Hanford vitrification plant may cost more than $12.2 billion

RICHLAND — The Department of Energy may not be able to complete the Hanford vitrification plant for the projected $12.2 billion, according to an internal DOE document.

The $12.2 billion figure is at risk due to uncertainties in congressional funding for the project, increased cost growth out

pacing savings and delays in resolving technical waste mixing issues, according to a briefing document by the Construction Project Review team.

However, a “refined approach to treating the small fraction” of the most difficult waste, which includes plutonium, could help curb cost growth, the document indicated. That could mean finishing the design of the plant to treat the majority of the waste and then continuing to work on studies for treating the most difficult waste.

DOE has not released the briefing document, considering it “predecisional,” but the document has been circulated outside Hanford by others. A formal report on the team’s most recent review has not been written and could differ from the document prepared to brief officials after the team’s latest visit to Hanford.

The team of industry, academic and DOE members assesses progress and potential problems on the project and advises DOE about every six months.

The document said that if Congress continues to provide the budgets DOE has outlined, the review team has identified a potential cost overrun of $800 million to $900 million.

However, that might be offset by $350 million saved if DOE proceeds with a phased commissioning of the plant, preparing some buildings to operate and then moving on to others, rather than commissioning the entire plant at once, according to the document. Labor costs could be lower and lessons learned commissioning the first buildings could save money on later buildings.

That also could lead to earlier operation of the part of the plant treating low activity radioactive waste.

The shortfall of up to $900 million is based on strong Hanford budgets at a time when Congress is looking to cut federal budgets. DOE has asked for $840 million for the vitrification plant in the fiscal year that starts Oct. 1, but the House has passed a budget that cuts that to $740 million. A final budget has yet to be approved.

“Funding uncertainty is the major project risk,” the document said. It also could affect the schedule of the plant, which is required to begin operating in 2019.

The vitrification plant project was planned on a steady budget of $690 million a year, but DOE now wants to spend more money in upcoming years and less money in out years.

The project also is continuing to struggle to prove whether the most difficult of Hanford’s waste can be kept well mixed at the plant to prevent problems, including the remove possibility of an uncontrolled chain reaction if too much plutonium settles out or a buildup of explosive gases.

The vitrification plant, or Waste Treatment Plant, is planned to treat for disposal all of Hanford’s high level radioactive waste and much of its low activity radioactive waste now held in underground tanks at Hanford. The waste, left from the past production of plutonium at Hanford, totals 56 million gallons.

“Significant progress has been achieved on some technical issues, but overall progress is slower than expected,” the document said.

DOE is addressing the issues with computer modeling and with a planned large-scale mixing demonstration.

However, the team said that waste in a small number of tanks is driving criticality concerns and the design for the mixing system. Hanford has 177 underground tanks, most of which still hold waste.

“The expectation that WTP must be demonstrated at design completion to be able to treat all of the waste puts the WTP project at risk,” the document said.

Bechtel National, the DOE contractor on the project, has said previously that when the plant begins operating, the less-challenging waste will be treated first. The plant as designed will be able to treat the vast majority of the high-level waste held in underground tanks now, but additional testing is needed to prove it can treat the remainder of the waste, Bechtel has said.

“As the Construction Project Review team noted, our project management team has made significant progress on the project and in resolving issues,” DOE said in a statement. “However, the Waste Treatment Plant project is a challenging and complex endeavor, and these types of reviews provide regular, independent feedback that enables the department to continuously improve its management of this important project.”

The document did find positive steps on the project. It has been effectively managed and led and the majority of previous recommendations are closed, it said.

“Significant progress towards completing the project has resulted over the past two years, primarily due to the actions taken by the new management and leadership on both the contractor and federal sides,” the document said.

The projected cost of $12.2 billion for the vitrification plant has held steady since fall 2006 when a comprehensive look at the cost and schedule of the plant was completed.

Former Energy Secretary Samuel Bodman had called for a validated cost and schedule after it became clear that the estimated $5.5 billion cost from March 2003 was far too low and that the plant would not be operating by a legal deadline then of 2011.

The increase to $12.2 billion was blamed on many factors, including rising steel costs, the need to revise earthquake design standards, technical problems, the lack of suppliers certified to perform nuclear-quality work, underestimating costs of a one-of-a-kind plant, management problems and inadequate Congressional budget support.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Cars drive along Cathcart Way next to the site of the proposed Eastview Village development that borders Little Cedars Elementary on Wednesday, May 7, 2025 in unincorporated Snohomish, Washington. (Olivia Vanni / The Herald)
Former engineer: Snohomish County rushed plans for Eastview development

David Irwin cited red flags from the developers. After he resigned, the county approved the development that’s now stalled with an appeal

Outside of the Madrona School on Monday, Aug. 26, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Sewer district notifies Edmonds schools of intent to sue

The letter of intent alleges the school district has failed to address long-standing “water pollution issues” at Madrona K-8 School.

Everett
Man stabbed in face outside Everett IHOP, may lose eye

Police say the suspect fled in the victim’s car, leading officers on a 6-mile chase before his arrest.

A person walks up 20th Street Southeast to look at the damage that closed the road on Wednesday, Nov. 20, 2024 in Lake Stevens, Washington. (Olivia Vanni / The Herald)
WA delegation urges Trump to reconsider request for bomb cyclone aid

The Washington state congressional delegation urged President Donald Trump on… Continue reading

Aaron Weinstock uses an x-ray machine toy inside the Imagine Children Museum on Tuesday, Dec. 3, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Imagine Children’s Museum $250k grant reinstated following federal court order

The federal grant supports a program that brings free science lessons to children throughout rural Snohomish County.

Snohomish County 911 Executive Director Kurt Mills talks about the improvements made in the new call center space during a tour of the building on Tuesday, May 20, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
New 911 center in Everett built to survive disaster

The $67.5 million facility brings all emergency staff under one roof with seismic upgrades, wellness features and space to expand.

Everett
Five arrested in connection with Everett toddler’s 2024 overdose death

More than a year after 13-month-old died, Everett police make arrests in overdose case.

Madison Family Shelter Family Support Specialist Dan Blizard talks about one of the pallet homes on Monday, May 19, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Madison Family Shelter reopens after hiatus

The Pallet shelter village, formerly Faith Family Village, provides housing for up to eight families for 90 days.

Brian Murril, who started at Liberty Elementary as a kindergartner in 1963, looks for his yearbook photograph during an open house for the public to walk through the school before its closing on Thursday, May 29, 2025 in Marysville, Washington. (Olivia Vanni / The Herald)
Locals say goodbye to Marysville school after 74 years

Liberty Elementary is one of two schools the Marysville School District is closing later this year to save costs.

U.S. Sen. Patty Murray speaks at a round table discussion with multiple Snohomish County agencies about the Trump administrator restricting homelessness assistance funding on Thursday, May 29, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Sen. Murray hears from county homelessness assistance providers

In early May, Snohomish County sued the Trump administration for putting unlawful conditions on $16.7M in grant funding.

Gov. Bob Ferguson, at podium, goes to shake hands with state Sen. Noel Frame, D-Seattle, at the signing of a bill to make clergy mandatory reporters of child abuse and neglect, on May 2, 2025 in Olympia. At center is Mary Dispenza, a founding member of the Catholic Accountability Project. (Photo by Jerry Cornfield/Washington State Standard)
Bishops sue to overturn new WA law requiring clergy to report child abuse

They argue it is unconstitutional to force Catholic priests to divulge information learned in confession.

DNR removes derelict barge from Spencer Island

The removal was done in partnership with state Fish and Wildlife within a broader habitat restoration project.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.