Pipeline delays cost builder millions, risking contract loss

By DAVID PITT

Associated Press

DES MOINES, Iowa — The completion of the Dakota Access oil pipeline has been delayed after the U.S. Army declined to grant an easement for the final few thousand feet under a Missouri River reservoir in North Dakota pending further study. Pipeline company Energy Transfer Partners originally was expected to finish the pipeline before the end of this year, but the Army’s move likely delays it by several months. That will be costly to the Dallas-based company, but industry experts say it’s unlikely to kill the project completely. Here’s a look at some of the ways the delay could impact the pipeline:

WHAT IS THE FINANCIAL IMPACT?

Delays have already cost Energy Transfer Partners more than $450 million, the company said in court documents last month, and continued delays cost $83.3 million per month. The Army Corps of Engineers isn’t very sympathetic saying in court filings that the company knowingly began construction prior to receiving all necessary approvals “at its own risk.”

HOW LONG OF A DELAY IS LIKELY?

The Army’s decision likely halts progress on the project until after President-elect Donald Trump takes office on Jan. 20. Trump, who supports the pipeline and holds stock in Energy Transfer Partners, hasn’t said whether he will try to overturn the Army’s decision. Dakota Access has said tunneling under Lake Oahe is likely to take at least 60 days once digging begins and some industry experts say it could take as long as 90 days. So, if the Trump administration were to immediately reverses course and authorize construction, the pipeline likely wouldn’t be completed until April or May.

COULD DELAYS DOOM THE PROJECT?

Dakota Access attorney William Scherman said in a Nov. 15 document filed in U.S. District Court in Washington that further delay could “threaten the very survival” of the $3.8 billion privately funded project, which would carry North Dakota oil through the Dakotas and Iowa to a shipping point in Illinois. He said the company has long-term transportation contracts with nine shippers indicating the pipeline will be in service by Jan. 1, 2017, and the shippers have the right to terminate those contracts if terms aren’t met. Industry experts say the contracts likely have several target dates including project start date, in-service date and differing start dates for the nine shippers. It’s difficult to say when they might walk, but shippers are unlikely to cancel the deal easily because most are probably shipping by rail now at a cost of $8 or $9 a barrel, while the pipeline is likely to cost much less, more like $5 or $6 a barrel, said Skip York, a vice president at energy industry consultant Wood Mackenzie.

COULDN’T SHIPPERS SEEK TO RENEGOTIATE IF CONTRACTS EXPIRE?

Yes. When Dakota Access signed on shippers in 2014, crude oil prices were at $95 a barrel, but they’ve averaged around $45 to $50 a barrel recently, which could be in incentive for some to use the delay as a reason to want to open up the terms for renegotiation. Shippers say they’re not concerned yet. Hess Corp. spokesman John Roper says the company can just continue using current transportation methods. Dennis Nuss, a spokesman for petroleum company Phillips 66, which owns a 25 percent stake in the pipeline, expressed confidence the project will be finished early next year.

ARE THERE OTHER OBSTACLES TO THE PIPELINE?

Yes. In Iowa, about a dozen landowners forced to allow the pipe on their farmland through a state eminent domain law are pressing forward on their own legal challenge. They contend, among other arguments, that a 2006 Iowa law prohibits an industry from using eminent domain to take agricultural land. They’re asking a judge to throw out what they consider to be illegal easements granted by the Iowa Utilities Board. If they win, they want the pipeline dug up and removed. “Dakota Access knew how to put it in, so it must know how to take it out,” they said in court documents.

A judge is set to hear arguments on Dec. 15

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Business

Dave Somers makes a speech after winning the Henry M. Jackson Award on Tuesday, April 22, 2025 in Tulalip, Washington. (Olivia Vanni / The Herald)
County Executive Dave Somers: ‘It’s working together’

Somers is the recipient of the Henry M. Jackson Award from Economic Alliance Snohomish County.

Mel Sheldon makes a speech after winning the Elson S. Floyd Award on Tuesday, April 22, 2025 in Tulalip, Washington. (Olivia Vanni / The Herald)
Mel Sheldon: Coming up big for the Tulalip Tribes

Mel Sheldon is the winner of the Elson S. Floyd Award from Economic Alliance Snohomish County

Paul Roberts makes a speech after winning the Chair’s Legacy Award on Tuesday, April 22, 2025 in Tulalip, Washington. (Olivia Vanni / The Herald)
Paul Roberts: An advocate for environmental causes

Roberts is the winner of the newly established Chair’s Legacy Award from Economic Alliance Snohomish County.

Craig Skotdal makes a speech after winning on Tuesday, April 22, 2025 in Tulalip, Washington. (Olivia Vanni / The Herald)
Craig Skotdal: Helping to breathe life into downtown Everett

Skotdal is the recipient of the John M. Fluke Sr. award from Economic Alliance Snohomish County

Laaysa Chintamani speaks after winning on Tuesday, April 22, 2025 in Tulalip, Washington. (Olivia Vanni / The Herald)
Laasya Chintamani: ‘I always loved science and wanted to help people’

Chintamani is the recipient of the Washington STEM Rising Star Award.

The Coastal Community Bank branch in Woodinville. (Contributed photo)
Top banks serving Snohomish County with excellence

A closer look at three financial institutions known for trust, service, and stability.

Image from Erickson Furniture website
From couch to coffee table — Local favorites await

Style your space with the county’s top picks for furniture and flair.

2025 Emerging Leader winner Samantha Love becomes emotional after receiving her award on Tuesday, April 8, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Samantha Love named 2025 Emerging Leader for Snohomish County

It was the 10th year that The Herald Business Journal highlights the best and brightest of Snohomish County.

2025 Emerging Leader Tracy Nguyen (Olivia Vanni / The Herald)
Tracy Nguyen: Giving back in her professional and personal life

The marketing director for Mountain Pacific Bank is the chair for “Girls on the Run.”

2025 Emerging Leader Kellie Lewis (Olivia Vanni / The Herald)
Kellie Lewis: Bringing community helpers together

Edmonds Food Bank’s marketing and communications director fosters connections to help others.

2025 Emerging Leader Christina Strand (Olivia Vanni / The Herald)
Christina Strand: Helping people on the move

Community engagement specialist believes biking, walking and public transit can have a positive impact.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.