Construction crews work in what will be the main hallway of the two-story building filled with classrooms at Park Place Middle School on Monday in Monroe. The project is currently in its first phase and is set to be completed by 2018 with reconstruction of classrooms, fields, administration office, gymnasium and cafeteria. (Daniella Beccaria / The Herald)

Construction crews work in what will be the main hallway of the two-story building filled with classrooms at Park Place Middle School on Monday in Monroe. The project is currently in its first phase and is set to be completed by 2018 with reconstruction of classrooms, fields, administration office, gymnasium and cafeteria. (Daniella Beccaria / The Herald)

Park Place Middle School remodel in Monroe taking shape

MONROE — Walls are nearly complete in the classroom wing. The roof is done on the new auxiliary gym. Updated athletic fields have been readied for the installation of artificial turf.

The remodel of Park Place Middle School on Main Street is well underway.

Work started in June on the $69 million project, the largest piece of a $110.9 million bond passed by voters in 2015.

Demolition of the old school buildings began just days after classes let out for the summer, said Erin Zacharda, district spokeswoman.

The project is expected to be done by the beginning of the 2018 school year.

Plans are to renovate or rebuild the gym, commons, one entire two-story building and portions of another. New classrooms are being added along with a track and field. School security also is being improved.

The construction is broken into phases so students can continue going to class during the work. There are 767 students at Park Place, which is for grades 6, 7 and 8.

About half of the old school was torn down during the summer. Classroom space was added in the other half using temporary walls to divide the library. The district also brought in portables.

Once the first half of the school is rebuilt, classes will move over there and the portables will remain in use until the rest of the campus is finished, Zacharda said.

Other bond projects include new ball fields at Monroe High School, the last of which should be finished this spring, and overhauls of Salem Woods and Frank Wagner elementaries. The elementaries are scheduled for construction starting this summer, including the addition of new buildings and classrooms. Work should be done by fall 2018.

Hidden River Middle School also is slated for an expansion, though not as extensive as Park Place. The $18.2 million project would improve security, build new science, art and technology classrooms, expand the kitchen and add a track, fields and play areas.

The bond is paying for other, smaller projects, among them replacing roofs, updating parking, resurfacing play areas, upgrading lighting and improving access for people with limited mobility. District officials also plan to improve security with new cameras, keyless entry and better lighting at schools.

Kari Bray: 425-339-3439; kbray@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Founder of Faith Lutheran Food Bank Roxana Boroujerd helps direct car line traffic while standing next to a whiteboard alerting clients to their date of closing on Friday, April 25, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Faith Food Bank to close, replacement uncertain

The food bank’s last distribution day will be May 9, following a disagreement with the church over its lease.

Anna Marie Laurence speaks to the Everett Public Schools Board of Directors on Thursday, May 1, 2025 in Everett, Washington. (Will Geschke / The Herald)
Everett school board selects former prosecutor to fill vacancy

Anna Marie Laurence will fill the seat left vacant after Caroline Mason resigned on March 11.

The Edmonds School Board discusses budget cuts during a school board meeting on Tuesday, April 15, 2025 in Edmonds, Washington. (Olivia Vanni / The Herald)
Edmonds school board approves potential staff cuts, eyes legislation

The district is awaiting action from Gov. Bob Ferguson on three bills that could bridge its $8.5 million deficit.

Janet Garcia walks into the courtroom for her arraignment at the Snohomish County Courthouse on Monday, April 22, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Everett mother found competent to stand trial in stabbing death of 4-year-old son

A year after her arraignment, Janet Garcia appeared in court Wednesday for a competency hearing in the death of her son, Ariel Garcia.

Logo for news use featuring the municipality of Brier in Snohomish County, Washington. 220118
Brier police levy fails; officials warn current staffing is not sustainable

With no new funding, officials say the department will remain stretched thin.

Fosse will not seek reelection; 2 candidates set to run for her seat

Mason Rutledge and Sam Hem announced this week they will seek the District 1 City Council position.

Lynnwood
Lynnwood police arrest two males in shooting at Swift bus

Man, 19, is booked for investigation of attempted murder. 17-year-old held at Denney Juvenile Justice Center on similar charges.

K-POP Empire store owners Todd Dickinson and Ricky Steinlars at their new store location on Thursday, April 17, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Lynnwood K-pop store wary of new tariffs

Much of the store’s merchandise, which arrives from China and South Korea, is facing new import fees.

Two-alarm fire destroys storage units, vehicles in South Everett

Nearly 60 firefighters from multiple agencies responded to the blaze. No initial word on a cause.

Christian Sayre sits in the courtroom before the start of jury selection on Tuesday, April 29, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Christian Sayre timeline

FEBRUARY 2020 A woman reports a sexual assault by Sayre. Her sexual… Continue reading

Snohomish County prosecutor Martha Saracino delivers her opening statement at the start of the trial for Christian Sayre at the Snohomish County Courthouse on Monday, May 5, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Opening statements begin in fourth trial of former bar owner

A woman gave her account of an alleged sexual assault in 2017. The trial is expected to last through May 16.

Lynnwood
Deputies: 11-year-old in custody after bringing knives to Lynnwood school

The boy has been transported to Denney Juvenile Justice Center. The school was placed in a modified after-school lockdown Monday.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.