to elevate the road above flood levels.

Noah Haglund: 425-339-3465, nhaglund@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

The Everett City Council on Wednesday, April 16, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Everett City Council approves apprenticeship ordinance

The new ordinance builds upon state law, requiring many city public works contracts to use at least 15% apprentice labor.

Logo for news use featuring the municipality of Stanwood in Snohomish County, Washington. 220118
Stanwood nears completion of deployable floodwall

The new floodwall will provide quick protection to the downtown area during flood conditions.

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

Steven M. Falk / The Philadelphia Inquirer / Tribune News Service
James Taylor plays Sunday and Monday at Chateau Ste. Michelle in Woodinville.
A&E Calendar for May 22

Send calendar submissions for print and online to features@heraldnet.com. To ensure your… Continue reading

Members of Washington State patrol salute the casket of slain trooper Chris Gadd during a memorial cremony on Tuesday, March 12, 2024, at Angel of the Winds Arena in Everett, Washington. (Ryan Berry / The Herald)
Opening statements begin in trial of man charged in crash of WSP trooper

Deputy prosecutor described to jurors what began as a routine patrol for Christopher Gadd — “until it wasn’t.”

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.