How was the timeline of ST3 shortened? Creative borrowing

This is part of a Sound Publishing special report on the Sound Transit 3 expansion proposal, which is on the ballot on Nov. 8. More

Faster. That’s the number-one thing Sound Transit heard from critics after releasing a draft version of its ST3 expansion plan in March. If passed, the then-$50 billion project would have upgraded our transit network with lots more light rail and commuter trains, among other things, but many of the target dates were too far-flung. The Ballard line wouldn’t be done until 2038, for instance, and Everett wouldn’t see a train until 2041.

So when the regional transit agency announced in June that it had moved up the timelines on eight different projects — speeding them up by five years in some cases — there was much rejoicing in Seattle’s urbanist enclaves and transit-hungry suburbs alike.

But cork the champagne for a second and put on your thinking cap. How did they move the timelines up?

We put the question to Sound Transit spokesperson Geoff Patrick. The answer: finance.

Yes, usury! The dark and arcane art that gave us the housing-market bubble and the credit-card economy — this is the magic that will deliver fast transit to the Puget Sound region, faster. “Working closely with a financial team that included outside consultants, we were able to leverage bonding to borrow about $4 billion in addition to what we’d assumed,” says Patrick. “By increasing the funding by that $4 billion, we were able to move up the timelines.” As a result, the overall ST3 budget rose from $50 billion to $53.8 billion.

In other words, some hired-gun economists put their heads together and found a way to materialize $4 billion out of thin air by borrowing it via bonds (that is, loans from regular citizens to the government). In the long run, of course, taxpayers have to pay back those bonds with interest, but in the relatively short term — in this case, a quarter-century — this economic magic trick frees enough cash flow to allow Sound Transit to break ground on eight of its projects years earlier than planned.

Cash flow: That’s the keyword here. The whole dilemma of finance, after all, is balancing the value of getting money you can invest in transit now (which will pay dividends to individuals and the economy as the Puget Sound area gets more and more crowded) against the price of borrowing (that is, interest). Functional governments can usually borrow money on the cheap because it’s a safe investment: It’s hard for a debtor to skip town when the debtor is a town. On the other hand, there’s a limit to how much even a municipality can borrow before it has so much debt — and so much associated risk of default — that its credit score gets downgraded and borrowing money via bonds becomes more expensive. This is what famously happened to our country’s credit score during the 2011 debt crisis.

In this case, Patrick says, the eggheads of fortune concluded that borrowing an extra $4 billion wouldn’t trigger a credit-score downgrade. So while it’s not free money — taxpayers have to pay it back eventually — it is cheap money.

Patrick explains how that cheap $4 billion can speed up eight different ST3 capital projects by 30 years cumulatively. “There’s two main factors in how long it takes to build a project,” he says. “First, let’s say money’s no object, it’s just how long it will take to build something. You have to go through several steps.” In some cases, project timelines — without accounting for any kind of legal delays — can take up to 15 years, he says. “[You] go through all the steps of alternatives analysis and environmental review, and then preliminary engineering takes you up to 30 percent design completion, then you go to final design — that’s 100 percent — and then you have to build it and open it,” says Patrick. “So it’s a significant time period with any major mass-transit project.

“Factor two is you also have to take into account your cash flow,” he says. That means making sure the right amount of money is available at the right time to pay for pencils, asphalt, and whatever else the builder gnomes of the regional transit district need to complete their transit mission. “Part of the challenge that we had with the draft measure is the cash flow was such that some projects were occurring later in the timeline than we wanted to, just by virtue of cash flow,” says Patrick. “In other words, [projects were delayed] not by how long it would take to build them, but by revenues.”

So you want to borrow revenues to speed them up. But doesn’t that add risk? One of the main talking points against ST3 — as articulated by the reliably anti-transit Seattle Times editorial board — is that it has too big a budget and too little oversight. On the other hand, the Times and the No on ST3 campaign website (which entirely relies on that Times editorial as its supporting “research”) are mostly upset about ST3 increasing taxes on property and cars.

Patrick says bonding is not particularly risky. “The Sound Transit 3 plan is built using direct funding for about 70 percent of the project cost and borrowing for about 30 percent of the project cost. In the greater scheme of things nationally, that kind of balance is very strong. There’s not an overextension, as far as the amount that’s appropriate to borrow. We’re able to do it with the assumption of maintaining our — outstanding, frankly — credit ratings.”

So are these new dates real? Can ST3 deliver Everett light rail five years sooner? Well, we who inhabit the region all know how unreliable infrastructure projects are. Sometimes they finish on time, but sometimes they really don’t. Patrick says that ST3’s updated dates were always deliverable in terms of construction timelines. The problem was cash flow and timing. Now that those eggheads figured out how to squeeze another $4 billion out of thin air, there’s no built-in reason why ST3 shouldn’t be able to keep the dates that it promises.

Casey Jaywork: 206-467-4332; cjaywork@seattleweekly.com.

Stories in this special report

Is Sound Transit 3 the $54 billion answer to our congestion?

What Snohomish County would pay — and what ST3 would deliver

ST3 skepticism in Snohomish County might be irrelevant

Sound Transit CEO Peter Rogoff takes on critics of ST3

How was the timeline of ST3 shortened? Creative borrowing

Meet the constituencies for and against Sound Transit’s plan

Not a smooth ride: A brief history of Puget Sound light rail

ST3 is more than rail: A look at bus rapid transit

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Snohomish County Health Department Director Dennis Worsham on Tuesday, June 11, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Snohomish County Health Department director tapped as WA health secretary

Dennis Worsham became the first director of the county health department in January 2023. His last day will be July 3.

Julia Zavgorodniy waves at her family after scanning the crowd to find them during Mariner High School’s 2025 commencement on Friday, June 13, 2025, at Angel of the Winds Arena in Everett, Washington. (Olivia Vanni / The Herald)
‘Dream without limit’: Thousands of Snohomish County seniors graduate

Graduations at the arena conclude this weekend with three Everett high schools on Saturday and Monroe High School on Sunday.

Police Cmdr. Scott King answers questions about the Flock Safety license plate camera system on Thursday, June 5, 2025 in Mountlake Terrace, Washington. (Olivia Vanni / The Herald)
Mountlake Terrace approves Flock camera system after public pushback

The council approved the $54,000 license plate camera system agreement by a vote of 5-2.

Cascadia College Earth and Environmental Sciences Professor Midori Sakura looks in the surrounding trees for wildlife at the North Creek Wetlands on Wednesday, June 4, 2025 in Bothell, Washington. (Olivia Vanni / The Herald)
Cascadia College ecology students teach about the importance of wetlands

To wrap up the term, students took family and friends on a guided tour of the North Creek wetlands.

Community members gather for the dedication of the Oso Landslide Memorial following the ten-year remembrance of the slide on Friday, March 22, 2024, at the Oso Landslide Memorial in Oso, Washington. (Ryan Berry / The Herald)
The Daily Herald garners 6 awards from regional journalism competition

The awards recognize the best in journalism from media outlets across Alaska, Idaho, Montana, Oregon and Washington.

Edmonds Mayor Mike Rosen goes through an informational slideshow about the current budget situation in Edmonds during a roundtable event at the Edmonds Waterfront Center on Monday, April 7, 2025 in Edmonds, Washington. (Olivia Vanni / The Herald)
Edmonds mayor recommends $19M levy lid lift for November

The city’s biennial budget assumed a $6 million levy lid lift. The final levy amount is up to the City Council.

A firefighting helicopter carries a bucket of water from a nearby river to the Bolt Creek Fire on Saturday, Sep. 10, 2022, on U.S. 2 near Index, Washington. (Ryan Berry / The Herald)
How Snohomish County property owners can prepare for wildfire season

Clean your roofs, gutters and flammable material while completing a 5-foot-buffer around your house.

(City of Everett)
Everett’s possible new stadium has a possible price tag

City staff said a stadium could be built for $82 million, lower than previous estimates. Bonds and private investment would pay for most of it.

Jennifer Humelo, right, hugs Art Cass outside of Full Life Care Snohomish County on Wednesday, May 28, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
‘I’ll lose everything’: Snohomish County’s only adult day health center to close

Full Life Care in Everett, which supports adults with disabilities, will shut its doors July 19 due to state funding challenges.

‘No Kings’ rallies draw thousands to Everett and throughout Snohomish County

Demonstrations were held nationwide to protest what organizers say is overreach by President Donald Trump and his administration.

Marysville is planning a new indoor sports facility, 350 apartments and a sizable hotel east of Ebey Waterfront Park. (Olivia Vanni / The Herald)
New report shifts outlook of $25M Marysville sports complex

A report found a conceptual 100,000-square-foot sports complex may require public investment to pencil out.

Logo for news use featuring Snohomish County, Washington. 220118
Snohomish County Board of Health looking to fill vacancy

The county is accepting applications until the board seat is filled.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.