Whitehorse Trail rebuild project delayed

OSO — The timeline for rebuilding a stretch of the Whitehorse Trail wiped out by the deadly mudslide that tore through this community in March has been pushed back a year.

Officials need additional time for planning and permitting. Meanwhile, they continue to monitor river levels and multiple washouts along the trail.

The county originally hoped to rebuild the mile-long segment of trail this summer, parks and recreation director Tom Teigen said. After conversations with state and federal teams in late November, it became clear that such a timeline wasn’t realistic, he said.

Instead, the county aims to finish plans and paperwork in 2015, followed by construction of the trail in summer 2016. The goal is to install at least two new culverts to help manage water flow in the area, similar to the approach taken in rebuilding Highway 530 through the slide zone.

The county is working with the Federal Emergency Management Agency on trail repairs in the slide area. They need to factor an altered landscape and unpredictable river into their plans.

The mudslide that killed 43 people and destroyed the Steelhead Haven neighborhood also changed the behavior of the North Fork Stillaguamish River in ways that are still being studied. The Whitehorse Trail skirts and crosses the river and its tributaries in a number of places on the path’s 27-mile route from Arlington to Darrington. At least two spots along the trail have been washed out this year, including a stretch that parallels Highway 530 in the heart of Oso, just west of the community’s fire hall.

The washout happened days before Thanksgiving on a stretch of trail that borders Deer Creek, a tributary of the North Fork Stillaguamish. That segment of trail had to be closed, Teigen said. However, it’s near enough to the road and the shoulder is wide enough that locals who use the trail regularly have been able to get around.

“And we’re certainly not encouraging any non-locals to be up on that corridor in these winter months,” Teigen said.

There is another washout on the trail near Darrington that crews have been monitoring for a while, he said.

The U.S. Geological Survey has installed extra river gauges along the Stillaguamish to track water levels and help provide an alert for potential flooding.

“Lots of folks are watching it and we’re putting together a plan of action,” Teigen said.

Along with the gauges, rangers visited the trail near the latest washout in the days immediately after Thanksgiving, he said.

The trail has been a busy place for rangers and other workers during the last six months. Crews hired by Workforce Snohomish through federal emergency relief funds spent the summer cleaning up the trail. They cut back brush, cleaned out garbage and widened the walkway, especially near Fortson Mill, a key access point for the trail.

Though segments of the trail, particularly those with bridges, remain closed pending repairs and safety upgrades, the parks department is on its way to creating a continuous recreational path between Arlington and Darrington. Officials hope the route will become a boon for businesses in Arlington, Darrington and the communities in between, including Oso.

The effort has received some solid backing in the private sector as well. Teigen expects that at least two of the old, unstable bridges along the trail to be repaired and upgraded by the end of the year thanks to a $301,000 private donation.

“Crews are out replacing railings and decking right now with some of our donated funds,” Teigen said.

The trail is an old Burlington Northern Railroad line, and 14 bridges on the route are in need of updates.

Another donor gifted the county with 30 acres adjacent to the trail near Fortson Mill and the parking area there. The county signed off on the donation the day before Thanksgiving. It gave Teigen something extra to be thankful for, he said. The property can be used to improve access to the trail and draw more people to the location, though specific plans have not yet been made.

Kari Bray: kbray@heraldnet.com; 425-339-3439

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Boeing firefighters union members and supporters hold an informational picket at Airport Road and Kasch Park Road on Monday, April 29, 2024 in Everett, Washington. (Annie Barker / The Herald)
Biden weighs in on Boeing lockout of firefighters in Everett, elsewhere

On Thursday, the president expressed support for the firefighters, saying he was “concerned” Boeing had locked them out over the weekend.

Everett officer Curtis Bafus answers an elderly woman’s phone. (Screen shot from @dawid.outdoor's TikTok video)
Everett officer catches phone scammer in the act, goes viral on TikTok

Everett Police Chief John DeRousse said it was unclear when the video with 1.5 million views was taken, saying it could be “years old.”

Construction occurs at 16104 Cascadian Way in Bothell, Washington on Tuesday, May 7, 2024. (Annie Barker / The Herald)
What Snohomish County ZIP codes have seen biggest jumps in home value?

Mill Creek, for one. As interest rates remain high and supplies are low, buyers could have trouble in today’s housing market.

The nose of the 500th 787 Dreamliner at the assembly plant in Everett on Wednesday morning on September 21, 2016. (Kevin Clark / The Herald)
Ex-Boeing engineer, sidelined after a 787 critique, defends troubled plane

Dueling narratives emerged as Boeing’s credibility is near an all-time low, leaving industry observers and the public at a loss as to the risk.

Washington Attorney General Bob Ferguson speaks at the Snohomish & Island County Labor Council champions dinner on Tuesday, Oct. 10, 2023 in Everett, Washington. (Olivia Vanni / The Herald)
3 Bob Fergusons now running for governor as race takes turn for the weird

A conservative Republican activist threw a monkey wrench into the race by recruiting two last-minute candidates.

Arlington
Tulalip woman dies in rollover crash on Highway 530

Kaylynn Driscoll, 30, was driving east of Arlington when she left the road and struck an embankment, according to police.

A person takes photos of the aurora borealis from their deck near Howarth Park on Friday, May 10, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Snohomish County residents marvel at dazzling views of northern lights

Chances are good that the aurora borealis could return for a repeat performance Saturday night.

Arlington
Motorcyclist dies, another injured in two-vehicle crash in Arlington

Detectives closed a section of 252nd St NE during the investigation Friday.

Convicted sex offender Michell Gaff is escorted into court. This photo originally appeared in The Everett Daily Herald on Aug. 15, 2000. (Justin Best / The Herald file)
The many faces of Mitchell Gaff, suspect in 1984 Everett cold case

After an unfathomable spree of sexual violence, court papers reveal Gaff’s efforts to leave those horrors behind him, in his own words.

Retired Snohomish County Superior Court Judge Anita Farris smiles as she speaks to a large crowd during the swearing-in of her replacement on the bench, Judge Whitney M. Rivera, on Thursday, May 9, 2024, at Snohomish County Superior Court in Everett, Washington. (Ryan Berry / The Herald)
One of state’s most senior judges retires from Snohomish County bench

“When I was interviewed, it was like, ‘Do you think you can work up here with all the men?’” Judge Anita Farris recalled.

A truck drives west along Casino Road past a new speed camera set up near Horizon Elementary on Wednesday, May 8, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
After traffic cameras went in, Everett saw 70% decrease in speeding

Everett sent out over 2,000 warnings from speed cameras near Horizon Elementary in a month. Fittingly, more cameras are on the horizon.

The Monroe Correctional Complex on Friday, June 4, 2021 in Monroe, Wash. (Olivia Vanni / The Herald)
Trans inmate says Monroe prison staff retaliated over safety concerns

Jennifer Jaylee, 48, claims after she reported her fears, she was falsely accused of a crime, then transferred to Eastern Washington.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.