Everett School Board’s changes could add $3.1 million to office plans

EVERETT — The Everett School District’s new administration building could cost $3.1 million more than previously expected, with the price now up to an estimated $26.4 million.

One of the reasons for the added cost is that school board members want a larger building — now 66,365 square feet. It is to be built on school district property south of Everett Memorial Stadium, on Broadway near 41st Street.

The main entrance will be on the west end of the site, near the parking area used for AquaSox games. It is scheduled to open in October 2013.

When the school board approved the project in July, the cost of what was then a 62,000-square-foot building was estimated at $23.3 million.

School board members said they wanted the new building to be useful for 50 to 75 years, rather than just what’s needed now.

Part of the increase in construction cost is addition of 925 square feet of space on the building’s first and second floors and 6,491 more square feet in the basement to allow for future expansion, said Mike Gunn, director of facilities and operations.

The additional basement space will increase the building’s long-term flexibility, he said.

These two steps are expected to add $800,000 to its cost.

Examples of other increases include a city-required storm drainage detention system, expected to cost $400,000; a larger stair landing required for fire safety, estimated at $12,000; upgrading insulation for energy efficiency, expected to cost $85,000; and special pilings and other work needed to build on the site, estimated to cost $135,000.

That adds up to about $1.4 million. The rest of the added costs are design changes and updated cost estimates.

What the district actually pays will depend on bids submitted by contractors, which means the cost could be lower than the estimated $26,430,000.

The School Board voted 3-0 to approve the expansion and layout of the building during a special meeting Tuesday. Those voting for the project were board members Kristi Dutton, Jeff Russell and Ed Petersen, board president.

Two board members, Carol Andrews and Jessica Olson, left the meeting about 20 minutes prior to the vote, because of scheduling conflicts.

Petersen initially suggested that the board delay voting on the changes in size and design, perhaps scheduling a decision for the next regular meeting on Nov. 22.

“This is more than we had planned on in July,” he said. Petersen said he also was concerned about the amount of money available in the school district’s capital fund “and how much we can afford to do.” Gunn said that he had confirmed that the district “could afford to do the building with these changes.”

The district has a capital fund to pay for all construction, ranging from new administration building to schools. Every year, the district adds money to the fund from bonds and the state.

Before leaving the meeting, Andrews said she backed making the changes to enlarge the building. She said she would like even more space for community activities. “Thinking 10 to 15 years down the road, it doesn’t look like enough space,” she said.

Ultimately, Petersen noted that with three members present, the board still had a quorum, meeting the legal requirement to take action.

Dutton made the motion to move ahead on the project. “This investment will save taxpayers’ dollars down the road by not having to go back and ask for more money,” she said.

Dutton said she supported adding space on the first and second floors, in part to add capacity for community meetings and other similar events.

“I see this as a once-in-50-years opportunity,” Petersen said.

Olson said she was astonished that the board voted Tuesday. “I didn’t realize there would be a vote on it,” she said.

Mary Ann Elbert, who was defeated earlier this month in her bid to be elected to the school board, was the only member of the public at the meeting.

“I have a problem with the overall cost of the project,” she said.

The building’s square footage has increased since the board approved the project in July, she said. “Maybe it totally makes sense to add in that extra stuff. But it sure looks like they have additional capacity without adding it on.”

The project is scheduled to go to bid in April, with an award in May and construction by June, Gunn said. Bids can’t be let sooner because architects have to finalize drawings and other documents, he said.

Over the past several months, Everett school board members and district administrators visited other office buildings in Western Washington as architects began drawing plans for the building.

Lake Washington School District officials said they wished that their administrative building had been constructed so that add-ons wouldn’t be so costly.

That was one of the reasons the Everett School Board decided to add space in the basement that won’t be used right away.

“Build it right the first time,” Russell said.

More costs could add up later — depending on options the School Board may choose later. The district will ask contractors to submit proposals for several other items, too. These include installing energy-saving LED lights estimated to cost $113,000; a second elevator costing $150,000; a “green” roof at the main entry, or one that has plants to reduce summer heat and absorb runoff, costing $40,000; and a driveway to the site’s parking lot for an estimated $273,000.

“We think all these items are important,” Gunn said. “We haven’t built them into the project yet because we’re trying to control the costs on the project.”

These and other improvements could potentially add another $576,000 to the building’s cost.

The construction cost of the building itself is $19.57 million, Gunn said.

About $6.6 million was added to the tab for state taxes, architectural and engineering fees, furniture and equipment, permits and a cushion for changes that need to be made during construction, he said.

Building plans show the school board’s meeting room will be on the first floor and have seating for 108 people. The current board room is cramped, and members of the public are often left standing in the hall as they wait to speak to the board.

There also will be temporary office space for community groups.

Talks will continue over the next several months on which groups might use the space, Gunn said. But the school district has talked with the YMCA, the Workforce Develop Council and the Everett Schools Foundation about the possibility of having a place to work in the administration building.

Administrative offices will be on the second floor, with office space for the superintendent and staff working in special educational services, curriculum and facilities and planning.

Sharon Salyer 425-339-3486; salyer@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Snohomish County prosecutor Kara Van Slyck delivers closing statement during the trial of Christian Sayre at the Snohomish County Courthouse on Thursday, May 8, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Jury deliberations begin in the fourth trial of former Everett bar owner

Jury members deliberated for about 2 hours before Snohomish County Superior Court Judge Millie Judge sent them home until Monday.

Danny Burgess, left, and Sandy Weakland, right, carefully pull out benthic organisms from sediment samples on Thursday, May 1, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
‘Got Mud?’ Researchers monitor the health of the Puget Sound

For the next few weeks, the state’s marine monitoring team will collect sediment and organism samples across Puget Sound

Everett
Everett considers ordinance to require more apprentice labor

It would require apprentices to work 15% of the total labor hours for construction or renovation on most city projects over $1 million.

Craig Skotdal makes a speech after winning on Tuesday, April 22, 2025 in Tulalip, Washington. (Olivia Vanni / The Herald)
Craig Skotdal: Helping to breathe life into downtown Everett

Skotdal is the recipient of the John M. Fluke Sr. award from Economic Alliance Snohomish County

Paine Field Community Day returns Saturday, May 17

The youth-focused celebration will feature aircraft displays, talks with pilots and a variety of local food vendors.

Jonathon DeYonker, left, helps student Dominick Jackson upload documentary footage to Premier at The Teen Storytellers Project on Tuesday, April 29, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Everett educator provides tuition-free classes in filmmaking to local youth

The Teen Storyteller’s Project gives teens the chance to work together and create short films, tuition-free.

Kyle Parker paddles his canoe along the Snohomish River next to Langus Riverfront Park on Thursday, May 8, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Tip to Tip: Kyle Parker begins his canoe journey across the country

The 24-year-old canoe fanatic started in Neah Bay and is making his way up the Skykomish River.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

Kamiak High School is pictured Friday, July 8, 2022, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo police respond to stabbing at Kamiak High School

One juvenile was taken into custody in connection with Friday’s incident. A victim was treated at a hospital with non-life-threatening injuries.

A Mukilteo firefighter waves out of a fire truck. (Photo provided by Mukilteo Fire Department)
Mukilteo council places EMS levy lift on November ballot

The city is seeking the funds to cover rising costs. The local firefighters union opposes the levy lift.

Everett
Federal prosecutors: Everett men looked to sell 7 kilos of fentanyl

Prosecutors alleged the two men stored fentanyl and other drugs while staying in a south Everett apartment.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.