Factory-built Marysville schools get attention from other districts

TULALIP — John Bingham walked through the carpeted halls of the administration building on the Marysville Secondary Campus.

A handful of school officials from central Washington followed him. They felt the walls, tapped the floor and snapped photos of the hallway, which like the three schools that surround it, was built in a factory.

“You don’t have that drumming you normally get when you walk into a portable,” said Bingham, capital projects director for the Marysville School District. “People don’t want to feel like they’re in portables.”

When the Marysville Secondary Campus opened last spring, it made history as the first major public school project built from manufactured housing in Washington. Except for the gymnasium, which was built from the ground up, the entire campus was constructed in a factory and trucked to its home on the Tulalip Reservation.

The three schools on the site — Tenth Street middle school, Heritage High School and Marysville Arts &Technology High School — were built much faster and cheaper than traditional schools, Bingham said. And the state doesn’t count portable classrooms when it determines funding for school construction. That means these classrooms won’t affect the amount of state funding the Marysville district can qualify for in the future.

Since the campus has opened, Bingham has led more than a dozen groups from school districts across the state on tours of the modular schools and the Marysville factory where they were built. The tour now also includes a stroll through Grove Elementary, which opened in September that combined a “stick-built” portion with eight portables camouflaged into the design. The district tried to make the portable classrooms mirror rooms in the “stick-built” portion and even surrounded them with bricks to make them blend in. The district owns the design plans for Grove and plans to replicate the layout in future schools, Bingham said.

The financial advantages to manufactured housing are substantial. Construction is cheaper and the state doesn’t factor portables into districts’ construction funding formula. So, for example, if the secondary campus contained conventional schools instead of modular ones, the district wouldn’t qualify for as much state funding for future construction projects.

School funding laws were crafted with the traditional brick-and-mortar schools in mind. Because of the Marysville Secondary Campus and moves by other districts away from traditional new schools to classrooms in leased spaces or public-private partnerships, the Office of Superintendent of Public Instruction is considering rewording the laws, said Jeanne Rynne, OSPI’s regional coordinator for Northwest Washington.

“This is the first time OSPI has come across this type of structure in K-12, so we’re still figuring it out,” she said. “We haven’t come up with a firm stance one way or another, but I think we’re going to have to look at that. It’s obviously out there now.”

The district is paying the secondary campus’s $25 million price tag with mitigation fees builders pay when they develop land.

Inspired by the secondary campus and looking to cut down on costs, the Warden School District in central Washington is thinking about using manufactured housing to construct a new cafeteria and locker rooms.

“I love it,” said Warden Superintendent Sandra Sheldon, after touring the secondary campus Friday. “The thing that’s really hard to express to people unless they see it, is that it’s modular, but it’s not like the old portables. Everybody thinks of modular as the old portables and everyone knows that’s not the best teaching space.”

When designing the schools, Marysville administrators tried to create spaces that didn’t seem like manufactured housing. One-third of the public school students in Marysville attend class in the district’s 110 portables, said Jim Baker, executive director of finance. Administrators wanted the secondary campus to feel different, he said.

They upgraded from the standard materials and designed portables that fit together to make schools with open spaces, bathrooms and locker rooms. The four buildings on the campus are made up of a total of more than 200 portables. Like traditional schools, they are expected to last 30 years before they need a major renovation, Baker said.

“I totally expect this facility to be around just as long as a conventionally built building,” he said, as he walked through Marysville Arts &Technology High School.

Baker and Bingham know that many people look down on manufactured housing, but they insist the secondary campus isn’t second-rate.

The proof is in the schools, they say.

Reporter Kaitlin Manry: 425-339-3292 or kmanry@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

A Flock Safety camera on the corner of 64th Avenue West and 196th Street Southwest on Oct. 28, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Everett seeks SnoCo judgment that Flock footage is not public record

The filing comes after a Skagit County judge ruled Flock footage is subject to records requests. That ruling is under appeal.

Information panels on display as a part of the national exhibit being showcased at Edmonds College on Nov. 19, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Edmonds College hosts new climate change and community resilience exhibit

Through Jan. 21, visit the school library in Lynnwood to learn about how climate change is affecting weather patterns and landscapes and how communities are adapting.

Lynnwood City Council members gather for a meeting on Monday, March 17, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Lynnwood raises property, utility taxes amid budget shortfall

The council approved a 24% property tax increase, lower than the 53% it was allowed to enact without voter approval.

Lynnwood
Lynnwood hygiene center requires community support to remain open

The Jean Kim Foundation needs to raise $500,000 by the end of the year. The center provides showers to people experiencing homelessness.

Logo for news use featuring Snohomish County, Washington. 220118
Vending machines offer hope in Snohomish County in time for the holidays.

Mariners’ radio announcer Rick Rizzs will help launch a Light The World Giving Machine Tuesday in Lynnwood. A second will be available in Arlington on Dec. 13.

UW student from Mukilteo receives Rhodes Scholarship

Shubham Bansal, who grew up in Mukilteo, is the first UW student to receive the prestigous scholarship since 2012.

Roger Sharp looks over memorabilia from the USS Belknap in his home in Marysville on Nov. 14, 2025. (Will Geschke / The Herald)
‘A gigantic inferno’: 50 years later, Marysville vet recalls warship collision

The USS Belknap ran into the USS John F. Kennedy on Nov. 22, 1975. The ensuing events were unforgettable.

Logo for news use featuring Snohomish County, Washington. 220118
Snohomish County man files suit against SIG SAUER over alleged defect in P320

The lawsuit filed Monday alleges the design of one of the handguns from the manufacturer has led to a “slew of unintended discharges” across the country.

The Everett City Council on Oct. 22, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Everett approves $613 million budget for 2026

No employees will be laid off. The city will pause some pension contributions and spend one-time funds to prevent a $7.9 million deficit.

Logo for news use featuring Snohomish County, Washington. 220118
2 Snohomish County men charged with internet-related child sexual abuse

Over the past two months, three men were charged in federal court after defendants allegedly used the internet to contact victims or obtain child sexual abuse material.

An excavator moves a large bag at the site of a fuel spill on a farm on Nov. 19, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
BP’s Olympic Pipeline fully restarts after 2-week shutdown

The oil giant has recovered 2,300 gallons of oil so far at the site of the leak east of Everett.

Judy Tuohy, the executive director of the Schack Art Center, in 2024. (Olivia Vanni / The Herald)
Director of Everett’s Schack Art Center announces retirement

Judy Tuohy, also a city council member, will step down from the executive director role next year after 32 years in the position.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.