Comment: Sound Transit $35B cost overrun calls for state audit

The cost for ST3 exceeds current and future taxpayers’ ability to fund the three-county system.

By Bob Pishue / For The Herald

Sound Transit, the agency in charge of the three-county light rail program, recently announced a shocking, $35 billion cost overrun on its ST3 program, bringing total program costs to at least $185 billion; just for light rail.

The latest bad news is on top of numerous cost overruns and delays associated with the Sound Move, and ST2 plans. With approximately 3.4 million people in the district, the new cost estimates equate to about $55,000 for every man, woman, and child within the district.

This staggering taxpayer cost doesn’t even include long-term debt payments into the 2060s, where future generations will shoulder the burden for decisions made today.

Each of the three phases for Sound Transit has involved missed deadlines, cancelled projects and massive cost inflation. As Charles Prestrud of the Washington Policy Center put it in August, the continual “underestimating” of costs, “finally caught up to them,” implying that the billions in current tax revenue aren’t enough to absorb the magnitude of cost overruns.

The program had already announced runaway costs on its latest program, ST3. The West Seattle link’s cost estimates have doubled to more than $7 billion, despite only increasing transit use by 1 percent over the bridge. Officials were far off the mark when they told voters the Ballard Extension would cost $5.2 billion to build, as cost estimates more than doubled to a whopping $10.1 billion.

This is a familiar story across the country as well. In New York, the most expensive subways (per-mile) in the world are being built, while the rest of the system continues to be plagued by maintenance failures and delays. Estimates to bring the system to a state of good repair surpass $110 billion alone.

And who isn’t familiar with California’s high speed rail debacle, which recently had federal funding pulled due to project cost inflation and delays.

Some areas are cancelling rail altogether because of the extreme financial burden of not just building rail, but operating it. Near Minneapolis, Minn., officials have cancelled the Northstar Commuter Rail Line because of a staggering $116 subsidy per ticket. Officials plan to replace rail with bus service that will cost 86 percent less and serve more people.

In Portland, Ore., one local transportation expert said they should close their WES commuter rail line amid dismal ridership numbers and a $108 per ride taxpayer subsidy, and “admit they made a mistake” in building the commuter line in the first place.

Rail projects across the country continue to see massive cost increases. While Sound Transit did use expert review panels to check the feasibility of their programs, those processes haven’t ensured a well-run rail program. Ultimately, the Washington state Auditor’s Office or JLARC (legislative auditor) should step in and conduct a comprehensive performance audit to examine the causes of the overruns and delays.

This is why infrastructure and transit programs should have strong controls in place to ensure financial accountability. Tying funding to performance measures, empowering oversight committees, and making transit board positions directly elected (rather than appointed) would go a long way to ensuring taxpayers receive what they are promised.

Bob Pishue is a policy analyst for the Mountain States Policy Center, an independent research organization based in Idaho, Montana, Eastern Washington and Wyoming. Online at mountainstatespolicy.org.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Opinion

FILE — COVID19 vaccines are prepared by a nurse in a mobile vaccine clinic at a senior living facility in McMinnville, Ore., Oct. 6, 2021. A dozen public health experts, along with seven former high-ranking officials, are describing the CDC under the leadership of Robert F. Kennedy Jr. as badly wounded and fast losing its legitimacy, portending harsh consequences for public health. (Alisha Jucevic/The New York Times)
Editorial: Western states take only course on vaccine access

The move assures access to covid vaccines but can’t replace a national policy vital to public health.

toon
Editorial cartoons for Saturday, Sept. 13

A sketchy look at the news of the day.… Continue reading

Comment: State agency’s cut would limit access to dialysis

The Health Care Authority is cutting Medicare reimbursement for kidney dialysis, affecting patients and costs.

Comment: Sound Transit $35B cost overrun calls for state audit

The cost for ST3 exceeds current and future taxpayers’ ability to fund the three-county system.

Sports Dad: The smallest things keep a rec league coach going

It’s goofy team names and little personal victories and parents who care enough to get kids on the field.

Mason Rutledge
Forum: Agree or not with Charlie Kirk, he fed need for discourse

Regardless of where we stand on issues, we have to find a path toward discussion and understanding.

The Buzz: What Charlie Kirk got right about our rights

Freedom of speech was just that to the conservative activist. He invited a sharing of perspectives. Here’s ours:

Comment: Cash grants do help children and families in poverty

A recent study, misinterpreted by many, does not argue against providing aid for low-income families.

toon
Editorial cartoons for Friday, Sept. 12

A sketchy look at the news of the day.… Continue reading

An image taken from a website attack advertisement targeting Everett school board member Anna Marie Jackson Laurence. (laurenceletusdown.com)
Editorial: Attack ads an undeserved slander of school official

Ads against an Everett school board candidate are a false and unfair attack on a public servant.

Pedestrians using umbrellas, some Washingtonians use them, as they cross Colby Avenue under pouring rain on Tuesday, Nov. 28, 2017 in Everett, Wa. The forecast through Saturday is cloudy with rain through Saturday. (Andy Bronson / The Herald)
Editorial: Speed limit reductions a good start on safety

Everett is reducing speed limits for two streets; more should follow to save pedestrian lives.

Gov. Bob Ferguson and Rep. Rick Larsen talk during a listening session with with community leaders and families addressing the recent spending bill U.S. Congress enacted that cut Supplemental Nutrition Assistance Program funding by 20% on Thursday, Aug. 21, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Editorial: Work to replace what was taken from those in need

The state and local communities will have to ensure food security after federal SNAP and other cuts.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.