I-405 tolls top estimate, but real value is long-term gains

Back in black? Depends on how you define the baseline.

In the first three months of operation, express toll lanes on I-405 brought in $3.7 million in toll revenue — three times the conservative $1 million estimate used for planning by the Washington State Department of Transportation.

That’s more than enough to cover the costs of operations so far.

But some key expenses have yet to kick in.

And while there are a lot of zeroes in that figure, tolling revenue is hardly a windfall (so far).

To put it in perspective, the overall $2.7 million net revenues is only a fraction of the total $463 million price to expand the highway south of Highway 522 and install toll equipment in the first place — 0.58 percent, to be precise.

At that pace, it would take over 40 years to pay off an equivalent project.

The vast majority of that $463 million was for various widening projects along the corridor. The tolling part of the project was $111 million, about 24 percent of the total. If we look only at the tolling portion of the project, toll revenues at the current pace would pay off the project in about a decade.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

In the long run, that’s not insignificant.

Tolling adds another stream of revenue to back the long-term debt payments required for major projects.

Tolling revenue from I-405 is kept in a separate account to be used on I-405 projects.

First up is expanding toll lanes south, for a total of 40 miles, to connect with similar lanes on Highway 167 south of Renton. A little over 18 percent of the total $1.1 billion cost of that project is expected to be covered by toll-backed funds. The rest comes from traditional funding sources, including the gas tax.

That all assumes the Legislature doesn’t dump tolling after its first two years, of course.

And operating in the black isn’t the only standard of success if you’re a commuter stuck in traffic that’s worse than before tolls.

If traffic doesn’t improve, opponents promise they’ll keep hacking away at “the snake oil of congestion reduction.”

Read more about the current financial statement for the toll lanes and how to understand them on the WSDOT Blog, at wsdotblog.blogspot.com.

Have a question? Email us at streetsmarts@heraldnet.com. Please include your first and last name and city of residence. Look for updates on the Street Smarts blog.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Jennifer Humelo, right, hugs Art Cass outside of Full Life Care Snohomish County on Wednesday, May 28, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
‘I’ll lose everything’: Snohomish County’s only adult day health center to close

Full Life Care in Everett, which supports adults with disabilities, will shut its doors July 19 due to state funding challenges.

(City of Everett)
Everett’s possible new stadium has a possible price tag

City staff said a stadium could be built for $82 million, lower than previous estimates. Bonds and private investment would pay for most of it.

The Edmonds City Council gathers to discuss annexing into South County Fire on Tuesday, Dec. 3, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Community group presents vision for Edmonds’ fiscal future

Members from Keep Edmonds Vibrant suggested the council focus on revenue generation and a levy lid lift to address its budget crisis.

The age of bridge 503 that spans Swamp Creek can be seen in its timber supports and metal pipes on Wednesday, May 15, 2024, in Lynnwood, Washington. The bridge is set to be replaced by the county in 2025. (Ryan Berry / The Herald)
Snohomish County report: 10 bridges set for repairs, replacement

An annual report the county released May 22 details the condition of local bridges and future maintenance they may require.

People listen as the Marysville School Board votes to close an elementary and a middle school in the 2025-26 school year while reconfiguring the district’s elementary schools to a K-6 model on Wednesday, Jan. 22, 2025 in Marysville, Washington. (Olivia Vanni / The Herald)
Marysville schools audit shows some improvement

Even though the district still faces serious financial problems, the findings are a positive change over last year, auditors said.

Outside of the Madrona School on Monday, Aug. 26, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Sewer district notifies Edmonds schools of intent to sue

The letter of intent alleges the school district has failed to address long-standing “water pollution issues” at Madrona K-8 School.

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in unincorporated Snohomish, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

Logo for news use featuring the municipality of Mukilteo in Snohomish County, Washington. 220118
Mukilteo police locate dead body near Olympic View Middle School

At around 7 a.m. Thursday, officers responded to reports of an individual with possible injuries.

SMART concludes investigation into police use of force used in pursuit

Results of the investigation into the death of Payton Michaels were forwarded to the Snohomish County Prosecutor’s Office for review.

Providence Regional Medical Center Everett. (Olivia Vanni/The Herald)
Providence Everett plans 25% cut to nursing assistant staffing

The reduction, effective July 11, will affect all 39 per diem nursing assistants and 80 full-time and part-time assistants.

The Musical Mountaineers perform at Everett’s McCollum Park on June 14, 2025. (Photo courtesy of Adopt A Stream Foundation)
Photo courtesy of Adopt A Stream Foundation
The Musical Mountaineers perform at Everett’s McCollum Park on June 14.
Coming events in Snohomish County

Send calendar submissions for print and online to features@heraldnet.com. To ensure your… Continue reading

Lynnwood Mayor Christine Frizzell and Lynnwood City Council Member David Parshall along with others involved in the renovation of Scriber Lake Park explore the new boardwalk on Wednesday, June 4, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Lynnwood cuts the ribbon to new Scriber Lake Park boardwalk

The new boardwalk provides year-round, ADA accessibility to the city’s only public lake.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.