Skagit bridge moving fast; why not other roadwork?

OLYMPIA — The swiftness with which the state is repairing the I-5 bridge in Skagit County is fueling interest among lawmakers to construct all highway projects with similar speed.

A bill introduced Friday directs the state Department of Transportation to handle permitting and environmental decision-making more expeditiously to save time and money.

State lawmakers had already taken a step in that direction before the 160-foot segment of the bridge crumbled into the water, approving a study on how Washington can complete its road projects cheaper and faster. The $325,000 analysis, which is due in December, is part of the transportation budget passed in April.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

“Realistically, we need to look at why, if we can do this (bridge repair project) in a couple of weeks, does it take us so long when we’re doing other projects,” said Sen. Curtis King, R-Yakima, a co-chair of the Senate Transportation Committee. “If we don’t take a look at it and learn from it, we’re not doing our jobs.”

This conversation is revving up partly in response to Skagit County where the bridge fell into the river after it was hit by a truck carrying an oversize load. Two vehicles fell into the river, but no one was seriously injured.

Constructions crews started working around the clock Saturday to open a temporary span in a matter of days. They had been waiting for the National Transportation Safety Board to finish up its investigation on the site.

A permanent fix is supposed to be in place no later than Oct. 1; a contract will be issued June 19. The state will pay $10 million for the short-term fix; there is not an estimate yet for the cost of the permanent solution.

These two projects are getting done in less than five months because this is an emergency situation, state transportation officials said. An entirely new bridge would require much more time, they acknowledged.

When Gov. Jay Inslee declared an emergency following the May 23 collapse it enabled most of the procedural playbook to be discarded, said DOT spokesman Travis Phelps.

The declaration suspended compliance with the State Environmental Policy Act, which can lead to time-consuming analyses on the potential effects of a project.

It also allowed the state to obtain permits verbally to remove debris from the water and work along the shoreline, though permit paperwork must be filed by the end of June.

And DOT officials can sidestep formal written notifications to leaders of state and federal agencies and area tribes about the plans for the projects. Rather, they can meet at the site to look at drawings or talk on the phone about concerns and objections.

“It’s not like we’re just putting blinders on and plowing forward,” Phelps said. “We value the public input. But when you have something of an emergency nature like this you need to have the flexibility to move. Our goal is to restore I-5 to its previous functionality.”

State transportation officials are in regular contact with the Swinomish and Upper Skagit tribes and representatives of federal agencies including the Fish and Wildlife, National Oceanic and Atmospheric Administration, Federal Highway Administration, Army Corps of Engineers and Coast Guard.

They also are keeping several state agencies up to date, including the Department of Archaeology and Historic Preservation, the Department of Ecology, the Department of Natural Resources and state Fish and Wildlife. Within DOT there is a special environmental protection division that is summoned as well.

Thus far there have been no objections raised by any agency or tribe to the scope of manner of the work, Phelps said.

What’s transpired in Skagit County is bolstering Republican-inspired efforts in the House for revamping the transportation construction process.

“We have got to have reforms in Washington state that will leverage tax dollars more effectively,” said Rep. Norma Smith, R-Clinton.

The chairwoman of the House Transportation Committee said the study should spur changes.

A consultant will figure out what existing policies and practices drive up costs the most in Washington then see if other states face the same challenges and if not, why not. They will also compare what Washington pays for large transportation projects with what other states pay for comparable undertakings.

Lawmakers want to know if the state does pay more and take longer, an often heard criticism of the Department of Transportation contend.

“There is a perceived problem,” said Carrie Dolwick, policy director for Transportation Choices Coalition. “Let’s figure out if there is a problem and what’s causing it then we can come up with solutions to address it.”

Rep. Judy Clibborn, D-Mercer Island, warned it may point out lawmakers are part of the problem by their inaction or, in some cases, changing the rules from one session to the next.

“The process that we have goes on and on and on and the problem is us — the Legislature, the City Councils, the people,” she said. “We just don’t make the decision and move forward. We rethink it 15 times.”

King agreed.

“There are times when we’ve been our own worst enemy,” he said. “Are we like a doctor that overmedicates? Are we like a doctor that overtreats? Are we too cautious?”

Clibborn cautioned against thinking reforms can be made easily. Resistance will surface to altering or removing ingredients of the current process, she said.

“The minute we start talking about changing environmental rules or the public review process we run into a buzz saw,” she said. “It’s not easy to change.”

Jerry Cornfield: 360-352-8623; jcornfield@heraldnet.com

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Students from Explorer Middle School gather Wednesday around a makeshift memorial for Emiliano “Emi” Munoz, who died Monday, May 5, after an electric bicycle accident in south Everett. (Aspen Anderson / The Herald)
Community and classmates mourn death of 13-year-old in bicycle accident

Emiliano “Emi” Munoz died from his injuries three days after colliding with a braided cable.

Danny Burgess, left, and Sandy Weakland, right, carefully pull out benthic organisms from sediment samples on Thursday, May 1, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
‘Got Mud?’ Researchers monitor the health of the Puget Sound

For the next few weeks, the state’s marine monitoring team will collect sediment and organism samples across Puget Sound

Everett postal workers gather for a portrait to advertise the Stamp Out Hunger Food Drive on Wednesday, May 7, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Snohomish County letter carriers prepare for food drive this Saturday

The largest single-day food drive in the country comes at an uncertain time for federal food bank funding.

Everett
Everett considers ordinance to require more apprentice labor

It would require apprentices to work 15% of the total labor hours for construction or renovation on most city projects over $1 million.

Snohomish County prosecutor Kara Van Slyck delivers closing statement during the trial of Christian Sayre at the Snohomish County Courthouse on Thursday, May 8, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Jury deliberations begin in the fourth trial of former Everett bar owner

Jury members deliberated for about 2 hours before Snohomish County Superior Court Judge Millie Judge sent them home until Monday.

Christian Sayre sits in the courtroom before the start of jury selection on Tuesday, April 29, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Christian Sayre timeline

FEBRUARY 2020 A woman reports a sexual assault by Sayre. Her sexual… Continue reading

Commuters from Whidbey Island disembark their vehicles from the ferry Tokitae on Wednesday, Feb. 28, 2018 in Mukilteo, Wa.  (Andy Bronson / The Herald)
Bids for five new hybrid ferries come in high

It’s raising doubts about the state’s plans to construct up to five new hybrid-electric vessels with the $1.3 billion lawmakers have set aside.

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Christian Sayre walks out of the courtroom in handcuffs after being found guilty on two counts of indecent liberties at the end of his trial at the Snohomish County Courthouse on Monday, May 12, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Former bar owner convicted on two of three counts of sexual abuse

A jury deliberated for about 8 hours before returning guilty verdicts on two charges of indecent liberties Monday.

From left: Patrick Murphy, Shawn Carey and Justin Irish.
Northshore school board chooses 3 finalists in superintendent search

Shaun Carey, Justin Irish and Patrick Murphy currently serve as superintendents at Washington state school districts.

Paine Field Community Day returns Saturday, May 17

The youth-focused celebration will feature aircraft displays, talks with pilots and a variety of local food vendors.

FILE — Jet fuselages at Boeing’s fabrication site in Everett, Wash., Sept. 28, 2022. Some recently manufactured Boeing and Airbus jets have components made from titanium that was sold using fake documentation verifying the material’s authenticity, according to a supplier for the plane makers. (Jovelle Tamayo/The New York Times)
Boeing adding new space in Everett despite worker reduction

Boeing is expanding the amount of space it occupies in… Continue reading

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.