Leaks found in some pontoons for Seattle bridge

SEATTLE — Small cracks have appeared in at least two the first six pontoons built for a new floating bridge in Lake Washington, but transportation officials said Friday the problem is manageable.

Leaks can be repaired and changes made in the construction of 61 remaining pontoons, said Steve Pierce, a spokesman for the Washington Department of Transportation.

Washington Gov. Chris Gregoire said she wants an independent expert panel to review the safety of pontoons.

Construction flaws were found in the first pontoons floated out of dry-dock in Aberdeen after being built, KOMO-TV reported Thursday after reviewing transportation department video and documents.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Also on Thursday, department Secretary Paul Hammond announced changes in the pontoon construction team to improve oversight and coordination. The changes were part of a review of the first cycle of pontoons that the agency conceded shows more cracking than expected.

The state has not yet accepted any of the pontoons from the contractor. The equipment will have to meet specifications for the new bridge expected to be completed in 2014 and last 75 years.

“We won’t accept the pontoons from out contractors until we are satisfied they meet contract specifications,” Hammond said in her statement.

The new bridge will replace an existing 49-year-old bridge that officials say is vulnerable to an earthquake.

The planned, six-lane bridge is the centerpiece of a 13-mile project costing more than $4 billion to improve Highway 520 between Seattle and its eastern suburbs.

It’s difficult to confirm whether more than two pontoons were leaking because of temporary ballast water added for balancing, residual water left from concrete curing, missing plugs for bolt sleeves, and hatch doors being left open, Pierce said.

An inspection of the pontoons was continuing.

“These are manageable issues,” Pierce said.

Some of the leaks are related to cracks that developed during construction because of interior cables that are tightened for strength, Pierce said.

Changes in construction have been made and experts are reviewing the process for possible changes, he said.

The transportation department is particularly concerned about pontoon W, the big end piece on the east side of the bridge, The Seattle Times reported.

Some of the cracks are superficial and some are structural, said Mike Cotton, a design-build manager for the department.

Water hasn’t been streaming in, but some cracks have allowed absorption and condensation so water appears inside the pontoon, he said.

Washington has three floating bridges that are among the longest in the world — two on Lake Washington and one across salt water on Hood Canal.

In 1990, the I-90 floating bridge on Lake Washington sank in a storm because some hatches had been left uncovered during renovation.

In 1979, half of the Hood Canal bridge sank in a windstorm.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

Snohomish County 911 Executive Director Kurt Mills talks about the improvements made in the new call center space during a tour of the building on Tuesday, May 20, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
New 911 center in Everett built to survive disaster

The $67.5 million facility brings all emergency staff under one roof with seismic upgrades, wellness features and space to expand.

Students, educators speak out against Early Learning Center closure

Public commenters criticized Everett Community College for its handling of the closure. The board backed the move, citing the center’s lack of funding.

A ferry passes by as Everett Fire Department, Everett Police and the U.S. Coast Guard conduct a water rescue for a sinking boat in Possession Sound off of Howarth Park on Wednesday, May 21, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Boat sinks in Possession Sound near Howarth Park

A good Samaritan rescued one person. Crews continued a search for three others.

Gov. Bob Ferguson’s signature on the the 1,367 page document outlining the state’s 2025 operating budget. (Photo by Jacquelyn Jimenez Romero/Washington State Standard)
Ferguson signs budget boosting Washington state spending and taxes

The governor used his veto pen sparingly, to the delight of Democrats and the disappointment of Republicans.

Madison Family Shelter Family Support Specialist Dan Blizard talks about one of the pallet homes on Monday, May 19, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Madison Family Shelter reopens after hiatus

The Pallet shelter village, formerly Faith Family Village, provides housing for up to eight families for 90 days.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.