Ready for roadwork?

  • By Bill Sheets Herald Writer
  • Wednesday, April 20, 2011 12:01am
  • Local News

LYNNWOOD — A busy highway construction season this year will mean some delays and lane closures but better traffic flow and safety when it’s all done, state transportation officials say.

Significant work is planned for the entire Puget Sound region. More than $370 million in projects are pla

nned for Snohomish County alone.

Biggies include widening of Highway 522 south of Monroe; repairs to girders on the U.S. 2 trestle near Everett; and continued work on new ramps where I-5 and I-405 intersect in Lynnwood.

Some of the work began last year and will continue through part of this year or beyond. Some closures will be needed and drivers should plan ahead and drive cautiously through construction zones, officials said.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Major regional projects include the early stages of the $4.5 billion replacement of the Highway 520 floating bridge across Lake Washington, and the $3.1 billion tunnel along the Seattle waterfront to replace the Alaskan Way Viaduct.

These two Seattle mega-projects are being financed with federal funds and planned tolls, in addition to state gas tax money.

State money for all the projects comes from two increases in the state gas tax: a hike of 5 cents per gallon in 2003 and an increase of 9.5 cents per gallon approved in 2005, phased in over four years.

Backed by these tax hikes, the state sold $15.5 billion in bonds to get the projects started quickly, state Transportation Secretary Paula Hammond said Tuesday.

Now, that money is beginning to run out. The tax money is still going toward paying off the bonds, she said.

Federal tax dollars also are beginning to dry up.

“What’s next?” she said. “How do we fund our transportation system for the future?”

The bond money was targeted for 421 projects, Hammond said. About 300 are done and nearly 50 more have begun, meaning 84 percent of the bond money backed by the tax hikes has been spent or is being spent.

“We’re living on it and we’ve spent it,” Hammond said.

Bill Sheets: 425-339-3439; sheets@heraldnet.com.

Major road projects in Snohomish County

Highway 522 widening, Snohomish River Bridge to U.S. 2, Monroe

Cost: $159.5 million

Start: Late spring 2011

Finish: Fall 2014

Highway 9 widening, 212th Street SE to 176th Street SE, Clearview

Cost: $87.3 million

Start: Summer 2011

Finish: Fall 2013

Ebey Slough Bridge, Highway 529, Marysville

Cost: $42.3 million

Start: July 2010

Finish: Late 2013

I-5, I-405 merging ramps, Lynnwood

Cost: $33.8 million

Start: August 2010

Finish: December 2011

U.S. 2 at Highway 522, connecting ramp, Monroe

Cost: $22.8 million

Start: June 2010

Finish: Summer 2012

Highway 9 widening, Lundeen Parkway to Highway 92, Lake Stevens

Cost: $22.5 million

Start: July 2010

Finish: December 2011

U.S. 2 trestle girder repair, Everett

Cost: $8 million

Start: Spring-summer 2011

Finish: Late fall 2011

I-5, Everett to Marysville, repaving, installing cameras and electronic signs

Cost: $2.9 million

Start: Spring-summer 2011

Finish: Late fall 2011

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

The Everett City Council on Wednesday, April 16, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Everett City Council approves apprenticeship ordinance

The new ordinance builds upon state law, requiring many city public works contracts to use at least 15% apprentice labor.

Logo for news use featuring the municipality of Stanwood in Snohomish County, Washington. 220118
Stanwood nears completion of deployable floodwall

The new floodwall will provide quick protection to the downtown area during flood conditions.

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

Steven M. Falk / The Philadelphia Inquirer / Tribune News Service
James Taylor plays Sunday and Monday at Chateau Ste. Michelle in Woodinville.
A&E Calendar for May 22

Send calendar submissions for print and online to features@heraldnet.com. To ensure your… Continue reading

Members of Washington State patrol salute the casket of slain trooper Chris Gadd during a memorial cremony on Tuesday, March 12, 2024, at Angel of the Winds Arena in Everett, Washington. (Ryan Berry / The Herald)
Opening statements begin in trial of man charged in crash of WSP trooper

Deputy prosecutor described to jurors what began as a routine patrol for Christopher Gadd — “until it wasn’t.”

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.