Winter storms threaten Camano’s lifeline, state warns

CAMANO ISLAND — One big winter storm could leave people unable to drive to and from Camano Island, so the state is planning to replace the Davis Slough bridge before it’s damaged by mounds of driftwood, high tides and flooding.

Davis Slough is located on a section of Highway 532 just west of the new Camano Gateway Bridge. The roadway there sits far too low for comfort, said state Department of Transportation project engineer Shane Spahr.

“Potentially, one strong storm could close the highway,” Spahr said.

The Davis Slough bridge, at 63 years old, isn’t a strong structure. During storms, large amounts of driftwood stack up against the bridge, he said. So, plans are in the works to raise and widen the highway there and replace the bridge.

The state plans to advertise the project early in 2013. The work is scheduled to begin next summer, with the estimated $26 million project to be completed in 2014. If all goes well, no major traffic delays are expected, Spahr said.

Project plans and pictures are to be displayed at a community open house from 4 to 7 p.m. Tuesday at the Camano Center, 606 Arrowhead Road on the island. Engineers plan to be on hand to answer questions and provide details about the project. No formal presentations are scheduled, so people are welcome to show up any time during the open house.

A good crowd is expected, Spahr said.

Julie Shallow, who has lived on Camano Island since 1999, plans to attend.

“I think the state will do the best they can to make this as painless as possible,” Shallow said. “There’s never a perfect time for construction. We will adjust our lives and commutes and just try to be as patient as possible. It sounds like it’s work that needs to be done.”

More than 15,000 people live on Camano Island, and Highway 532 is busy all the time, Spahr said.

To help drivers, the state plans first to build a section of new highway on the south side of the current bridge. In the summer of 2014, drivers will use the new section of highway at Davis Slough while the old is torn down and replaced.

Nearly a mile of highway will be raised 5 to 9 feet, and the shoulders, lanes and median will be widened in the area between Smith and Eide roads, Spahr said.

“Though the roadway shoulders will be very narrow during construction, we should be able to have two lanes of traffic open most of the time,” he said.

Gale Fiege: 425-339-3427; gfiege@heraldnet.com.

Open house

A community open house regarding an upcoming construction project on Highway 532 is set from 4 to 7 p.m. Tuesday at the Camano Center, 606 Arrowhead Road, Camano Island. For those unable to attend, more information is available at www.wsdot.wa.gov/projects/sr532/DavisSloughBridge.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Everett Historic Theater owner Curtis Shriner inside the theater on Tuesday, May 13, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Historic Everett Theatre sale on horizon, future uncertain

With expected new ownership, events for July and August will be canceled. The schedule for the fall and beyond is unclear.

Contributed photo from Snohomish County Public Works
Snohomish County Public Works contractor crews have begun their summer 2016 paving work on 13 miles of roadway, primarily in the Monroe and Stanwood areas. This photo is an example of paving work from a previous summer. A new layer of asphalt is put down over the old.
Snohomish County plans to resurface about 76 miles of roads this summer

EVERETT – As part of its annual road maintenance and preservation program,… Continue reading

City of Everett Engineer Tom Hood, left, and City of Everett Engineer and Project Manager Dan Enrico, right, talks about the current Edgewater Bridge demolition on Friday, May 9, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
How do you get rid of a bridge? Everett engineers can explain.

Workers began dismantling the old Edgewater Bridge on May 2. The process could take one to two months, city engineers said.

Smoke from the Bolt Creek fire silhouettes a mountain ridge and trees just outside of Index on Sept. 12, 2022. (Olivia Vanni / The Herald)
County will host two wildfire-preparedness meetings in May

Meetings will allow community members to learn wildfire mitigation strategies and connect with a variety of local and state agencies.

Helion's 6th fusion prototype, Trenta, on display on Tuesday, July 9, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Helion celebrates smoother path to fusion energy site approval

Helion CEO applauds legislation signed by Gov. Bob Ferguson expected to streamline site selection process.

Vehicles travel along Mukilteo Speedway on Sunday, April 21, 2024, in Mukilteo, Washington. (Ryan Berry / The Herald)
Mukilteo cameras go live to curb speeding on Speedway

Starting Friday, an automated traffic camera system will cover four blocks of Mukilteo Speedway. A 30-day warning period is in place.

Carli Brockman lets her daughter Carli, 2, help push her ballot into the ballot drop box on the Snohomish County Campus on Tuesday, Nov. 5, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Here’s who filed for the primary election in Snohomish County

Positions with three or more candidates will go to voters Aug. 5 to determine final contenders for the Nov. 4 general election.

Sound Transit approves contract to build Bothell bus facility

The 365,000-square-foot facility will be the heart of the agency’s new Stride bus rapid transit system, set to open in 2028.

One dead in Everett crash involving motorcycle and two vehicles

Police shut down the 10300 block of Evergreen Way in both directions during the multi-vehicle collision investigation.

Katie Wallace, left, checks people into the first flight from Paine Field to Honolulu on Friday, Nov. 17, 2023 in Everett, Washington. (Olivia Vanni / The Herald)
Executive order makes way for Paine Field expansion planning

Expansion would be a long-range project estimated to cost around $300 million.

A person pauses to look at an art piece during the Schack Art Center’s 50th anniversary celebration on Thursday, Oct. 10, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Everett to seek Creative District designation

The city hopes to grow jobs in the creative sector and access new grant funds through the state label.

Former Herald writer Melissa Slager’s new book was 14-year project

The 520-page historical novel “Contests of Strength” covers the 1700 earthquake and tsunami on Makah lands.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.