Courthouse site a surprise to business owners

EVERETT — David Jolly’s Rockefeller Avenue law offices still smell new, thanks to a painstaking, top-to-bottom remodel completed last year.

In the building next door, elegant library shelves, wainscotting and swinging doors give attorney Royce Ferguson’s digs an unmistakable old-timey Everett feel.

Both buildings could be demolished in a year or so, following Snohomish County’s decision to build a new nine-story courthouse on an adjacent parking lot it already owns. The project would displace a half-dozen property owners who share the block, including attorneys, a bail bonds business and a legal messenger service.

Reactions to last week’s decision included resignation and anger.

“As a taxpayer I am outraged and as a building owner, I am absolutely devastated,” Jolly wrote Wednesday in an email to County Executive John Lovick. “Frankly, we feel duped and misled.”

In late September, the council had removed the parking lot option from consideration. That’s why it came as a shock to Jolly and some other affected property owners when it was added back in November.

The County Council on Nov. 25 voted 3-2 to build the courthouse there, on Wall Street between Oakes and Rockefeller avenues. The other choice was the plaza in front of the existing 1960s-era courthouse, about a block west on the other side of Wall Street.

At $150 million, the base price for the parking lot option is an estimated $30 million more than constructing a similar building next to the current courthouse. Security, energy-conservation and other features added another $12 million to the total price.

To pay for it, the council approved a property tax increase that will cost an average homeowner about $20 more per year.

Councilman Brian Sullivan supported the parking lot site. He remains comfortable with the decision, even with the consequences for the neighboring business owners.

“In the end, this really was the best decision,” Sullivan said.

The alternative would have erected the new building within about six feet of the old courthouse, while it remained up and running.

“There’s no doubt that it would have made it disruptive for the courts during the construction process,” he said.

In Sullivan’s opinion, temporarily relocating the courts while a new courthouse was built on site would have been too expensive.

The legal businesses aren’t the only parts of the landscape that will have to make room for the new court building.

The 100 spaces in the county parking lot would go away during construction. The new building would have a parking garage.

Additionally, the county will have to rebuild Matthew Parsons Park on the corner of Wall Street and Rockefeller. Built in 1999, the park was named in honor of a child homicide victim who was beaten into a coma at age 12 and died several years later.

“We know this park is important to many people in our community,” said Rebecca Hover, Lovick’s spokeswoman. “We want to respect that as well as continue to honor the memory of Matthew Parsons.”

The demolition and eventual redevelopment of the old courthouse also would force the relocation of the veterans memorial in the courthouse plaza. The courthouse design process will look into options for how to go about that.

Tour the law offices on Rockefeller, and it becomes obvious that the attorneys’ objections to being displaced are more than courtroom theatrics.

Ferguson moved in about 20 years ago and set about overhauling the one-story building to complement its surroundings, including bricks to match the church across the street.

Inside, a law library is filled with heavy tomes, in an age when many colleagues have gone digital. Framed pictures and newspaper articles on the wall provide windows into the region’s past — and some high points in Ferguson’s legal career.

“We didn’t want it to look brand new,” Ferguson said. “We knew we were going to be here a long time.”

Cec Tennessen worked as Ferguson’s secretary even before they relocated here from a downtown office building.

“So much better, here, so much better,” she said.

Tennessen helps people who walk in off the street, trying to navigate the county courthouse a half block away. In spring, she fills the building’s sidewalk planters with flowers.

Ferguson had wanted to stay for a few more years, until retiring. Now he’s resigned to that not happening.

“You’ve heard it before: You can’t fight city hall,” he said.

Janean Jolly manages the office for husband David Jolly. They lease space to six other attorneys.

They bought the building from a printing business last year and gutted it. By the time they were through, they’d spent nearly $500,000. They expected to measure their future there in terms of decades, not months.

“We put a lot of our time, our money and our heart into it,” Janean Jolly said. “Our whole retirement is in this building.”

Also affected are the law offices of Brian M. Sullivan, not to be confused with the county councilman, Brian J. Sullivan.

“This is where I was hoping to get wheeled out in my 80s when I croaked,” said Sullivan, the attorney. “I really just saw myself in here until I died.”

Brian M. Sullivan and the Jollys said they were skeptical about the county’s plans to get rid of the old courthouse, a place with which they’re intimately acquainted.

“I go to the courthouse all the time,” Sullivan said. “I see people in shackles all the time. I’ve never felt unsafe. The staff does a fantastic job.”

David Jolly said the county’s concerns, particularly safety, could have been addressed with a new building on the plaza next to the old courthouse. Tax money for the more expensive site would have been better used to hire police or deputy prosecuting attorneys, he said.

In his email to the county executive, Jolly urged Lovick to veto the council-backed plan. During the budget process, however, Lovick told the council he would support whatever choice they made. He did not endorse one site over the other.

For now, the Jollys are hiring attorneys of their own as they prepare to negotiate with the county over the price of their building.

“We expect that to be a real battle,” David Jolly said.

Sullivan, the councilman, said making sure the property owners get the best possible deal will be a top priority.

Deputy Executive Mark Ericks also promised staff would “figure out a way to make it fair for them.” Moreover, it’s the law, he said.

The county expects to acquire the properties next year. Under the current timeline, most of the construction would take place in 2015 and 2016, with staff able to move in at some point in 2017.

It’s unknown whether the county will demolish the old courthouse right away. The adjacent Mission Building, the courthouse built in 1911, will be preserved.

Noah Haglund: 425-339-3465; nhaglund@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

(City of Everett)
Everett’s possible new stadium has a possible price tag

City staff said a stadium could be built for $82 million, lower than previous estimates. Bonds and private investment would pay for most of it.

Jennifer Humelo, right, hugs Art Cass outside of Full Life Care Snohomish County on Wednesday, May 28, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
‘I’ll lose everything’: Snohomish County’s only adult day health center to close

Full Life Care in Everett, which supports adults with disabilities, will shut its doors July 19 due to state funding challenges.

The age of bridge 503 that spans Swamp Creek can be seen in its timber supports and metal pipes on Wednesday, May 15, 2024, in Lynnwood, Washington. The bridge is set to be replaced by the county in 2025. (Ryan Berry / The Herald)
Snohomish County report: 10 bridges set for repairs, replacement

An annual report the county released May 22 details the condition of local bridges and future maintenance they may require.

The Edmonds City Council gathers to discuss annexing into South County Fire on Tuesday, Dec. 3, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Community group presents vision for Edmonds’ fiscal future

Members from Keep Edmonds Vibrant suggested the council focus on revenue generation and a levy lid lift to address its budget crisis.

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in unincorporated Snohomish, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

People listen as the Marysville School Board votes to close an elementary and a middle school in the 2025-26 school year while reconfiguring the district’s elementary schools to a K-6 model on Wednesday, Jan. 22, 2025 in Marysville, Washington. (Olivia Vanni / The Herald)
Marysville schools audit shows some improvement

Even though the district still faces serious financial problems, the findings are a positive change over last year, auditors said.

Outside of the Madrona School on Monday, Aug. 26, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Sewer district notifies Edmonds schools of intent to sue

The letter of intent alleges the school district has failed to address long-standing “water pollution issues” at Madrona K-8 School.

Raul Benitez Santana in the courtroom Wednesday. (Will Geschke / The Herald)
Jury convicts driver in death of Washington State Patrol trooper

The jury took four hours Wednesday to find Raul Benitez Santana guilty of vehicular homicide and vehicular assault.

Lake Stevens honors council member who died in office

Marcus Tageant, 52, served on the Lake Stevens City Council for more than a decade. He died on May 26.

Community members gather for the dedication of the Oso Landslide Memorial following the ten-year remembrance of the slide on Friday, March 22, 2024, at the Oso Landslide Memorial in Oso, Washington. (Ryan Berry / The Herald)
The Daily Herald garners 6 awards from regional journalism competition

The awards recognize the best in journalism from media outlets across Alaska, Idaho, Montana, Oregon and Washington.

Edmonds Mayor Mike Rosen goes through an informational slideshow about the current budget situation in Edmonds during a roundtable event at the Edmonds Waterfront Center on Monday, April 7, 2025 in Edmonds, Washington. (Olivia Vanni / The Herald)
Edmonds mayor recommends $19M levy lid lift for November

The city’s biennial budget assumed a $6 million levy lid lift. The final levy amount is up to the City Council.

Amit B. Singh, president of Edmonds Community College. 201008
Edmonds College and schools continue diversity programs

Educational diversity programs are alive and well in Snohomish County.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.