Whitehorse Trail rebuild project delayed

OSO — The timeline for rebuilding a stretch of the Whitehorse Trail wiped out by the deadly mudslide that tore through this community in March has been pushed back a year.

Officials need additional time for planning and permitting. Meanwhile, they continue to monitor river levels and multiple washouts along the trail.

The county originally hoped to rebuild the mile-long segment of trail this summer, parks and recreation director Tom Teigen said. After conversations with state and federal teams in late November, it became clear that such a timeline wasn’t realistic, he said.

Instead, the county aims to finish plans and paperwork in 2015, followed by construction of the trail in summer 2016. The goal is to install at least two new culverts to help manage water flow in the area, similar to the approach taken in rebuilding Highway 530 through the slide zone.

The county is working with the Federal Emergency Management Agency on trail repairs in the slide area. They need to factor an altered landscape and unpredictable river into their plans.

The mudslide that killed 43 people and destroyed the Steelhead Haven neighborhood also changed the behavior of the North Fork Stillaguamish River in ways that are still being studied. The Whitehorse Trail skirts and crosses the river and its tributaries in a number of places on the path’s 27-mile route from Arlington to Darrington. At least two spots along the trail have been washed out this year, including a stretch that parallels Highway 530 in the heart of Oso, just west of the community’s fire hall.

The washout happened days before Thanksgiving on a stretch of trail that borders Deer Creek, a tributary of the North Fork Stillaguamish. That segment of trail had to be closed, Teigen said. However, it’s near enough to the road and the shoulder is wide enough that locals who use the trail regularly have been able to get around.

“And we’re certainly not encouraging any non-locals to be up on that corridor in these winter months,” Teigen said.

There is another washout on the trail near Darrington that crews have been monitoring for a while, he said.

The U.S. Geological Survey has installed extra river gauges along the Stillaguamish to track water levels and help provide an alert for potential flooding.

“Lots of folks are watching it and we’re putting together a plan of action,” Teigen said.

Along with the gauges, rangers visited the trail near the latest washout in the days immediately after Thanksgiving, he said.

The trail has been a busy place for rangers and other workers during the last six months. Crews hired by Workforce Snohomish through federal emergency relief funds spent the summer cleaning up the trail. They cut back brush, cleaned out garbage and widened the walkway, especially near Fortson Mill, a key access point for the trail.

Though segments of the trail, particularly those with bridges, remain closed pending repairs and safety upgrades, the parks department is on its way to creating a continuous recreational path between Arlington and Darrington. Officials hope the route will become a boon for businesses in Arlington, Darrington and the communities in between, including Oso.

The effort has received some solid backing in the private sector as well. Teigen expects that at least two of the old, unstable bridges along the trail to be repaired and upgraded by the end of the year thanks to a $301,000 private donation.

“Crews are out replacing railings and decking right now with some of our donated funds,” Teigen said.

The trail is an old Burlington Northern Railroad line, and 14 bridges on the route are in need of updates.

Another donor gifted the county with 30 acres adjacent to the trail near Fortson Mill and the parking area there. The county signed off on the donation the day before Thanksgiving. It gave Teigen something extra to be thankful for, he said. The property can be used to improve access to the trail and draw more people to the location, though specific plans have not yet been made.

Kari Bray: kbray@heraldnet.com; 425-339-3439

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Alan Edward Dean, convicted of the 1993 murder of Melissa Lee, professes his innocence in the courtroom during his sentencing Wednesday, April 24, 2024, at Snohomish County Superior Court in Everett, Washington. (Ryan Berry / The Herald)
Bothell man gets 26 years in cold case murder of Melissa Lee, 15

“I’m innocent, not guilty. … They planted that DNA. I’ve been framed,” said Alan Edward Dean, as he was sentenced for the 1993 murder.

Bothell
Man gets 75 years for terrorizing exes in Bothell, Mukilteo

In 2021, Joseph Sims broke into his ex-girlfriend’s home in Bothell and assaulted her. He went on a crime spree from there.

A Tesla electric vehicle is seen at a Tesla electric vehicle charging station at Willow Festival shopping plaza parking lot in Northbrook, Ill., Saturday, Dec. 3, 2022. A Tesla driver who had set his car on Autopilot was “distracted” by his phone before reportedly hitting and killing a motorcyclist Friday on Highway 522, according to a new police report. (AP Photo/Nam Y. Huh)
Tesla driver on Autopilot caused fatal Highway 522 crash, police say

The driver was reportedly on his phone with his Tesla on Autopilot on Friday when he crashed into Jeffrey Nissen, killing him.

Boeing firefighters union members and supporters hold an informational picket at Airport Road and Kasch Park Road on Monday, April 29, 2024 in Everett, Washington. (Annie Barker / The Herald)
After bargaining deadline, Boeing locks out firefighters union in Everett

The union is picketing for better pay and staffing. About 40 firefighters work at Boeing’s aircraft assembly plant at Paine Field.

Andy Gibbs, co-owner of Andy’s Fish House, outside of his restaurant on Wednesday, May 1, 2024 in Snohomish, Washington. (Olivia Vanni / The Herald)
City: Campaign can’t save big tent at Andy’s Fish House in Snohomish

A petition raised over 6,000 signatures to keep the outdoor dining cover — a lifeline during COVID. But the city said its hands are tied.

A Tesla electric vehicle is seen at a Tesla electric vehicle charging station at Willow Festival shopping plaza parking lot in Northbrook, Ill., Saturday, Dec. 3, 2022. A Tesla driver who had set his car on Autopilot was “distracted” by his phone before reportedly hitting and killing a motorcyclist Friday on Highway 522, according to a new police report. (AP Photo/Nam Y. Huh)
After Stanwood man’s death, feds open probe into Tesla Autopilot feature

The National Highway Traffic Safety Administration was investigating Tesla’s recall on its vehicles with the Autopilot function.

Pacific Stone Company owner Tim Gray talks with relocation agent Dan Frink under the iconic Pacific Stone sign on Friday, May 3, 2024, in Everett, Washington. The business will be relocating to Nassau Street near the intersection of Marine View Drive and California Street. (Ryan Berry / The Herald)
Will readerboard romance on Rucker survive long-distance relationship?

Pacific Stone is moving a mile from Totem Diner, its squeeze with another landmark sign. Senior housing will be built on the site.

The site of a new Uniqlo store coming to Alderwood Mall in Lynnwood, Washington on May, 3, 2024. (Annie Barker / The Herald)
Clothing retailer Uniqlo to open Lynnwood store

Uniqlo, a Tokyo-based chain, offers clothing for men, women and children. The company plans to open 20 new stores this year in North America.

A dog looks up at its trainer for the next command during a training exercise at a weekly meeting of the Summit Assistance Dogs program at the Monroe Correctional Complex on Tuesday, Feb. 6, 2024 in Monroe, Washington. (Olivia Vanni / The Herald)
At Monroe prison, dog training reshapes lives of humans, canines alike

Since 2010, prisoners have helped train service animals for the outside world. “I don’t think about much else,” one student said.

James McNeal. Courtesy photo
Charges: Ex-Bothell council member had breakup ‘tantrum’ before killing

James McNeal was giving Liliya Guyvoronsky, 20, about $10,000 per month, charging papers say. King County prosecutors charged him with murder Friday.

Edmonds City Council members answer questions during an Edmonds City Council Town Hall on Thursday, April 18, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Edmonds wants to hear your thoughts on future of fire services

Residents can comment virtually or in person during an Edmonds City Council public hearing set for 7 p.m. Tuesday.

Girl, 11, missing from Lynnwood

Sha’niece Watson’s family is concerned for her safety, according to the sheriff’s office. She has ties to Whidbey Island.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.