As Boeing halts Max output, Airbus can’t build jets fast enough

The European planemaker has had to offer a wide range of cabin layouts that has complicated assembly.

By Siddharth Philip / Bloomberg News

LONDON — As the Boeing Co. halts production of its beleaguered 737 Max, global rival Airbus is grappling with a very different problem: speeding output of its rival narrow-body.

So-called “stretch” versions of the A320neo jet have sparked an order frenzy as airlines snap them up to replace costly twin-aisle planes on longer routes or cram in seats on shorter legs. But to achieve that flexibility Airbus has had to offer a wide range of cabin layouts that’s made assembly far more complex.

Slower build rates on the top-priced A321 variant mean that the European company needs to lift deliveries 75% this month compared with November to meet full-year production targets. It’s a vital challenge for Airbus — not only to consolidate its advantage over a flailing Boeing, but also to maximize returns from its most expensive narrow-bodies as demand peaks for even more-lucrative wide-body models.

“The A321 matters because as a stretch it should be by far the highest-margin aircraft of the Airbus narrow-bodies,” said Sash Tusa, an analyst at Agency Partners in London. The increased popularity of single-aisle planes on longer routes could mean they come to account for three-quarters of the total value of planes delivered in a given year, up from 50% previously, he added.

Airbus is targeting 860 deliveries across its airliner range for 2019, 20 fewer than the initial goal after the company acknowledged in October that its plants were behind schedule. Each missed jet will wipe at least 10 million euros ($11 million) off profit, Citi Research analyst Charles Armitage estimates.

While that’s a big hit, the delays could have wider ramifications — potentially stymieing future orders for a model that’s already booked out until 2024 with a backlog of 6,193 planes.

Airbus Chief Executive Officer Guillaume Faury has already said that A320-series output won’t properly be back on track until 2021, by which time production is due to reach 63 aircraft a month from 60 now.

Responding to questions from Bloomberg, Airbus said meeting the 135-plane December goal will be “challenging” but that the company is counting on jets that were already close to complete at the end of last month to swell handovers.

Demand for the A321neo planes has been “much higher than we originally anticipated,” a spokesman said, with a jet that once accounted for just 10% of A320-series demand now constituting 40% of sales and growing.

Orders got a further shot in the arm with the launch of an extra-long-range or XLR upgrade in June. United Airlines this month agreed to buy 50 of the planes, joining a customer base that also includes American Airlines Group Inc. and JetBlue Airways Corp.

To be sure, Airbus has faced a year-end race to hit delivery targets before, with assembly-line staff working through the holidays to hand over 127 jets in both December 2018 and 2017.

Those delays were focused on glitches with jet engines at suppliers. This December’s challenge is a different one, concerning the pace of cabin installation at Airbus’s A321 assembly site in Hamburg.

At the heart of the holdups is the Airbus Cabin Flex option that allows airlines to choose from A321 layouts ranging from a high-density economy configuration accommodating 240 people at India’s Indigo to 102 seats in four classes — including flat-bed berths, as American has specified.

The combinations require changes to the location, layout and number of emergency exits and even galleys and toilets. Airbus says it has hired over 1,000 people for the Hamburg line and added 20 robots to improve efficiency.

The long-range A321LR entered service a year ago, while the XLR, launched at the Paris Air Show in June, is set for its first delivery in 2023. The new plane, with a range of 4,700 nautical miles, has a list price of more than $140 million, compared with $108 million for the baseline A320neo.

Airbus’s long-term fix should come in the form of a new assembly line, likely to be located on the site of an A380 superjumbo facility in Toulouse, France, that’s due to be closed in 2021 as the double-decker ends production. The site will most likely be devoted to the A321neo and its variants in order to ease the pressure on its Hamburg plant.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Business

Lily Lamoureux stacks Weebly Funko toys in preparation for Funko Friday at Funko Field in Everett on July 12, 2019.  Kevin Clark / The Herald)
Everett-based Funko: ‘Serious doubt’ it can continue without new owner or funding

The company made the statements during required filings to the SEC. Even so, its new CEO outlined his plan for a turnaround.

A runner jogs past construction in the Port of Everett’s Millwright District on Tuesday, July 15, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Port of Everett finalizes ‘conservative’ 2026 budget

Officials point to fallout from tariffs as a factor in budget decisions.

The Verdant Health Commission holds a meeting on Oct. 22, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Verdant Health Commission to increase funding

Community Health organizations and food banks are funded by Swedish hospital rent.

Sound Sports Performance & Training owner Frederick Brooks inside his current location on Oct. 30, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Lynnwood gym moves to the ground floor of Triton Court

Expansion doubles the space of Sound Sports and Training as owner Frederick Brooks looks to train more trainers.

The entrance to EvergreenHealth Monroe on Monday, April 1, 2019 in Monroe, Wash. (Andy Bronson / The Herald)
EvergreenHealth Monroe buys medical office building

The purchase is the first part of a hospital expansion.

The new T&T Supermarket set to open in November on Oct. 20, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
TT Supermarket sets Nov. 13 opening date in Lynnwood

The new store will be only the second in the U.S. for the Canadian-based supermarket and Asian grocery.

Judi Ramsey, owner of Artisans, inside her business on Sept. 22, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Artisans PNW allows public to buy works of 100 artists

Combo coffee, art gallery, bookshop aims to build business in Everett.

The Port of Everett’s new Director of Seaport Operations Tim Ryker on Oct. 14, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Port of Everett names new chief of seaport operations

Tim Ryker replaced longtime Chief Operating Officer Carl Wollebek, who retired.

The Lynnwood City Council listens to a presentation on the development plan for the Lynnwood Event Center during a city council meeting on Oct. 13, 2025 in Lynnwood, Washington. (Olivia Vanni / The Herald)
Lynnwood City Council approves development of ‘The District’

The initial vision calls for a downtown hub offering a mix of retail, events, restaurants and residential options.

Everly Finch, 7, looks inside an enclosure at the Reptile Zoo on Aug. 19, 2025 in Monroe, Washington. (Olivia Vanni / The Herald)
Monroe’s Reptile Zoo to stay open

Roadside zoo owner reverses decision to close after attendance surge.

Trade group bus tour makes two stops in Everett

The tour aimed to highlight the contributions of Washington manufacturers.

Downtown Everett lumberyard closes after 75 years

Downtown Everett lumber yard to close after 75 years.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.