I-5 HOV lane, Highway 529 interchange work to start this year

WSDOT awarded the $123.1 million project’s design-build contract to Guy F. Atkinson Construction.

A little later and more costly than originally envisioned, the state has a contractor to build a carpool lane on northbound Interstate 5 and redo the Highway 529 interchange in Marysville.

The Washington State Department of Transportation awarded the $123.1 million project’s design-build contract to Renton-based Guy F. Atkinson Construction. Work is expected to begin later this year and finish in 2025.

“This work will improve mobility for highway users, ease congestion and provide more access to and from Marysville,” Atkinson senior project manager Reggie Wageman said in a news release. “We intend to build a project that meets the needs of the community, minimizes effects on travelers and looks for efficiencies in design and construction to provide the best value for taxpayers.”

When first proposed in 2015, the state’s estimated price tag was around $85 million.

Higher costs for labor, land and supplies raised the cost since then.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The project has three parts:

  • Extending the northbound high occupancy vehicle (HOV) lane from U.S. 2 in Everett to south of Highway 529 in Marysville;
  • A northbound ramp from I-5 to Highway 529; and
  • A ramp from Highway 529 to southbound I-5.

Funding problems were identified in 2020. At the time, state DOT staff warned work on the southbound ramp from Highway 529 to I-5 could be delayed. That element of the total project was expected to be $7.2 million over the budget. A major reason for that cost increase is the state had to offset wetland lost during construction by paying several million dollars to restore about 11.3 acres where saltwater and freshwater mix in the Snohomish River near Port Gardner.

Then construction labor and materials got costlier.

The Legislature’s 16-year, nearly $17 billion Move Ahead WA transportation package plugged the funding gap with $30.5 million.

The Highway 529/I-5 interchange project includes a northbound ramp from the freeway onto the highway into Marysville, and a southbound ramp from the highway to the interstate. A funding gap in its original budget was plugged by the Legislature’s 16-year nearly $17 billion transportation package. (Washington State Department of Transportation)

The Highway 529/I-5 interchange project includes a northbound ramp from the freeway onto the highway into Marysville, and a southbound ramp from the highway to the interstate. A funding gap in its original budget was plugged by the Legislature’s 16-year nearly $17 billion transportation package. (Washington State Department of Transportation)

Redoing the interchange is considered a critical transportation project for Marysville to circumvent the train tracks that run through town and can cut off travelers from I-5.

Currently there is no southbound access to I-5 from Highway 529, also called State Avenue through Marysville. Instead, drivers can get to the freeway from Fourth Street which takes them across the train tracks. When freight rolls through, it can hold up traffic for minutes at a time.

Marysville Mayor Jon Nehring credited state Rep. Emily Wicks, and state Sens. Marko Liias and June Robinson for the project’s full funding.

“To take that to the back of the line would have been devastating regionally,” he said.

Extending the HOV lane north could help some of the estimated 66,000 daily commuters cruise past the backups that form at the U.S. 2 interchange, off-ramp to Marine View Drive and across the Snohomish River Bridge. Nearly 25% of those northbound vehicles could use the HOV lane, according to state data.

Crews will make the existing three general purpose lanes smaller and move them to the right, and restripe the roadway to add the HOV lane. Shoulders on both sides of I-5 will be more narrow.

Construction is scheduled to begin later this year and wrap in 2025.

“Once we give the contractor notice to proceed, then they’ll start working on a project schedule and timeline. That includes completing design work on the interchange,” WSDOT spokesperson Kris Olsen said in an email.

WSDOT doesn’t expect the four-month concrete delivery strike to affect the project timeline since construction has not started and Teamsters Local 174 offered to return to work.

Have a question? Call 425-339-3037 or email streetsmarts@heraldnet.com. Please include your first and last name and city of residence.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Jonathon DeYonker, left, helps student Dominick Jackson upload documentary footage to Premier at The Teen Storytellers Project on Tuesday, April 29, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Everett educator provides tuition-free classes in filmmaking to local youth

The Teen Storyteller’s Project gives teens the chance to work together and create short films, tuition-free.

Edmonds Activated Facebook group creators Kelly Haller, left to right, Cristina Teodoru and Chelsea Rudd on Monday, May 5, 2025 in Edmonds, Washington. (Olivia Vanni / The Herald)
‘A seat at the table’: Edmonds residents engage community in new online group

Kelly Haller, Cristina Teodoru and Chelsea Rudd started Edmonds Activated in April after learning about a proposal to sell a local park.

Everett
Man arrested in connection with armed robbery of south Everett grocery store

Everet police used license plate reader technology to identify the suspect, who was booked for first-degree robbery.

Anna Marie Laurence speaks to the Everett Public Schools Board of Directors on Thursday, May 1, 2025 in Everett, Washington. (Will Geschke / The Herald)
Everett school board selects former prosecutor to fill vacancy

Anna Marie Laurence will fill the seat left vacant after Caroline Mason resigned on March 11.

Lynnwood
Lynnwood woman injured in home shooting; suspect arrested

Authorities say the man fled after the shooting and was later arrested in Shoreline. Both he and the Lynnwood resident were hospitalized.

Swedish Edmonds Campus on Wednesday, Aug. 7, 2024 in Edmonds, Washington. (Olivia Vanni / The Herald)
Data breach compromises info of 1,000 patients from Edmonds hospital

A third party accessed data from a debt collection agency that held records from a Providence Swedish hospital in Edmonds.

Construction continues on Edgewater Bridge along Mukilteo Boulevard on Wednesday, Jan. 22, 2025. (Olivia Vanni / The Herald)
Everett pushes back opening of new Edgewater Bridge

The bridge is now expected to open in early 2026. Demolition of the old bridge began Monday.

Jacquelyn Jimenez Romero / Washington State Standard
The Washington state Capitol on April 18.
Why police accountability efforts failed again in the Washington Legislature

Much like last year, advocates saw their agenda falter in the latest session.

A scorched Ford pickup sits beneath a partially collapsed and blown-out roof after a fire tore through part of a storage facility Monday evening, on Tuesday, May 6, 2025, in Everett. (Aspen Anderson / The Herald)
Two-alarm fire destroys storage units, vehicles in south Everett

Nearly 60 firefighters from multiple agencies responded to the blaze.

Christian Sayre sits in the courtroom before the start of jury selection on Tuesday, April 29, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Christian Sayre timeline

FEBRUARY 2020 A woman reports a sexual assault by Sayre. Her sexual… Continue reading

Snohomish County prosecutor Martha Saracino delivers her opening statement at the start of the trial for Christian Sayre at the Snohomish County Courthouse on Monday, May 5, 2025 in Everett, Washington. (Olivia Vanni / The Herald)
Opening statements begin in fourth trial of former bar owner

A woman gave her account of an alleged sexual assault in 2017. The trial is expected to last through May 16.

Lynnwood
Deputies: 11-year-old in custody after bringing knives to Lynnwood school

The boy has been transported to Denney Juvenile Justice Center. The school was placed in a modified after-school lockdown Monday.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.