Federal memo criticizes nuclear cleanup contractor

YAKIMA — The company hired to design and build a massive plant at the nation’s most contaminated nuclear site should no longer have authority over its design, according to an internal U.S. Department of Energy memo released Tuesday.

The memo raises more questions about a waste treatment plant project long viewed as critical to ridding the Pacific Northwest of pollutants left from decades of weapons production for the nation’s nuclear arsenal, but one that has endured countless technical problems, delays and skyrocketing costs.

It also raises more concerns about the contractor at the center of the mix, Bechtel National Inc., which has come under fire in recent months from critics who say the company has suppressed employee concerns related to the plant’s safety and retaliated against whistleblowers.

The memo noted 34 instances where Bechtel National provided information that was incorrect, technically unfeasible or failed to provide the best value to the government, among other things, while designing the $12.3 billion plant at south-central Washington’s Hanford nuclear reservation.

“The behavior and performance of Bechtel Engineering places unnecessarily high risk that the WTP design will not be effectively completed,” Gary Brunson, the Energy Department’s engineering director assigned to the project, said of the waste treatment plant in a memo to top Energy Department managers Thursday.

The federal government created Hanford in the 1940s as part of the top-secret Manhattan Project to build the atomic bomb, and the site continued to produce plutonium for nuclear weapons through the Cold War. Today, it is the nation’s most contaminated nuclear site, with cleanup expected to last decades.

“This memo details exhaustive and disturbing evidence of why Bechtel should be terminated from this project and subject to an independent investigation,” Tom Carpenter, executive director of Hanford Challenge, a watchdog group that monitors cleanup efforts, said in a statement.

Bechtel project director Frank Russo said the findings highlight how the project — and the demands on the contractor — have changed in the past decade, rather than failures by the company.

Russo said the company and the Energy Department have hired hundreds of consultants who are experts in their fields to review calculations and design decisions for a project where the available information is constantly changing — including the cost and scope.

“If we ignore new information, we can finish it on price and we can finish it on schedule, and it would look like an ideal project that would make some people happy,” he said. “But if we review new information as it becomes available, it’s not failure.

“The reality is that this project has a huge element of science and a huge element of research involved before (the Energy Department) decides it has enough information to make a decision,” he said. “And when that happens, there will always be groups of people who believe it’s a wrong decision.”

Long considered the cornerstone of Hanford cleanup, the waste treatment plant is being built to convert millions of gallons of highly radioactive waste into a stable glass form. The waste is currently stored in underground tanks, many of which have leaked into the groundwater, threatening the neighboring Columbia River.

The plant’s unresolved issues include inadequate mixing of the waste, which could lead to a buildup of flammable gases or a small risk of creating a nuclear reaction inside the plant, and whether the rate of corrosion in piping and vessels will hold the radioactive waste. The issues are of particular concern because workers will be barred from entering highly radioactive areas of the plant — and repairing potential problems — once it is operating under the current design.

Design of the plant is 85 percent complete, and construction is more than 50 percent complete.

The plant had been scheduled to begin operating in 2019, but the Energy Department has said a new estimate on the plant’s start date and cost will be pushed off for a least a year while it embarks on additional tests to resolve those problems.

The Energy Department said in a statement Tuesday that it was reviewing Brunson’s memo and continues to work with Bechtel to address ongoing technical issues, though it continues to be frustrated with the lack of progress.

“Addressing these challenges effectively will require both additional work by the contractor, as well as improved oversight by the department,” the statement said. “It’s also important to note that the successful completion of this important project depends on employees continuing to be able to freely raise concerns.”

The federal government spends roughly $2 billion each year for Hanford cleanup, $690 million of which goes toward the plant.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

The Sana Biotechnology building on Tuesday, Aug. 19, 2025 in Bothell, Washington. (Olivia Vanni / The Herald)
Bothell loses planned biotechnology manufacturing plant

New biotechnology manufacturing jobs in Bothell are on indefinite hold.

Two troopers place a photo of slain Washington State Patrol trooper Chris Gadd outside district headquarters about 12 hours after Gadd was struck and killed in a crash on southbound I-5 on March 2 in Marysville. (Ryan Berry / The Herald)
One More Stop targets drunk driving this weekend in honor of fallen trooper

Troopers across multiple states will be patrolling from 4 p.m. Friday to 5 a.m. Monday.

Students walk outside of Everett High School on Wednesday, Sept. 17, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
SnoCo students perform well on metrics, state data shows

At many school districts across the county, more students are meeting or exceeding grade-level standards compared to the state average.

Customers walk in and out of Fred Meyer along Evergreen Way on Monday, Oct. 31, 2022 in Everett, Washington. (Olivia Vanni / The Herald)
Everett council rebukes Kroger for plans to close Fred Meyer store

In the resolution approved by 6-1 vote, the Everett City Council referred to store closure as “corporate neglect.”

Logo for news use featuring the municipality of Arlington in Snohomish County, Washington. 220118
A divided Arlington City Council votes to reduce SkyFest grant by half

After months of debate over lodging tax funds, the council voted 4-3 to award the popular aviation event $20,000.

Logo for news use featuring the municipality of Stanwood in Snohomish County, Washington. 220118
Stanwood jail costs expected to exceed budget by end of 2025

As of September, the Stanwood police has spent $53,078 of its $59,482 annual jail budget.

Alex Waggoner is handcuffed after being sentenced to 19 years for the murder of Abdulkadir Shariif Gedi on Wednesday, Sept. 17, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Edmonds man sentenced to more than 19 years for death of rideshare driver

Judge Richard Okrent sentenced Alex Waggoner, 23, Wednesday after a jury earlier found him guilty of murder in the 2nd degree.

Snohomish County Sheriff's Office K-9 vehicle along U.S. 2 where a man was shot on Wednesday, Sep. 17, 2025, in Sultan, Washington. (Snohomish County Sheriff's Office)
Suspect arrested in King County after person shot near Sultan along US 2

The assault investigation closed down east and westbound lanes of U.S. 2 Wednesday afternoon.

A person walks past the freshly painted exterior of the Everett Historic Theatre on Sept. 24, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre reopens with a new look and a new owner

After a three-month closure, the venue’s new owner aims to keep the building as a cultural hub for Everett.

Local colleges see fewer international students as fall quarter begins

Edmonds College saw a 25% decrease in new international student enrollment, citing visa appointment difficulties.

Cutting the ribbon to celebrate recent upgrades at the Sultan Wastewater Treatment Plant on Sept. 24. (Provided photo)
Sultan celebrates new park and treatment plant upgrades

Two ribbon-cuttings occurred with the community and elected officials from the city, county and state.

The Washington State University Everett campus on Wednesday, July 25, 2018 in Everett, Wa. (Olivia Vanni / The Herald)
Everett allocates funding toward north Broadway bridge design

The $2.5 million in grant dollars will pay for the design of a long-awaited pedestrian bridge near Everett Community College.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.